| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/19/2025 | Complete | DENMAR ELECTRIC CORP | General Wiring |
| 03/11/2023 | Complete | DENMAR ELECTRIC CORP | General Wiring |
| 12/07/2022 | Complete | BRONXDALE ELECTRIC INC | 13 meters, 12 new_meters |
| 09/07/2021 | Complete | JOSEPH WEINSTEIN ELECTRIC | General Wiring |
| 05/29/2019 | Complete | WILLDAN ELECTRICAL OF NY | — |
| Owner | Filings | Most Recent |
|---|---|---|
| HANCOCK ASSOCIATES | 56 | 07/08/2026 |
| 1079 HANCOCK ASSOCIATES | 5 | 03/22/2026 |
| PL CONSTRUCTION | 3 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| HAMANN ENGINEERING, PLLC | 8 | 09/10/2025 |
| EAB ENGINEERING PC | 10 | 03/17/2022 |
| ASHRAF CORP | 1 | 08/24/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| SUPERIOR FIRE CONTROL | 1 | 03/21/2026 |
| BIG ORANGE EXPEDITING | 16 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| H&T DESIGNS CORP | General Contractor | 6 | 07/08/2026 |
| WIESLAW MAKSIM | Electrical | 2 | 03/21/2026 |
| SUPERB PLUMBING & HEATING | Plumbing | 2 | 07/08/2026 |
| MAX CONSTRUCTION USA CORP | General Contractor | 2 | 07/08/2026 |
| DONE RIGHT KITCHEN EXHAUS | General Contractor | 1 | 07/08/2026 |
| WILLDAN ELECTRICAL OF NY | Electrical | 1 | 03/22/2026 |
| JOSEPH WEINSTEIN ELECTRIC 000796 | General Contractor | 1 | 03/22/2026 |
| CARL HAMANN | Electrical | 1 | 03/21/2026 |
| TOMCHRIS CONTRACTING CORP | General Contractor | 1 | 07/08/2026 |
| INFINITI ESC PLUMBING COR | Plumbing | 1 | 07/08/2026 |
| BIG ORANGE SAFETY FIRST | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HAMANN ENGINEERING, PLLC | 4949 | 8 | 09/10/2025 |
| EAB ENGINEERING, PC | 2048 | 6 | 03/17/2022 |
| ASHRAF CORPORATION | 1973 | 1 | 08/24/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | TOMCHRIS CONTRACTING CORP | 07/10/2025 |
| DOB NOW | General Construction | Permit Issued | H&T DESIGNS CORP | 08/26/2024 |
| DOB NOW | Plumbing | Signed-off | SUPERB PLUMBING & HEATING | 02/27/2023 |
| DOB NOW | Mechanical Systems | Signed-off | BIG ORANGE SAFETY FIRST | 12/22/2022 |
| DOB NOW | Plumbing | Signed-off | SUPERB PLUMBING & HEATING | 07/28/2022 |
| DOB NOW | Mechanical Systems | Signed-off | MAX CONSTRUCTION USA CORP | 12/17/2021 |
| DOB NOW | Mechanical Systems | Signed-off | DONE RIGHT KITCHEN EXHAUS | 12/13/2021 |
| DOB NOW | Plumbing | Signed-off | INFINITI ESC PLUMBING COR | 10/25/2021 |
| DOB NOW | General Construction | Signed-off | MAX CONSTRUCTION USA CORP | 10/14/2021 |
| BIS | OT | ISSUED | INTRAKO INC | 04/25/2016 |
| BIS | PL | ISSUED | PRACTICAL PLBG & HTG INC | 03/18/2016 |
| BIS | OT | ISSUED | TSA CONSTRUCTION LLC | 11/06/2015 |
| BIS | PL | ISSUED | PRACTICAL PLBG & HTG INC | 03/23/2012 |
| BIS | OT | ISSUED | TSA CONSTRUCTION LLC | 03/05/2012 |
| BIS | PL | ISSUED | PRACTICAL PLBG & HTG INC | 02/27/2012 |
| BIS | PL | ISSUED | ERAX PLUMBING, INC | 05/11/2011 |
| BIS | OT | ISSUED | TSA CONSTRUCTION LLC | 05/03/2011 |
| BIS | BL | ISSUED | A.M.N. CORPORATION | 01/04/2006 |
| BIS | PL | ISSUED | A.M.N. CORPORATION | 01/04/2006 |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/17/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/19/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/02/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/23/2024 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 06/14/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/14/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/14/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/08/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/19/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/12/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/24/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/22/2022 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 07/12/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/16/2022 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 03/11/2022 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 12/22/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/27/2025 | Lighting controls | CARL HAMANN | energy_progress |
| 08/27/2025 | Tenant Protection Plan Compliance | — | special |
| 08/27/2025 | Energy Code Compliance Inspections | CARL HAMANN | progress |
| 08/27/2025 | Fire-Resistant Penetrations and Joints | CARL HAMANN | special |
| 08/27/2025 | Interior lighting power | CARL HAMANN | energy_progress |
| 02/22/2023 | HVAC-R and service water piping design and insulation | CARL HAMANN | energy_progress |
| 02/22/2023 | Fire-Resistant Penetrations and Joints | CARL HAMANN | special |
| 02/22/2023 | Energy Code Compliance Inspections | CARL HAMANN | progress |
| 02/22/2023 | Maintenance information | CARL HAMANN | energy_progress |
| 02/22/2023 | HVAC-R and service water heating system controls | CARL HAMANN | energy_progress |
| 02/22/2023 | HVAC-R and service water heating equipment | CARL HAMANN | energy_progress |
| 12/14/2022 | Fire-Resistant Penetrations and Joints | CARL HAMANN | special |
| 12/05/2022 | Tenant Protection Plan Compliance | CARL HAMANN | special |
| 08/24/2022 | HVAC-R and service water piping design and insulation | CARL HAMANN | energy_progress |
| 08/24/2022 | Maintenance information | CARL HAMANN | energy_progress |
| 08/24/2022 | Fire-Resistant Penetrations and Joints | CARL HAMANN | special |
| 08/24/2022 | HVAC-R and service water heating equipment | CARL HAMANN | energy_progress |
| 08/24/2022 | Energy Code Compliance Inspections | CARL HAMANN | progress |
| 08/24/2022 | HVAC-R and service water heating system controls | CARL HAMANN | energy_progress |
| 04/01/2022 | HVAC-R and service water piping design and insulation | Iraj Issapour | energy_progress |
| 04/01/2022 | HVAC-R and service water heating system controls | Iraj Issapour | energy_progress |
| 04/01/2022 | HVAC-R and service water heating equipment | Iraj Issapour | energy_progress |
| 04/01/2022 | Mechanical Systems | Iraj Issapour | special |
| 04/01/2022 | Final | Iraj Issapour | progress |
| 04/01/2022 | Maintenance information | Iraj Issapour | energy_progress |