ECB07/10/2025AT TIME OF INSPECTION OBSERVED ELECTRICAL WORK BEING DONE TO NEWLY CONSTRUCTED GARAGE AT EXPO 3 OF PROPERTY; NEW ELECTRICAL WIRING, OUTLETS AND BREAKER BOX BEING INSTALLED. ELECTRICAL WORK IS APPROX 50% COMPLET$8K due
ECB07/10/2025AT TIME OF INSPECTION WAS ABLE TO GAIN ACCESS TO COMPLAINT AREA ( GARAGE AT EXPO 3), OBSERVED NEWLY CONSTRUCTED V ROOF GARAGE APPROX 12'LX12'WX10'H ; AND FRESHLY POURED CONCRETE FLOOR (10% COMPLETED).OVERALL GA$12K due
Two family converted from one family · 3,518 sf lot · 0.47 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.