| Firm | Filings | Most Recent |
|---|---|---|
| ETRECTE LLC | 2 | 03/05/2026 |
| BAZINI ENGINEERING, P.C. | 2 | 02/09/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| PATRIOT ENERGY SOLUTIONS CORP | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PATRIOT ENERGY SOL CO | General Contractor | 3 | 03/21/2026 |
| MAK ELECTRICAL CONTR CORP | Electrical | 1 | 03/22/2026 |
| NULITE FUEL OIL CO., LTD | General Contractor | 1 | 04/09/2026 |
| NULITE FUEL OIL CO LTD | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ETRECTE LLC | 8116 | 2 | 03/05/2026 |
| BAZINI ENGINEERING, P.C. | 1808 | 1 | 02/09/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | NULITE FUEL OIL CO., LTD | 03/05/2026 |
| DOB NOW | Plumbing | Signed-off | NULITE FUEL OIL CO LTD | 03/04/2026 |
| DOB NOW | Solar | Signed-off | PATRIOT ENERGY SOL CO | 10/03/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/29/2025 | Complete | MAK ELECTRICAL CONTR CORP | 2 meters |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/06/2026 | Energy Code Compliance Inspections | VYACHESLAV NECHAYEV | progress |
| 03/06/2026 | Air barrier - visual inspection | VYACHESLAV NECHAYEV | energy_progress |
| 03/06/2026 | Fire-Resistant Penetrations and Joints | VYACHESLAV NECHAYEV | special |
| 03/06/2026 | Final | VYACHESLAV NECHAYEV | progress |
| 02/09/2026 | HVAC-R and service water heating equipment | Joseph Bazini | energy_progress |
| 12/04/2025 | Air barrier - visual inspection | VYACHESLAV NECHAYEV | energy_progress |
| 12/04/2025 | Energy Code Compliance Inspections | VYACHESLAV NECHAYEV | progress |
| 12/04/2025 | Final | VYACHESLAV NECHAYEV | progress |
| 12/04/2025 | Fire-Resistant Penetrations and Joints | VYACHESLAV NECHAYEV | special |
| 09/12/2025 | Final | Joseph Bazini | progress |
| 09/12/2025 | Mechanical Systems | Joseph Bazini | special |