| Owner | Filings | Most Recent |
|---|---|---|
| 109 BUILDER LLC | 1 | 03/22/2026 |
| REGAL REALTY | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/23/2023 | $1.1M | — | 109 BUILDER LLC → Private party | $455/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| PIROOZ ENGINEERING, P.C. | 6 | 02/11/2023 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| YAFE MEOD CORP | General Contractor | 4 | 07/08/2026 |
| SKY ELECTRIC LLC | Electrical | 1 | 03/22/2026 |
| KAIETEUR CONSTRUCTION INC. | General Contractor | 1 | 07/08/2026 |
| INFINITI ESC PLUMBING COR | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PIROOZ ENGINEERING P.C | 7177 | 2 | 03/19/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | YAFE MEOD CORP | 12/16/2022 |
| DOB NOW | Curb Cut | Signed-off | YAFE MEOD CORP | 12/16/2022 |
| DOB NOW | Plumbing | Signed-off | INFINITI ESC PLUMBING COR | 04/18/2022 |
| DOB NOW | Construction Fence | Signed-off | KAIETEUR CONSTRUCTION INC | 10/05/2021 |
| BIS | — | ISSUED | KAIETEUR CONSTRUCTION INC. | 08/18/2022 |
| BIS | — | ISSUED | KAIETEUR CONSTRUCTION INC. | 03/01/2022 |
| BIS | — | ISSUED | KAIETEUR CONSTRUCTION INC. | 01/28/2022 |
| BIS | — | ISSUED | KAIETEUR CONSTRUCTION INC. | 01/21/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/14/2021 | Complete | SKY ELECTRIC LLC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 02/27/2023 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 04/27/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 04/27/2022 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 04/27/2022 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 04/27/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/16/2022 | HVAC and service water heating equipment | PIROOZ SOLTANIZADEH | energy_progress |
| 09/16/2022 | HVAC insulation and sealing | PIROOZ SOLTANIZADEH | energy_progress |
| 09/16/2022 | HVAC and service water heating system controls | PIROOZ SOLTANIZADEH | energy_progress |
| 09/16/2022 | Energy Code Compliance Inspections | PIROOZ SOLTANIZADEH | progress |
| 09/16/2022 | Fire-Resistant Penetrations and Joints | PIROOZ SOLTANIZADEH | special |
| 09/16/2022 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | PIROOZ SOLTANIZADEH | special |
| 09/16/2022 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | PIROOZ SOLTANIZADEH | special |
| 07/13/2022 | Fire-Resistant Penetrations and Joints | PIROOZ SOLTANIZADEH | special |
| 07/13/2022 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | PIROOZ SOLTANIZADEH | special |
| 07/13/2022 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | PIROOZ SOLTANIZADEH | special |
| 07/13/2022 | Energy Code Compliance Inspections | PIROOZ SOLTANIZADEH | progress |
| 07/13/2022 | HVAC and service water heating system controls | PIROOZ SOLTANIZADEH | energy_progress |
| 07/13/2022 | HVAC insulation and sealing | PIROOZ SOLTANIZADEH | energy_progress |
| 07/13/2022 | HVAC and service water heating equipment | PIROOZ SOLTANIZADEH | energy_progress |
| 10/29/2020 | Fire-Resistant Penetrations and Joints | PIROOZ SOLTANIZADEH | special |
| 10/29/2020 | HVAC and service water heating system controls | PIROOZ SOLTANIZADEH | energy_progress |
| 10/29/2020 | HVAC and service water heating equipment | PIROOZ SOLTANIZADEH | energy_progress |
| 10/29/2020 | HVAC insulation and sealing | PIROOZ SOLTANIZADEH | energy_progress |
| 10/29/2020 | Heating Systems | PIROOZ SOLTANIZADEH | special |
| 06/19/2020 | Final | JAN PEREZ | progress |
| 06/19/2020 | Mechanical Systems | PIROOZ SOLTANIZADEH | special |