| Owner | Filings | Most Recent |
|---|---|---|
| Fabio Realty | 3 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| BFS Architect | 7 | 10/25/2024 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| 5 Points Rehab | General Contractor | 8 | 07/08/2026 |
| Lemode Plumbing & Heating | specialty_contractor | 4 | 07/08/2026 |
| 5 Points Rehab | specialty_contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BFS Architect | 7477 | 6 | 10/25/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Foundation | Permit Issued | 5 Points Rehab | 03/25/2026 |
| DOB NOW | Mechanical Systems | Signed-off | 5 Points Rehab | 01/08/2025 |
| DOB NOW | Foundation | Permit Issued | 5 Points Rehab | 02/06/2024 |
| DOB NOW | Sprinklers | Signed-off | Lemode Plumbing & Heating | 10/19/2023 |
| DOB NOW | Plumbing | Signed-off | Lemode Plumbing & Heating | 10/19/2023 |
| DOB NOW | Plumbing | Signed-off | Lemode Plumbing & Heating | 10/03/2023 |
| DOB NOW | General Construction | Signed-off | 5 Points Rehab | 06/06/2023 |
| DOB NOW | Plumbing | Signed-off | Lemode Plumbing & Heating | 09/26/2022 |
| DOB NOW | General Construction | Signed-off | 5 Points Rehab | 09/19/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/25/2024 | Permit Issued | 5 Points Rehab | Heating Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/25/2024 | Signed-off | Lemode Plumbing & Heating | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/25/2024 | Signed-off | Lemode Plumbing & Heating | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/14/2023 | Complete | AL Electrical Group | General Wiring |
| 01/24/2023 | Complete | AL Electrical Group | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/27/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 01/14/2025 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 12/18/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/17/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/14/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/22/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 12/01/2023 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 12/01/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 12/01/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/01/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 11/29/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/26/2024 | Structural Stability – Alterations of existing buildings | Belal Salim | special |
| 11/26/2024 | Concrete - Cast-In-Place | Belal Salim | special |
| 11/26/2024 | Subgrade Inspections | Belal Salim | special |
| 11/26/2024 | Fire-Resistant Penetrations and Joints | Belal Salim | special |
| 11/26/2024 | Masonry | Belal Salim | special |
| 11/26/2024 | Energy Code Compliance Inspections | Belal Salim | progress |
| 11/26/2024 | Subsurface Investigations (Borings/Test Pits) | BRIAN FLYNN | special |
| 11/26/2024 | Final | Belal Salim | progress |
| 11/26/2024 | Fire-Resistance Rated Construction | Belal Salim | progress |
| 11/26/2024 | Footing and Foundation | Belal Salim | progress |
| 11/26/2024 | Fenestration air leakage | Belal Salim | energy_progress |
| 11/26/2024 | Permanent certificate | Belal Salim | energy_progress |
| 11/26/2024 | Insulation placement and R values | Belal Salim | energy_progress |
| 11/26/2024 | Air barrier - visual inspection | Belal Salim | energy_progress |
| 11/26/2024 | Interior lighting power | Belal Salim | energy_progress |
| 11/26/2024 | Fenestration and door U-factor and product ratings | Belal Salim | energy_progress |
| 11/26/2024 | Air barrier — testing | Belal Salim | energy_progress |
| 11/26/2024 | Fenestration areas | Belal Salim | energy_progress |
| 11/26/2024 | Maintenance information | Belal Salim | energy_progress |
| 11/26/2024 | Metering | Belal Salim | energy_progress |
| 03/20/2024 | HVAC-R and service water heating system controls | Belal Salim | energy_progress |
| 03/20/2024 | Sprinkler Systems | Belal Salim | special |
| 03/20/2024 | Fire-Resistant Penetrations and Joints | Belal Salim | special |
| 03/20/2024 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | Belal Salim | special |
| 03/20/2024 | Post-installed Anchors | Belal Salim | special |