| Owner | Filings | Most Recent |
|---|---|---|
| ALPHA DEVELOPMENT | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 10/17/2025 | $885K | — | Private party → Private party | $740/sf building |
| 02/25/2025 | $685K | — | — → — | $573/sf building |
| 06/22/2023 | $485K | — | Private party → Private party | $406/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| PARKER AND WEST ENGINEERING, PLLC | 1 | 11/20/2025 |
| TABRIZ GROUP ENTERPRISES | 1 | 02/26/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| SUNRUN | 1 | 03/21/2026 |
| TABRIZ GROUP ENTERPRISE | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SUNRUN INSTALLATION SVC | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PARKER AND WEST ENGINEERI | 5272 | 1 | 11/20/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | SUNRUN INSTALLATION SVC | 11/25/2025 |
| BIS | — | ISSUED | GUERRERO'S INC | 06/19/2007 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/03/2025 | Complete | CUNNINGHAM ELECTRIC CORP | General Wiring |
| 11/20/2025 | Complete | SUNRUN SOLAR ELECTL CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/26/2025 | — | — | 1 scope_items |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/20/2025 | Air barrier - visual inspection | Walid Abdulla | energy_progress |
| 11/20/2025 | Structural Stability – Alterations of existing buildings | Walid Abdulla | special |
| 11/19/2025 | Fire-Resistant Penetrations and Joints | Walid Abdulla | special |
| 11/19/2025 | Energy Code Compliance Inspections | Walid Abdulla | progress |
| 11/19/2025 | Final | Walid Abdulla | progress |
| 02/11/2025 | Masonry | — | special |
| 02/11/2025 | Structural Stability – Alterations of existing buildings | — | special |
| 02/11/2025 | Energy Code Compliance Inspections | — | progress |
| 02/11/2025 | Fire-Resistance Rated Construction | — | progress |
| 02/11/2025 | Permanent certificate | — | energy_progress |
| 02/11/2025 | Subsurface Investigations (Borings/Test Pits) | — | special |
| 02/11/2025 | Concrete - Cast-In-Place | — | special |
| 02/11/2025 | Excavations - Sheeting, Shoring, and Bracing | — | special |
| 02/11/2025 | Fire-Resistant Penetrations and Joints | — | special |
| 02/11/2025 | Metering | — | energy_progress |
| 02/11/2025 | Electric vehicle service equipment requirements | — | energy_progress |
| 02/11/2025 | Fenestration areas | — | energy_progress |
| 02/11/2025 | Fenestration air leakage | — | energy_progress |
| 02/11/2025 | Interior lighting power | — | energy_progress |
| 02/11/2025 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 02/11/2025 | Maintenance information | — | energy_progress |
| 02/11/2025 | Insulation placement and R values | — | energy_progress |
| 02/11/2025 | Air barrier - visual inspection | — | energy_progress |
| 01/28/2025 | Footing and Foundation | — | progress |
| 01/28/2025 | Final | — | progress |