← Back
BuildNYC
Elevator apt, semi-fireproof with stores
1073 SUMMIT AVENUE
BRONX · BIN 2003492
💬 Discuss this project
2011Year Built
10Stories
D7Building Class
R7-1Zoning
98,555 sfGross Floor Area
106Units
LL97 CoveredRent Stabilized7 Active Violations 4 likely answered ▸
Elevator apt, semi-fireproof with stores · Owner of record: Summit Avenue Development · 21,875 sf lot · 4.51 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Whole building & multi-floor projectsStagg STAGG GROUP5 filings
RoofStagg1p · 2 filings
Floor 2Sta G G G R O Up1 filing
Floor 1Sta G G G R O Up2p · 7 filings · 13 docs
CellarSta G G G R O Up1 filing · 13 docs
Site & exterior4-point suspended scaffold1 filing · 3 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
RYTY Home Builders11207/08/2026
Stagg Group503/22/2026
Summit Avenue Development303/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Marin Architects P C3603/21/2026
Consolidated Scaffold Bridge1203/21/2026
KM Associates of New York103/21/2026
Synergy Building Consultants103/21/2026
K & M Associates103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Be Bronx BuildersGeneral Contractor1007/08/2026
Ariana ContractingFire Protection707/08/2026
Be Bronx BuildersScaffold707/08/2026
Consolidated ScaffoldingScaffold707/08/2026
Junior Carter MechanicalPlumbing607/08/2026
AL Electrical GroupElectrical303/21/2026
CS BridgeScaffold307/08/2026
The Right Connection P&HFire Protection207/08/2026
Precision Hoist & Scaffo*Scaffold107/08/2026
Minkuk KimElectrical103/21/2026
AL Electrical GroupElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
KZ Engineering4665105/12/2023
Dominick R. Pilla13002408/15/2022
Twin Peaks317106/11/2021
Building Lifecycle
All (215)Filed (38)Permit Issued (33)Signed Off (13)Violation (60)Inspection (7)Objection (34)Special Inspection (30)
06/12/2026
Violation issued (HPD, closed)
C
06/12/2026
Violation issued (HPD, closed)
C
06/12/2026
Violation issued (HPD, open)
C
04/27/2026
Violation issued (HPD, closed)
B
04/27/2026
Violation issued (HPD, closed)
C
02/04/2026
Violation issued (HPD, closed)
B
02/04/2026
Violation issued (HPD, closed)
B
02/04/2026
Violation issued (HPD, closed)
C
12/05/2025
Violation issued (HPD, closed)
C
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
10/08/2025
Violation issued (HPD, open)
C
08/17/2025
Violation issued (HPD, closed)
C
08/17/2025
Violation issued (HPD, closed)
C
08/17/2025
Violation issued (HPD, closed)
C
03/29/2025
Violation issued (HPD, open)
C
10/05/2024
Violation issued (HPD, closed)
C
10/03/2024
Violation issued (HPD, closed)
C
09/23/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/23/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/14/2024
Violation issued (HPD, closed)
C
08/13/2024
Violation issued (HPD, closed)
C
08/13/2024
Violation issued (HPD, open)
C
08/02/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
07/29/2024
Violation issued (HPD, closed)
B
07/29/2024
Violation issued (HPD, closed)
C
06/29/2024
Violation issued (HPD, closed)
A
06/02/2024
Violation issued (HPD, open)
C
06/01/2024
Violation issued (HPD, closed)
C
06/01/2024
Violation issued (HPD, closed)
C
05/31/2024
Violation issued (HPD, closed)
B
05/02/2024
Permit issued — Supported Scaffold
X00872822-I1-SF
05/02/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
02/03/2024
Violation issued (HPD, closed)
C
02/03/2024
Violation issued (HPD, closed)
C
01/21/2024
Violation issued (HPD, closed)
C
01/11/2024
Violation issued (HPD, closed)
C
01/11/2024
Violation issued (HPD, closed)
C
01/11/2024
Violation issued (HPD, closed)
C
12/05/2023
Violation issued (HPD, closed)
C
12/05/2023
Violation issued (HPD, closed)
C
11/27/2023
Violation issued (HPD, closed)
C
11/27/2023
Violation issued (HPD, closed)
C
11/22/2023
Violation issued (HPD, closed)
B
11/22/2023
Violation issued (HPD, closed)
B
11/22/2023
Violation issued (HPD, closed)
B
11/22/2023
Violation issued (HPD, closed)
B
11/15/2023
Violation issued (HPD, closed)
C
11/15/2023
Violation issued (HPD, closed)
C
11/08/2023
Violation issued (HPD, closed)
C
11/08/2023
Violation issued (HPD, closed)
C
06/20/2023
Violation issued (HPD, closed)
B
06/20/2023
Violation issued (HPD, closed)
B
05/15/2023
Permit issued — Supported Scaffold
X00872822-I1-SF
05/12/2023
Filed — Alteration
X00872822-I1
05/12/2023
Permit issued — Supported Scaffold
X00872822-I1-SF
05/10/2023
Special inspection requirement — Post-installed Anchors
Karol Zdancewicz
05/02/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/04/2023
Signed off — Alteration
Mechanical work type filed in conjunction with NB application#220704744.
X00341525-I1
01/03/2023
Signed off — Alteration
Mechanical related to tenant fit out for community facility space at 1st floor. Fit out application #X00643768, NB application #220704744.
X00643454-I1
Latest 60 of 215 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSupported ScaffoldPermit IssuedCS Bridge05/02/2024
DOB NOWSupported ScaffoldPermit IssuedCS Bridge05/15/2023
DOB NOWSupported ScaffoldPermit IssuedPrecision Hoist & Scaffo*05/12/2023
DOB NOWStandpipeSigned-offAriana Contracting02/03/2022
DOB NOWSprinklersSigned-offAriana Contracting02/03/2022
DOB NOWSprinklersSigned-offAriana Contracting02/01/2022
DOB NOWSprinklersSigned-offMax P & H01/28/2022
DOB NOWStandpipeSigned-offMax P & H01/28/2022
DOB NOWMechanical SystemsSigned-offBe Bronx Builders12/30/2021
DOB NOWPlumbingSigned-offJunior Carter Mechanical12/30/2021
DOB NOWGeneral ConstructionSigned-offBe Bronx Builders12/17/2021
DOB NOWSidewalk ShedSigned-offConsolidated Scaffolding12/02/2021
DOB NOWStandpipeSigned-offAriana Contracting08/31/2021
DOB NOWStandpipeSigned-offAriana Contracting08/30/2021
DOB NOWBoiler EquipmentSigned-offJunior Carter Mechanical08/18/2021
DOB NOWPlumbingSigned-offJunior Carter Mechanical05/28/2021
DOB NOWMechanical SystemsSigned-offBe Bronx Builders05/17/2021
DOB NOWConstruction FenceSigned-offBe Bronx Builders05/13/2021
DOB NOWStructuralSigned-offBe Bronx Builders05/13/2021
DOB NOWPlumbingSigned-offJunior Carter Mechanical05/07/2021
DOB NOWMechanical SystemsSigned-offBe Bronx Builders03/01/2021
DOB NOWSprinklersSigned-offAriana Contracting02/22/2021
DOB NOWStructuralSigned-offBe Bronx Builders02/10/2021
DOB NOWConstruction FenceSigned-offBe Bronx Builders02/10/2021
DOB NOWPlumbingSigned-offJunior Carter Mechanical01/08/2021
DOB NOWPlumbingSigned-offJunior Carter Mechanical12/07/2020
DOB NOWStructuralSigned-offBe Bronx Builders12/05/2020
DOB NOWSidewalk ShedSigned-offConsolidated Scaffolding12/04/2020
DOB NOWSupported ScaffoldSigned-offConsolidated Scaffolding12/03/2020
DOB NOWStandpipeSigned-offAriana Contracting08/28/2020
DOB NOWConstruction FenceSigned-offBe Bronx Builders07/07/2020
DOB NOWConstruction FenceSigned-offBe Bronx Builders06/17/2020
DOB NOWConstruction FenceSigned-offBe Bronx Builders06/11/2020
BIS—ISSUEDBe Bronx Builders03/22/2021
BISEQISSUEDConsolidated Scaffolding01/08/2021
BIS—ISSUEDBe Bronx Builders11/18/2020
BIS—ISSUEDBe Bronx Builders09/16/2020
BIS—ISSUEDBe Bronx Builders09/14/2020
BIS—RE-ISSUEDBe Bronx Builders09/09/2020
6 projects · most recent 03/12/2023
General Wiring
FiledStatusContractorScope
03/12/2023CompleteAL Electrical Group109 meters, 109 new_meters
02/19/2021CompleteLippolis Electric—
01/28/2021CompleteJam Electrical—
12/11/2020CompleteLippolis ElectricGeneral Wiring
12/03/2020CompleteV. Vass Electric—
12/02/2020CompleteV. Vass Electric—
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
07/27/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/13/2022Certified Gas-Gas-Piping-RoughingCertifiedView ↗
07/13/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/08/2022Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
03/12/2022Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
03/07/2022Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
02/25/2022Pass-Final Boiler Equipment InspectionPassView ↗
▾Special Inspection Requirements (DOB NOW) — 79
DateRequirementInspectorRole
05/10/2023Post-installed AnchorsKarol Zdancewiczspecial
08/15/2022Fire-Resistant Penetrations and JointsDominick Pillaspecial
08/15/2022Fire-Resistant Penetrations and JointsDominick Pillaspecial
05/23/2022Fire-Resistant Penetrations and JointsDominick Pillaspecial
05/23/2022Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationDominick Pillaspecial
05/19/2022Mechanical SystemsDominick Pillaspecial
05/19/2022HVAC and service water heating equipment Dominick Pillaenergy_progress
05/19/2022HVAC insulation and sealing Dominick Pillaenergy_progress
05/19/2022HVAC and service water heating system controls Dominick Pillaenergy_progress
05/19/2022Duct leakage testing Dominick Pillaenergy_progress
05/19/2022FinalDominick Pillaprogress
05/04/2022HVAC and service water heating equipment Dominick Pillaenergy_progress
05/04/2022FinalDominick Pillaprogress
05/04/2022Mechanical SystemsDominick Pillaspecial
05/04/2022HVAC insulation and sealing Dominick Pillaenergy_progress
05/04/2022HVAC and service water heating system controls Dominick Pillaenergy_progress
05/04/2022Duct leakage testing Dominick Pillaenergy_progress
05/02/2022Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationDominick Pillaspecial
05/02/2022Fire-Resistant Penetrations and JointsDominick Pillaspecial
04/07/2022Interior lighting powerYahaira Volquez Colomboenergy_progress
04/07/2022Lighting controlsYahaira Volquez Colomboenergy_progress
04/07/2022FinalYahaira Volquez Colomboprogress
04/04/2022Fire-Resistant Penetrations and JointsDominick Pillaspecial
03/31/2022Fire-Resistant Penetrations and JointsDominick Pillaspecial
03/31/2022Sprinkler SystemsDominick Pillaspecial
Latest 25 of 79.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Sta G G G R O UpEducationCellar, Floors 1, 2
Project X00643768 Alteration · LOC Issued · 12/13/2021
Project X00643449 Alteration · LOC Issued · 12/10/2021
Project X00643451 Alteration · LOC Issued · 12/10/2021
Project X00643454 Alteration · LOC Issued · 12/10/2021
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 284 on file (BIS + DOB NOW)
▸Plans & Drawings42
▸DOB NOWPlans/Sketch15
08/25/2026X00643454-I1Request digital key ↗
08/24/2026X00573460-I1Request digital key ↗
08/24/2026X00573460-P1Request digital key ↗
Showing 3 of 15 on file for this type
▸DOB NOWPlans/Sketch - Standpipe6
08/25/2026X00389845-I1Request digital key ↗
08/25/2026X00358345-P3Request digital key ↗
08/15/2026X00389845-P1Request digital key ↗
Showing 3 of 6 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed5
08/25/2026X00434717-I1Request digital key ↗
08/25/2026X00434717-P1Request digital key ↗
08/15/2026X00434717-P2Request digital key ↗
Showing 3 of 5 on file for this type
▸DOB NOWPlans/Sketch - Plumbing5
08/25/2026X00335247-I1Request digital key ↗
08/25/2026X00335247-P5Request digital key ↗
08/25/2026X00335247-P3Request digital key ↗
Showing 3 of 5 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler4
08/25/2026X00358345-P3Request digital key ↗
08/15/2026X00358345-P2Request digital key ↗
08/15/2026X00358345-P1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems3
08/24/2026X00341525-I1Request digital key ↗
08/24/2026X00341525-P1Request digital key ↗
08/15/2026X00341525-P2Request digital key ↗
▸DOB NOWPlans/Sketch - Structural2
08/15/2026X00328290-I1Request digital key ↗
08/15/2026X00328290-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Supported Scaffold1
08/25/2026X00434713-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Construction Fence1
08/26/2026X00354101-I1Request digital key ↗
▸Applications & Permits26
▸BISPLAN / WORK APPROVAL APPLICATION18
03/06/2023220704744Open ↗
10/13/2022220704744Open ↗
05/13/2022220704744Open ↗
Showing 3 of 18 on file for this type
▸BISWORK PERMIT APPLICATION6
03/24/2021220704744Open ↗
01/08/2021240299459Open ↗
11/18/2020220704744Open ↗
Showing 3 of 6 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
03/10/2022220704744Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
07/28/2021240275331Open ↗
▸Zoning, Tax Lot & Property Records7
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED1
08/12/2020220704744Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
08/12/2020220704744Open ↗
▸BISVERIFY TAX LOT1
04/13/2022220704744Open ↗
▸BISADDRESS: NEW HOUSE NUMBER APPROVED1
08/12/2020220704744Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
04/13/2022220704744Open ↗
▸BISZONING DIAGRAM1
08/12/2020220704744Open ↗
▸BISZONING EXHIBIT II: CERTIFICATION1
08/12/2020220704744Open ↗
▸Seals & Professional Certifications124
▸DOB NOWSpecial Inspector Seal & Signature50
10/03/2026X00358345-P1Open ↗
10/03/2026X00358345-P1Open ↗
10/03/2026X00358345-P1Open ↗
Showing 3 of 50 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature38
08/26/2026X00328290-P1Open ↗
08/26/2026X00328290-I1Open ↗
08/25/2026X00434717-P1Open ↗
Showing 3 of 38 on file for this type
▸DOB NOWProgress Inspector Seal & Signature26
09/02/2026X00643768-P1Open ↗
09/02/2026X00643768-P1Open ↗
09/02/2026X00328290-P1Open ↗
Showing 3 of 26 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION6
04/13/2022220704744Open ↗
04/13/2022220704744Open ↗
09/09/2020220704744Open ↗
Showing 3 of 6 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
01/05/2021240299459Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
07/10/2020240275331Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
01/05/2021240299459Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
01/05/2021240299459Open ↗
▸Trade Schedules & Equipment5
▸BISDETECTOR:SMOKE-CERT. OF INSTALLATION1
04/12/2022220704744Open ↗
▸BISDETECTOR:CARBON MONOXIDE-CERT.OF INSTALL1
04/11/2022220704744Open ↗
▸BISSTANDPIPE ALARM DRAWINGS & AI1 (OR AI1 PROOF)1
09/01/2020220704744Open ↗
▸BIS* SEWER CONNECTION: DEP SD1 & SD21
08/12/2020220704744Open ↗
▸BISSTANDPIPE WORK PERMIT1
09/01/2020220704744Open ↗
▸Safety & Tenant Protection5
▸BISSTREET TREE CHECKLIST3
02/22/2021240275331Open ↗
08/12/2020220704744Open ↗
03/05/2020220704744Open ↗
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN1
09/09/2020220704744Open ↗
▸BISSITE SAFETY PLANS1
09/09/2020220704744Open ↗
▸Energy Compliance10
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY5
04/11/2022220704744Open ↗
11/24/2020220704744Open ↗
11/24/2020220704744Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
04/13/2022220704744Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
04/11/2022220704744Open ↗
▸BISPRELIMINARY COMMISSIONING REPORT CERTIFICATION1
07/14/2022220704744Open ↗
▸DOB NOWEN2: As Built Energy Analysis1
08/13/2026X00643768-I1Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026X00573460-I1Open ↗
▸Inspections & Test Reports19
▸BISTECHNICAL REPORT: RESPONSIBILITY12
04/11/2022220704744Open ↗
02/10/2022240299459Open ↗
02/08/2022240299459Open ↗
Showing 3 of 12 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER3
10/08/2021220704744Open ↗
11/24/2020220704744Open ↗
11/24/2020220704744Open ↗
▸BISTR2: CONCRETE FIELD TESTING TECHNICAL REPORT1
09/09/2020220704744Open ↗
▸BISSOIL REPORT1
08/12/2020220704744Open ↗
▸BISTECHNICAL REPORT: SOIL INSPECTION1
08/12/2020220704744Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
09/09/2020220704744Open ↗
▸Approvals, Objections & Sign-offs21
▸BISSCHEDULE A - OCCUPANCY / USE10
10/13/2022220704744Open ↗
05/13/2022220704744Open ↗
04/11/2022220704744Open ↗
Showing 3 of 10 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST5
04/13/2022220704744Open ↗
04/13/2022220704744Open ↗
02/11/2022240299459Open ↗
Showing 3 of 5 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION3
03/24/2021220704744Open ↗
09/16/2020220704744Open ↗
08/12/2020220704744Open ↗
▸BISSUPERSEDING LETTER1
11/18/2020220704744Open ↗
▸BISMECHANICAL (MH) SIGNOFF1
02/15/2023220704744Open ↗
▸BISSUSTAINABLE ROOF ZONE FORM (SIGNOFF)1
04/11/2022220704744Open ↗
▸Cost, Insurance & Ownership1
▸BISPROJECT-SPECIFIC GL INSURANCE1
09/09/2020220704744Open ↗
▸Filing & Intake Forms18
▸BISADDITIONAL INFORMATION13
10/13/2022220704744Open ↗
03/11/2022220704744Open ↗
03/03/2022220704744Open ↗
Showing 3 of 13 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET2
01/05/2021240299459Open ↗
07/10/2020240275331Open ↗
▸BISEFILING COVER SHEET2
03/05/2020220704744Open ↗
03/05/2020220704744Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
02/22/2021240275331Open ↗
▸Other Documents6
▸BISBPP-PARKS: PLANT NEW TREE1
02/17/2021240275331Open ↗
▸BISSUSTAINABLE ROOF ZONE FORM1
08/12/2020220704744Open ↗
▸BISCOMMERICAL KITCHENS REQUIRE FIRE SUPRESSION SYSTEM(S)LOA BASED ON MC 507.2.1THRU 507.2.4(BC27-778)NYC FC901.4.5.1-LOA REQUIRED PRIOR TO NEXT TCO RENEWAL-NYCFC 112-01(B)(1)(D).1
02/21/2023220704744Open ↗
▸BISPROVIDE PROOF OF COMPLIANCE WITH BB2019-010 GREEN ROOF REQUIREMENTS FOR NEW BUILDINGS1
02/21/2023220704744Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
02/22/2021240275331Open ↗
▸BISPLOT DIAGRAM1
08/12/2020220704744Open ↗