← Back
Two stories - detached, small or mid-size
1076 VICTORY BOULEVARD
STATEN ISLAND · BIN 5015399
💬 Discuss this project
1925Year Built
2Stories
A1Building Class
R2Zoning
1,296 sfGross Floor Area
1Units
1 Open Violation ▸FDNY Report ↗
Two stories - detached, small or mid-size · 4,000 sf lot · 0.32 FAR built · Flood zone X
Locations of Work
Architecture
Floor 11p · 1 filing · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CHARLES A. MAGRINO, AIA509/13/2022
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
JOSHUA CONSTRUCTION CORPGeneral Contractor203/21/2026
LIQUID PLBG & HTNG SCS INPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ISLAND ENGINEERING ASSOCI264509/13/2022
Building Lifecycle
All (40)Filed (5)Permit Issued (2)Signed Off (2)Violation (1)Special Inspection (30)
10/26/2022
Signed off — Alteration
REPLACE, RELOCATE, AND/OR INSTALL NEW PLUMBING FIXTURES AND PIPING THROUGHOUT AS NECESSARY TO REPAIR FIRE DAMAGE.
S00618423-I1
10/26/2022
Signed off — Alteration
REPAIR FIRE DAMAGE THROUGHOUT. MODIFY PARTITIONS. MODIFY STRUCTURE IN CELLAR.
S00618839-I1
09/14/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
WILLIAM DURDEN, P.E.
09/14/2022
Special inspection requirement — Energy Code Compliance Inspections
WILLIAM DURDEN, P.E.
09/14/2022
Special inspection requirement — Maintenance information
WILLIAM DURDEN, P.E.
09/14/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
WILLIAM DURDEN, P.E.
09/14/2022
Special inspection requirement — HVAC-R and service water heating equipment
WILLIAM DURDEN, P.E.
09/14/2022
Special inspection requirement — HVAC-R and service water heating system controls
WILLIAM DURDEN, P.E.
09/13/2022
Filed — Alteration
REPLACE, RELOCATE, AND/OR INSTALL NEW PLUMBING FIXTURES AND PIPING THROUGHOUT AS NECESSARY TO REPAIR FIRE DAMAGE.
S00618423-P2
09/13/2022
Special inspection requirement — HVAC-R and service water heating equipment
WILLIAM DURDEN, P.E.
09/13/2022
Special inspection requirement — Maintenance information
WILLIAM DURDEN, P.E.
09/13/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
WILLIAM DURDEN, P.E.
09/13/2022
Special inspection requirement — HVAC-R and service water heating system controls
WILLIAM DURDEN, P.E.
09/13/2022
Special inspection requirement — Energy Code Compliance Inspections
WILLIAM DURDEN, P.E.
09/13/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
WILLIAM DURDEN, P.E.
08/12/2022
Filed — Alteration
REPLACE, RELOCATE, AND/OR INSTALL NEW PLUMBING FIXTURES AND PIPING THROUGHOUT AS NECESSARY TO REPAIR FIRE DAMAGE.
S00618423-P1
08/11/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
WILLIAM DURDEN, P.E.
08/11/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
WILLIAM DURDEN, P.E.
08/11/2022
Special inspection requirement — Energy Code Compliance Inspections
WILLIAM DURDEN, P.E.
08/11/2022
Special inspection requirement — HVAC-R and service water heating equipment
WILLIAM DURDEN, P.E.
08/11/2022
Special inspection requirement — HVAC-R and service water heating system controls
WILLIAM DURDEN, P.E.
08/11/2022
Special inspection requirement — Maintenance information
WILLIAM DURDEN, P.E.
01/13/2022
Permit issued — Plumbing
S00618423-I1-PL
11/29/2021
Permit issued — General Construction
S00618839-I1-GC-CX
11/20/2021
Special inspection requirement — Air barrier - visual inspection
WILLIAM DURDEN, P.E.
11/20/2021
Special inspection requirement — Insulation placement and R values
WILLIAM DURDEN, P.E.
11/20/2021
Special inspection requirement — Fireplaces
WILLIAM DURDEN, P.E.
11/20/2021
Special inspection requirement — Energy Code Compliance Inspections
WILLIAM DURDEN, P.E.
11/20/2021
Special inspection requirement — Structural Wood Frame
WILLIAM DURDEN, P.E.
11/20/2021
Special inspection requirement — Final
WILLIAM DURDEN, P.E.
11/20/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
WILLIAM DURDEN, P.E.
11/20/2021
Special inspection requirement — Structural Steel - Details
WILLIAM DURDEN, P.E.
11/20/2021
Special inspection requirement — Structural Stability – Alterations of existing buildings
WILLIAM DURDEN, P.E.
11/20/2021
Special inspection requirement — Fenestration areas
WILLIAM DURDEN, P.E.
11/20/2021
Special inspection requirement — Fenestration air leakage
WILLIAM DURDEN, P.E.
11/20/2021
Special inspection requirement — Fenestration and door U-factor and product ratings
WILLIAM DURDEN, P.E.
11/18/2021
Filed — Alteration
REPAIR FIRE DAMAGE THROUGHOUT. MODIFY PARTITIONS. MODIFY STRUCTURE IN CELLAR.
S00618839-P1
10/27/2021
Filed — Alteration
REPAIR FIRE DAMAGE THROUGHOUT. MODIFY PARTITIONS. MODIFY STRUCTURE IN CELLAR.
S00618839-I1
10/26/2021
Filed — Alteration
REPLACE, RELOCATE, AND/OR INSTALL NEW PLUMBING FIXTURES AND PIPING THROUGHOUT AS NECESSARY TO REPAIR FIRE DAMAGE.
S00618423-I1
06/26/2021
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offLIQUID PLBG & HTNG SCS IN01/13/2022
DOB NOWGeneral ConstructionSigned-offJOSHUA CONSTRUCTION CORP11/29/2021
1 project · most recent 07/18/2022
General Wiring
FiledStatusContractorScope
07/18/2022CompleteOHM PRO ELECTL CONST CORPGeneral Wiring
▾Special Inspection Requirements (DOB NOW) — 46
DateRequirementInspectorRole
09/14/2022Fire-Resistant Penetrations and JointsWILLIAM DURDEN, P.E.special
09/14/2022Energy Code Compliance InspectionsWILLIAM DURDEN, P.E.progress
09/14/2022Maintenance informationWILLIAM DURDEN, P.E.energy_progress
09/14/2022HVAC-R and service water piping design and insulationWILLIAM DURDEN, P.E.energy_progress
09/14/2022HVAC-R and service water heating equipmentWILLIAM DURDEN, P.E.energy_progress
09/14/2022HVAC-R and service water heating system controlsWILLIAM DURDEN, P.E.energy_progress
09/13/2022HVAC-R and service water heating equipmentWILLIAM DURDEN, P.E.energy_progress
09/13/2022Maintenance informationWILLIAM DURDEN, P.E.energy_progress
09/13/2022HVAC-R and service water piping design and insulationWILLIAM DURDEN, P.E.energy_progress
09/13/2022HVAC-R and service water heating system controlsWILLIAM DURDEN, P.E.energy_progress
09/13/2022Energy Code Compliance InspectionsWILLIAM DURDEN, P.E.progress
09/13/2022Fire-Resistant Penetrations and JointsWILLIAM DURDEN, P.E.special
08/11/2022HVAC-R and service water piping design and insulationWILLIAM DURDEN, P.E.energy_progress
08/11/2022Fire-Resistant Penetrations and JointsWILLIAM DURDEN, P.E.special
08/11/2022Energy Code Compliance InspectionsWILLIAM DURDEN, P.E.progress
08/11/2022HVAC-R and service water heating equipmentWILLIAM DURDEN, P.E.energy_progress
08/11/2022HVAC-R and service water heating system controlsWILLIAM DURDEN, P.E.energy_progress
08/11/2022Maintenance informationWILLIAM DURDEN, P.E.energy_progress
11/20/2021Air barrier - visual inspectionWILLIAM DURDEN, P.E.energy_progress
11/20/2021Insulation placement and R valuesWILLIAM DURDEN, P.E.energy_progress
11/20/2021FireplacesWILLIAM DURDEN, P.E.energy_progress
11/20/2021Energy Code Compliance InspectionsWILLIAM DURDEN, P.E.progress
11/20/2021Structural Wood FrameWILLIAM DURDEN, P.E.progress
11/20/2021FinalWILLIAM DURDEN, P.E.progress
11/20/2021Fire-Resistant Penetrations and JointsWILLIAM DURDEN, P.E.special
Latest 25 of 46.
▾Documents — 57 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/25/2026S00618839-I1Request digital key ↗
08/25/2026S00618839-P1Request digital key ↗
08/24/2026S00618423-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸Seals & Professional Certifications48
▸DOB NOWProgress Inspector Seal & Signature32
09/01/2026S00618423-P1Open ↗
09/01/2026S00618423-P1Open ↗
09/01/2026S00618423-P1Open ↗
Showing 3 of 32 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature11
09/01/2026S00618423-P1Open ↗
08/30/2026S00618839-P1Open ↗
08/30/2026S00618839-P1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/25/2026S00618839-I1Open ↗
08/25/2026S00618839-P1Open ↗
08/24/2026S00618423-I1Open ↗
Showing 3 of 5 on file for this type
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form2
08/25/2026S00618839-I1Open ↗
08/13/2026S00618423-I1Open ↗
▸Energy Compliance2
▸DOB NOWEN2: As Built Energy Analysis.2
08/13/2026S00618423-I1Open ↗
08/13/2026S00618839-I1Open ↗