| Owner | Filings | Most Recent |
|---|---|---|
| LEMOR DEVELOPMENT GROUP | 6 | 09/19/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ETTINGER ENGINEERING ASSOCIATES | 4 | 08/18/2026 |
| CITYSCAPE ENGINEERING, PLLC | 4 | 08/14/2026 |
| PRONTO ENGINEERING | 1 | 03/12/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| DVA Advisors | 1 | 03/21/2026 |
| WILLIAM VITACCO ASSOCIATES | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| FOREMOST CONTRACTING & BU | General Contractor | 3 | 07/08/2026 |
| ISAAC KRITZLER | Electrical | 1 | 03/21/2026 |
| FIVE BOROUGH NYC LLC | Fire Protection | 1 | 09/19/2026 |
| RELIABLE PLBG & HTG CORP | Plumbing | 1 | 06/28/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AMERICAN CONSTRUCTION TES | 9731 | 7 | 08/18/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Permit Issued | FIVE BOROUGH NYC LLC | 09/18/2026 |
| DOB NOW | Plumbing | Permit Issued | RELIABLE PLBG & HTG CORP | 06/18/2026 |
| DOB NOW | Support of Excavation | Permit Issued | FOREMOST CONTRACTING & BU | 04/21/2026 |
| DOB NOW | Structural | Permit Issued | FOREMOST CONTRACTING & BU | 04/21/2026 |
| DOB NOW | Construction Fence | Permit Issued | FOREMOST CONTRACTING & BU | 04/16/2026 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/29/2025 | Permit Issued | FIVE BOROUGH NYC LLC | 55 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/18/2026 | Permit Issued | RELIABLE PLBG & HTG CORP | Gas, Storm, Water/Sanitary |
| 08/29/2025 | — | — | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/26/2026 | Permit Issued | KEPLER ELECTRICAL CONT | 1 meters, 1 new_meters |
| 06/25/2026 | Permit Issued | KEPLER ELECTRICAL CONT | General Wiring |
| 12/20/2025 | Permit Issued | NATIONAL POWER ELECTRIC L | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/14/2026 | Permit Issued | FOREMOST CONTRACTING & BU | 2 scope_items |
| 08/14/2026 | Permit Issued | FOREMOST CONTRACTING & BU | Steel, Concrete, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/12/2026 | Permit Issued | FOREMOST CONTRACTING & BU | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/19/2026 | Fire-Resistant Penetrations and Joints | EDWIN HOPKINS | special |
| 08/17/2026 | Concrete - Precast | EDWIN HOPKINS | special |
| 08/17/2026 | Structural Steel - Welding | — | special |
| 08/17/2026 | Post-installed Anchors | — | special |
| 08/17/2026 | Structural Steel - High Strength Bolting | — | special |
| 08/17/2026 | Structural Cold-Formed Steel | EDWIN HOPKINS | special |
| 08/17/2026 | Masonry | EDWIN HOPKINS | special |
| 08/17/2026 | Structural Steel - Details | EDWIN HOPKINS | special |
| 08/17/2026 | Final | EDWIN HOPKINS | progress |
| 08/17/2026 | Concrete - Cast-In-Place | EDWIN HOPKINS | special |
| 06/25/2026 | Excavations - Sheeting, Shoring, and Bracing | EDWIN HOPKINS | special |