| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/10/2026 | Permit Issued | AMERICAN RESIDENTIAL CON* | Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/06/2026 | Permit Issued | FIREQUEST CORP | 36 heads |
| 10/09/2025 | Permit Issued | ARCO PLBG AND HTG INC | 5 heads |
| 02/08/2023 | — | — | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/06/2026 | Permit Issued | MT ENERGY INC | Water/Sanitary |
| 10/09/2025 | Signed-off | ARCO PLBG AND HTG INC | Water/Sanitary |
| 09/09/2022 | Permit Issued | SIGNORE & SONS PLBG CORP | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/19/2026 | Permit Issued | GM-POWER ELECTRIC CORP | General Wiring |
| 01/12/2026 | Permit Issued | CMY ELECTRICAL CORP | — |
| 01/12/2026 | Permit Issued | CMY ELECTRICAL CORP | General Wiring |
| 04/19/2024 | Complete | BOROWIDE ELECT'L CONTR'S | — |
| 12/19/2022 | Permit Issued | ALLSTATE ELECTRIC CORP | General Wiring |
| 11/03/2021 | Permit Issued | MAUCERI ELECTRIC CORP. | General Wiring |
| 01/05/2021 | Complete | SUPREME ELECTRIC CORP | General Wiring |
| 06/14/2018 | Complete | AUJLA ELECTRIC CORP | General Wiring, Lighting |
| 06/07/2018 | Complete | FIBERTEK DATA & ELEC CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/06/2026 | Permit Issued | FIREQUEST CORP | Tenant Protection Plan 72 Hour |
| Owner | Filings | Most Recent |
|---|---|---|
| 108-114 WOOSTER STREET | 62 | 09/13/2026 |
| FIRST SERVICE RESIDENTIAL | 9 | 07/08/2026 |
| 108-114 WOOSTER | 12 | 03/22/2026 |
| THE ANDREWS ORGANIZATION | 1 | 03/21/2026 |
| ANDREWS BUILDING | 4 | 03/21/2026 |
| 108 WOOSTER STREET | 6 | 03/21/2026 |
| 108-114 4 WOOSTER STREET | 2 | 03/21/2026 |
| 108 114 WOOSTER ST CORP C O ANDR | 3 | 03/21/2026 |
| 108 WOOSTER STREET OWNERS | 2 | 03/21/2026 |
| 108-114 WO | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ALL HANDS ARCHITECTURE PLLC | 1 | 07/07/2026 |
| E4P CONSULTING ENGINEERING PLLC | 5 | 06/10/2026 |
| COLLECTIF ENGINEERING PLLC | 1 | 01/06/2026 |
| ESNYC CONSULTING INC | 1 | 11/19/2025 |
| SPENCER ENGINEERING, PC | 6 | 10/09/2025 |
| SW ENGINEERING COMPANY | 5 | 08/16/2024 |
| MSM ENGINEERING SERVICES, PLLC | 2 | 04/12/2024 |
| LEON SKVIRSKY PE | 1 | 02/01/2024 |
| YAO W GUO ARCHITECT, PC | 3 | 03/17/2023 |
| THE EIPEL ENGINEERING GROUP, D.P.C. | 1 | 12/21/2022 |
| WILLIAM LENART, ARCHITEC PLLC | 2 | 12/19/2022 |
| MQ CONSULTING | 1 | 12/19/2022 |
| CHARLES G. MICHEL ENGINEERING, PC. | 1 | 09/09/2022 |
| ARCHITECTURE+CONSTRUCTION, PLLC | 1 | 06/29/2022 |
| SZEKELY ENGINEERING | 1 | 10/05/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| BOYD CONSULTING | 10 | 03/21/2026 |
| EA DESIGN GROUP | 8 | 03/21/2026 |
| ARCHVISION DESIGN STUDIO | 2 | 03/21/2026 |
| BUILDING BROTHERS | 2 | 03/21/2026 |
| SRA ARCHITECTURE + ENGINEERING | 12 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ANDAMIO SCAFFOLDING LLC | General Contractor | 6 | 03/21/2026 |
| SF CONSTRUCTION EXPERTS | General Contractor | 4 | 04/09/2026 |
| D.B.J. CONTRACTING CORP | General Contractor | 3 | 07/08/2026 |
| A W R GROUP INC | General Contractor | 2 | 03/21/2026 |
| KAPNAG HEATING & PLBG COR | Fire Protection | 2 | 07/08/2026 |
| PATH MECHANICAL CORP | General Contractor | 2 | 03/21/2026 |
| BURA CONSTRUCTION CORP | General Contractor | 2 | 03/21/2026 |
| M & E GUNDERSEN CONSTRUCT | General Contractor | 1 | 07/08/2026 |
| ADRIAS PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| ARCO PLBG AND HTG INC | Plumbing | 1 | 07/08/2026 |
| KAPNAG HTG & PLBG CORP. | Plumbing | 1 | 07/08/2026 |
| MT ENERGY INC | Plumbing | 1 | 07/08/2026 |
| ORBIT PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| SIGNORE & SONS PLBG CORP | Plumbing | 1 | 07/08/2026 |
| DICAPUA, JOHN | Electrical | 1 | 03/21/2026 |
| PAUL SIGNS | Scaffold | 1 | 07/08/2026 |
| JOHN DICAPUA | Electrical | 1 | 03/21/2026 |
| ARCO PLBG AND HTG INC | Fire Protection | 1 | 07/08/2026 |
| FIREQUEST CORP | Fire Protection | 1 | 07/08/2026 |
| METFLOW FIRE CONTROL LLC | Fire Protection | 1 | 07/08/2026 |
| AMERICAN RESIDENTIAL CON* | General Contractor | 1 | 06/27/2026 |
| COAST BUILDING MANAGEMENT | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PROJECT TACTICAL SOLUTION | 5859 | 7 | 06/10/2026 |
| ESNYC CONSULTING INC | 4099 | 2 | 01/06/2026 |
| SA-DA ARCHITECTURE | 2640 | 1 | 01/06/2026 |
| SE INSPECTIONS | 7486 | 4 | 10/09/2025 |
| SRA INSPECTIONS | 3461 | 2 | 10/09/2025 |
| YAO W GUO ARCHITECT P.C. | 1754 | 1 | 02/08/2023 |
| AK ENGINEERING PC | 678 | 3 | 12/21/2022 |
| CHARLES G MICHEL ENGINEER | 2871 | 1 | 09/09/2022 |
| SZEKELY ENGINEERING | 299 | 1 | 10/05/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | AMERICAN RESIDENTIAL CON* | 06/24/2026 |
| DOB NOW | Plumbing | Permit Issued | FIREQUEST CORP | 06/18/2026 |
| DOB NOW | Plumbing | Permit Issued | ORBIT PLBG & HTG INC | 06/18/2026 |
| DOB NOW | General Construction | Permit Issued | SF CONSTRUCTION EXPERTS | 03/20/2026 |
| DOB NOW | Sprinklers | Permit Issued | MT ENERGY INC | 02/10/2026 |
| DOB NOW | Mechanical Systems | Signed-off | COAST BUILDING MANAGEMENT | 12/11/2025 |
| DOB NOW | General Construction | Permit Issued | SF CONSTRUCTION EXPERTS | 12/10/2025 |
| DOB NOW | Sprinklers | Permit Issued | ARCO PLBG AND HTG INC | 11/05/2025 |
| DOB NOW | Plumbing | Signed-off | ARCO PLBG AND HTG INC | 11/05/2025 |
| DOB NOW | General Construction | Signed-off | A W R GROUP INC | 08/13/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | M & E GUNDERSEN CONSTRUCT | 07/17/2024 |
| DOB NOW | Sprinklers | Signed-off | KAPNAG HEATING & PLBG COR | 05/10/2024 |
| DOB NOW | Supported Scaffold | Signed-off | ANDAMIO SCAFFOLDING LLC | 04/12/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | ANDAMIO SCAFFOLDING LLC | 04/12/2024 |
| DOB NOW | Sign | Signed-off | PAUL SIGNS, INC | 02/02/2024 |
| DOB NOW | General Construction | Permit Issued | BURA CONSTRUCTION | 02/24/2023 |
| DOB NOW | Plumbing | Signed-off | KAPNAG HTG & PLBG CORP. | 02/08/2023 |
| DOB NOW | Plumbing | Signed-off | KAPNAG HEATING & PLBG COR | 02/08/2023 |
| DOB NOW | Structural | Signed-off | DBJ CONTRACTING | 02/08/2023 |
| DOB NOW | General Construction | Signed-off | DBJ CONTRACTING | 02/07/2023 |
| DOB NOW | Plumbing | Permit Issued | SIGNORE & SONS PLBG CORP | 09/06/2022 |
| DOB NOW | General Construction | Signed-off | DBJ CONTRACTING | 07/28/2022 |
| DOB NOW | Mechanical Systems | Signed-off | PATH MECHANICAL CORP | 10/26/2021 |
| DOB NOW | Plumbing | Signed-off | ADRIAS PLUMBING CORP | 02/06/2020 |
| DOB NOW | Sprinklers | Permit Issued | METFLOW FIRE CONTROL LLC | 02/04/2020 |
| BIS | OT | ISSUED | M & E GUNDERSEN CONSTRUCT | 04/13/2022 |
| BIS | SP | ISSUED | NONSTOP PLUMBERS CORP | 02/01/2021 |
| BIS | OT | ISSUED | FIGURE GROUND INC | 01/26/2021 |
| BIS | PL | ISSUED | AUTHENTIC PLBG CORP | 01/08/2021 |
| BIS | OT | ISSUED | IGUANA SERVICES INC | 11/04/2020 |
| BIS | OT | ISSUED | STEADFAST DEVELOPMENT AND | 10/22/2019 |
| BIS | OT | ISSUED | UGB CONSTRUCTION INC | 05/15/2018 |
| BIS | OT | ISSUED | UGB CONSTRUCTION INC | 05/15/2018 |
| BIS | OT | ISSUED | UGB CONSTRUCTION INC | 02/14/2018 |
| BIS | PL | ISSUED | J.A. MECH. PLBG. & HTG IN | 12/06/2017 |
| BIS | SP | ISSUED | PHILTON CONTRACTING, LLC | 07/13/2017 |
| BIS | OT | ISSUED | USMAN G. BHUTTA | 03/17/2017 |
| BIS | — | ISSUED | FIVE TOWN NEON SIGN CO IN | 06/19/2015 |
| BIS | PL | ISSUED | F.S. SITE CORP | 11/01/2012 |
| BIS | PL | ISSUED | F.S. SITE CORP | 11/01/2012 |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/10/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 07/08/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/08/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/24/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/10/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/10/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/10/2024 | Certified Sprinkler - SP - Roughing | Certified | View ↗ |
| 10/18/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/12/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/31/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/31/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Water Test | Certified | View ↗ |
| 03/02/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/23/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/25/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/05/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/03/2026 | Final | Benjamin Carr | progress |
| 06/04/2026 | HVAC-R and service water heating system controls | Max Lee | energy_progress |
| 06/04/2026 | HVAC-R and service water heating equipment | Max Lee | energy_progress |
| 06/04/2026 | Maintenance information | Max Lee | energy_progress |
| 06/04/2026 | Tenant Protection Plan Compliance | Max Lee | special |
| 06/04/2026 | Fire-Resistant Penetrations and Joints | Max Lee | special |
| 06/04/2026 | HVAC-R and service water piping design and insulation | Max Lee | energy_progress |
| 06/04/2026 | Tenant Protection Plan Compliance | Max Lee | special |
| 06/04/2026 | Final | Max Lee | progress |
| 06/04/2026 | Shutoff dampers | Max Lee | energy_progress |
| 06/04/2026 | Energy Code Compliance Inspections | Max Lee | progress |
| 06/04/2026 | HVAC-R and service water piping design and insulation | Max Lee | energy_progress |
| 06/04/2026 | Mechanical Systems | Max Lee | special |
| 06/04/2026 | Fire-Resistant Penetrations and Joints | Max Lee | special |
| 06/04/2026 | Post-installed Anchors | Max Lee | special |
| 05/21/2026 | Interior lighting power | Max Lee | energy_progress |
| 05/21/2026 | Lighting controls | Max Lee | energy_progress |
| 05/21/2026 | Energy Code Compliance Inspections | Max Lee | progress |
| 04/20/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 04/20/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 04/20/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 04/20/2026 | Energy Code Compliance Inspections | — | progress |
| 04/14/2026 | Final | Max Lee | progress |
| 04/14/2026 | Fire-Resistant Penetrations and Joints | Max Lee | special |
| 04/14/2026 | Fire-Resistance Rated Construction | Max Lee | progress |