← Back
BuildNYC
Elevator cooperative
108 EAST 91ST STREET
MANHATTAN · BIN 1048283
💬 Discuss this project
1928Year Built
9Stories
D4Building Class
R8BZoning
37,207 sfGross Floor Area
38Units
LL97 CoveredRent Stabilized0 Active ViolationsFISP: SWARMPFDNY Report ↗
Elevator cooperative · Owner of record: 91st Street Tenants · 5,438 sf lot · 6.84 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Whole building & multi-floor projectsMatthew Adam Properties, INC.1 filing
RoofMatthew Adam properties Inc.1p · 1 filing · 3 docs
Floor 1Heavy duty sidewalk shed1 filing · 2 docs
Site & exteriorMatthew Adam properties Inc.4 filings · 4 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Matthew Adam Properties2707/08/2026
91st Street Tenant1103/22/2026
91st Street Tebabt Ciroiratuib203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
New Age601/07/2026
Ashraf305/29/2024
Rigid Structural Design105/29/2024
Stone106/26/2023
Navi Structural Engineering104/11/2018
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Prat Enterprises203/21/2026
Rigid Structural Design403/21/2026
Stone203/21/2026
Eurocelt Expediting203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Intersystems Installation S&SScaffold807/08/2026
Universal SystemsScaffold407/08/2026
Demar MechanicalPlumbing407/08/2026
Prat EnterprisesGeneral Contractor303/21/2026
Demar PlumbingFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
New Age Engineering7746601/07/2026
Metric Consulting and Ins1803106/26/2023
Building Lifecycle
All (102)Filed (13)Permit Issued (13)Signed Off (5)Facade (FISP) (17)Violation (41)Inspection (9)Special Inspection (4)
01/26/2026
Permit issued — Plumbing
M00968569-I1-PL
01/07/2026
Filed — Alteration
INSTALL NEW GAS METER AND PIPING FOR EXISTING GAS-FIRED DRYERS AS PER PLANS. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
M00968569-P5
11/03/2025
Violation issued (HPD, closed)
C
11/03/2025
Violation issued (HPD, closed)
C
10/23/2025
Cycle 10 facade report signed — SAFE
09/17/2025
Violation issued (FDNY_NOV, closed)
08/26/2025
Violation issued (ECB, closed)
Construction
08/18/2025
Cycle 10 facade report submitted
08/11/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/06/2025
Cycle 10 facade inspection completed
05/16/2025
Filed — Alteration
INSTALL NEW GAS METER AND PIPING FOR EXISTING GAS-FIRED DRYERS AS PER PLANS. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
M00968569-P3
05/09/2025
Permit issued — Plumbing
M00968569-S1-PL
05/09/2025
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
02/13/2025
Signed off — Alteration
Installation of a temporarily heavy-duty sidewalk per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00918366-I1
02/13/2025
Signed off — Alteration
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M01055967-I1
02/13/2025
Signed off — Alteration
M00918378-I1
01/08/2025
Signed off — Alteration
M00985386-I1
11/14/2024
Violation issued (FDNY_NOV, closed)
11/06/2024
Cycle 9 facade report submitted
10/25/2024
Cycle 9 facade inspection completed
09/19/2024
Permit issued — Sidewalk Shed
M00918366-I1-SH
07/17/2024
Inspection — Pass-Final SP - Up to 3 Requested Floors
Pass
View inspection ↗
07/10/2024
Inspection — Pass-Final PL - More than 10 Requested Floors
Pass
View inspection ↗
07/01/2024
Inspection — Pass-Final PL - More than 10 Requested Floors
Pass
View inspection ↗
06/14/2024
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
06/12/2024
Violation issued (FDNY_NOV, closed)
06/03/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/30/2024
Permit issued — Supported Scaffold
M01055967-I1-SF
05/29/2024
Filed — Alteration
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M01055967-I1
05/29/2024
Filed — Alteration
Installation of a temporarily heavy-duty sidewalk per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00918366-P1
05/28/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/21/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/10/2024
Permit issued — Sprinklers
M00968569-S2-EW-SP
05/01/2024
Permit issued — Plumbing
M00968569-S1-PL
04/29/2024
Filed — Alteration
INSTALL NEW GAS METER AND PIPING FOR EXISTING GAS-FIRED DRYERS AS PER PLANS. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
M00968569-S2
04/10/2024
Filed — Alteration
INSTALL NEW GAS METER AND PIPING FOR EXISTING GAS-FIRED DRYERS AS PER PLANS. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
M00968569-P1
04/10/2024
Special inspection requirement — Tenant Protection Plan Compliance
Stephen Shishko
04/10/2024
Special inspection requirement — Sprinkler Systems
Stephen Shishko
04/01/2024
Filed — Alteration
INSTALL NEW GAS METER AND PIPING FOR EXISTING GAS-FIRED DRYERS AS PER PLANS. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
M00968569-S1
04/01/2024
Violation issued (HPD, closed)
A
03/28/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Stephen Shishko
03/28/2024
Special inspection requirement — Tenant Protection Plan Compliance
Stephen Shishko
01/16/2024
Signed off — Alteration
INSTALLATION OF A HEAVY DUTY SIDEWALK SHED APPROXIMATELY 85' LONG AS PER PLANS DURING FACADE REPAIRS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE OF 2018.
M00034460-I1
01/12/2024
Permit issued — Suspended Scaffold
M00985386-I1-SC
01/04/2024
Filed — Alteration
M00985386-I1
12/20/2023
Permit issued — Plumbing
M00968569-I1-PL
12/14/2023
Filed — Alteration
INSTALL NEW GAS METER AND PIPING FOR EXISTING GAS-FIRED DRYERS AS PER PLANS. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
M00968569-I1
10/13/2023
Permit issued — General Construction
M00884871-I1-GC
08/23/2023
Permit issued — Protection and Mechanical Methods
M00918378-I1-PMM
08/22/2023
Filed — Alteration
M00918378-I1
08/22/2023
Permit issued — Sidewalk Shed
M00918366-I1-SH
08/21/2023
Filed — Alteration
Installation of a temporarily heavy-duty sidewalk per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00918366-I1
06/26/2023
Filed — Alteration
Facade repair plans. No change in use egress or occupancy.
M00884871-I1
05/02/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/15/2023
Violation issued (HPD, closed)
A
12/01/2022
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/28/2022
Cycle 9 facade report signed — SWARMP
02/15/2022
Violation issued (HPD, closed)
A
02/11/2022
Cycle 9 facade report submitted
12/21/2021
Cycle 9 facade inspection completed
Latest 60 of 102 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offDemar Mechanical01/26/2026
DOB NOWPlumbingSigned-offDemar Mechanical05/09/2025
DOB NOWSidewalk ShedSigned-offIntersystems Installation S&S09/19/2024
DOB NOWSupported ScaffoldSigned-offIntersystems Installation S&S05/30/2024
DOB NOWSprinklersSigned-offDemar Plumbing05/10/2024
DOB NOWPlumbingSigned-offDemar Mechanical05/01/2024
DOB NOWSuspended ScaffoldSigned-offPratt Construction & Restoration01/12/2024
DOB NOWPlumbingSigned-offDemar Mechanical12/20/2023
DOB NOWGeneral ConstructionPermit IssuedPrat Enterprises10/13/2023
DOB NOWProtection and Mechanical MethodsSigned-offIntersystems Installation S&S08/23/2023
DOB NOWSidewalk ShedSigned-offIntersystems Installation S&S08/22/2023
DOB NOWSidewalk ShedSigned-offUniversal Systems01/28/2019
DOB NOWSidewalk ShedSigned-offUniversal Systems04/17/2018
BISPLISSUEDAbr Plumbing & Heating Contracting06/15/2022
BISPLISSUEDT.N.T. Plumbing & Heating01/30/2019
BISOTISSUEDEvan Long Island Painting01/11/2019
BISOTISSUEDEverlast Solutions09/18/2018
BISPLISSUEDA.M.N07/25/2017
BISOTISSUEDTaurus Construction07/10/2017
BISPLISSUEDExpress Plumbing Sewr and WTR02/22/2011
BISOTISSUEDPrincipal Builders Soluti01/13/2011
BISPLISSUEDPlumbing & Heating Doctor06/04/2008
BISOTISSUEDS & G Contracting MNGT04/02/2007
BISOTRE-ISSUEDSM Construction & Contracting03/15/2007
BISPLISSUEDPlumbing & Heating Doctor02/10/2004
BISOTISSUEDCertified of N.Y11/20/2003
BISOTISSUEDG S Universal Cosntr11/07/2003
BISOTISSUEDG S Universal Cosntr09/23/2003
BISOTISSUEDVema Contracting09/03/2002
BISEQISSUEDSpring Scaffolding08/27/2002
BISPLISSUEDN.pagano Plumbing & Heating Cont06/16/1997
BISOTISSUEDJ & J Johnson General Contracting04/18/1997
BISFBISSUEDH.lieblich/Co11/30/1992
1 project · most recent 01/07/2026
Gas
FiledStatusContractorScope
01/07/2026Signed-offDemar MechanicalGas
2 projects · most recent 09/12/2023
FiledStatusContractorScope
09/12/2023Permit IssuedAUR0RA Electrical Contg—
04/02/2018CompleteTop Shelf Electric—
▾Field Inspections (DOB CAP) — 9
DateTypeResultReport
08/11/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/09/2025Fail-Final PL - Up to 3 Requested FloorsFailView ↗
07/17/2024Pass-Final SP - Up to 3 Requested FloorsPassView ↗
07/10/2024Pass-Final PL - More than 10 Requested FloorsPassView ↗
07/01/2024Pass-Final PL - More than 10 Requested FloorsPassView ↗
06/14/2024Fail-Final PL - Up to 3 Requested FloorsFailView ↗
06/03/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/28/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/21/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 4
DateRequirementInspectorRole
04/10/2024Tenant Protection Plan ComplianceStephen Shishkospecial
04/10/2024Sprinkler SystemsStephen Shishkospecial
03/28/2024Fire-Resistant Penetrations and JointsStephen Shishkospecial
03/28/2024Tenant Protection Plan ComplianceStephen Shishkospecial
▾Documents — 120 on file (BIS + DOB NOW)
▸Plans & Drawings13
▸DOB NOWPlans/Sketch13
09/06/2026M00034460-I1Request digital key ↗
08/30/2026M00884871-I1Request digital key ↗
08/29/2026M00918366-P1Request digital key ↗
Showing 3 of 13 on file for this type
▸Applications & Permits19
▸BISPLAN / WORK APPROVAL APPLICATION10
11/10/2021123684432Open ↗
08/10/2021122136786Open ↗
07/11/2019123684432Open ↗
Showing 3 of 10 on file for this type
▸BISWORK PERMIT APPLICATION9
06/17/2022122136786Open ↗
08/07/2019123684432Open ↗
01/31/2019123407848Open ↗
Showing 3 of 9 on file for this type
▸Seals & Professional Certifications27
▸DOB NOWDPL-1: Design Professional Seal & Signature13
08/29/2026M00918366-P1Open ↗
08/29/2026M00918366-I1Open ↗
08/29/2026M00918378-I1Open ↗
Showing 3 of 13 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION9
06/25/2019123407848Open ↗
06/24/2019123684432Open ↗
05/07/2019123412002Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/01/2026M00968569-S2Open ↗
09/01/2026M00968569-S2Open ↗
08/24/2026M00968569-P1Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
03/28/2018123412002Open ↗
▸Trade Schedules & Equipment9
▸BISSELF-CERT PLUMBING NOTICE4
11/09/2012120535340Open ↗
08/25/2011120535340Open ↗
06/02/2011120535340Open ↗
Showing 3 of 4 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE3
06/24/2019123684432Open ↗
01/04/2019123407848Open ↗
07/19/2017122136786Open ↗
▸BISSCHEDULE B - PLUMBING2
06/28/2012120535340Open ↗
11/22/2010120535340Open ↗
▸Safety & Tenant Protection4
▸BISTenant Protection Plan and Notes4
06/24/2019123684432Open ↗
01/04/2019123407848Open ↗
03/28/2018123412002Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos6
▸BISASBESTOS: CERTIFICATION (DEP ACP5)4
07/11/2019123684432Open ↗
01/04/2019123407848Open ↗
03/28/2018123412002Open ↗
Showing 3 of 4 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
11/22/2010120535340Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026M00884871-I1Open ↗
▸Energy Compliance10
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS6
06/25/2019123407848Open ↗
06/24/2019123684432Open ↗
05/07/2019123412002Open ↗
Showing 3 of 6 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS3
06/12/2023122136786Open ↗
06/25/2019123407848Open ↗
05/07/2019123412002Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
06/12/2023122136786Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
06/12/2023122136786Open ↗
06/12/2023122136786Open ↗
▸Approvals, Objections & Sign-offs6
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST4
07/11/2023122136786Open ↗
06/25/2019123407848Open ↗
05/07/2019123412002Open ↗
Showing 3 of 4 on file for this type
▸BISADMINISTRATIVE OBJECTIONS1
11/22/2010120535340Open ↗
▸BISSUPERSEDING LETTER1
06/17/2022122136786Open ↗
▸Cost, Insurance & Ownership10
▸BISCOST AFFIDAVIT9
06/12/2023122136786Open ↗
06/25/2019123407848Open ↗
06/24/2019123684432Open ↗
Showing 3 of 9 on file for this type
▸BISHIC LICENSE OR AFFIDAVIT1
01/11/2019123407848Open ↗
▸Filing & Intake Forms10
▸BISEFILING COVER SHEET5
06/24/2019123684432Open ↗
01/04/2019123407848Open ↗
03/28/2018123412002Open ↗
Showing 3 of 5 on file for this type
▸BISBOROUGH INTAKE FORM3
06/17/2022122136786Open ↗
06/25/2019123407848Open ↗
05/07/2019123412002Open ↗
▸BISADDITIONAL INFORMATION2
06/24/2019123684432Open ↗
01/04/2019123407848Open ↗
▸Other Documents4
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION2
11/10/2021123684432Open ↗
07/17/2017122136786Open ↗
▸DOB NOWManufacturer's Specifications1
08/13/2026M00985386-I1Open ↗
▸DOB NOWCalculations1
08/13/2026M00985386-I1Open ↗