RoofCentury Development Group10p · 4 filings · 14 docs
ArchitectureDMElectricalGeneralMechanicalStructural
Issued Permit Scope
Protection and Mechanical Methods · Structural
Application for the installation and use of mobile equipment as per plans filed herein. No change in egress, use or occupancy.
On file for this project
2 documents · 1 drawing sheet
Installation of dunnage at rooftop filed to resolve violation; 39145804X.
On file for this project
5 documents · 2 drawing sheets
INSTALLATION OF 300 PSF SIDEWALK SHED, OVERHEAD PROTECTION, AND ROOF PROTECTION AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
4 documents · 4 drawing sheets
Latest 3 of 4 filings on this floor.
BulkheadMps Two, LLC1p · 1 filing · 3 docs
Fire Protection
PROPOSED TO CAP AND REMOVE SPRINKLER SYSTEM ,NO CHANGE TO USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
3 documents · 1 drawing sheet
Floor 9Century Development Group1p · 1 filing · 2 docs
Mechanical
Installation of a temporary roof and OHP protection per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
On file for this project
2 documents · 1 drawing sheet
Floor 8
Floor 7Century Development Group1p · 1 filing · 2 docs
Structural
Issued Permit Scope
Protection and Mechanical Methods
Application for the installation and use of mobile equipment as per plans filed herein. No change in egress, use or occupancy.
On file for this project
2 documents
Floor 6Century Development Group1p · 1 filing · 2 docs
Structural
Issued Permit Scope
Protection and Mechanical Methods
Application for the installation and use of mobile equipment as per plans filed herein. No change in egress, use or occupancy.
On file for this project
2 documents
Floor 5Century Development Group1p · 1 filing · 2 docs
Structural
Issued Permit Scope
Protection and Mechanical Methods
Application for the installation and use of mobile equipment as per plans filed herein. No change in egress, use or occupancy.
On file for this project
2 documents
Floor 4Century Development Group1p · 1 filing · 2 docs
Structural
Issued Permit Scope
Protection and Mechanical Methods
Application for the installation and use of mobile equipment as per plans filed herein. No change in egress, use or occupancy.
On file for this project
2 documents
Floor 3Century Development Group1p · 1 filing · 2 docs
Structural
Issued Permit Scope
Protection and Mechanical Methods
Application for the installation and use of mobile equipment as per plans filed herein. No change in egress, use or occupancy.
On file for this project
2 documents
Floor 2Century Development Group2p · 2 filings · 5 docs
Fire ProtectionStructural
Issued Permit Scope
Protection and Mechanical Methods · Sprinklers
Application for the installation and use of mobile equipment as per plans filed herein. No change in egress, use or occupancy.
On file for this project
2 documents
PROPOSED TO CAP AND REMOVE SPRINKLER SYSTEM ,NO CHANGE TO USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
3 documents
Floor 1Mps Two, LLC2p · 1 filing · 3 docs
DMFire Protection
Issued Permit Scope
Sprinklers
PROPOSED TO CAP AND REMOVE SPRINKLER SYSTEM ,NO CHANGE TO USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
3 documents · 1 drawing sheet
Site & exteriorCentury Development Group12p · 5 filings · 20 docs
ArchitectureCivilElectricalEquipmentGeneralMechanicalPlumbingStructural
Issued Permit Scope
Construction Fence · Protection and Mechanical Methods · Sidewalk Shed · Supported Scaffold
INSTALLATION OF PIPE SCAFFOLDING AND NEEDLE BEAM AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER # 33 OF THE 2022 CODE. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
12 documents · 12 drawing sheets
INSTALLATION OF 300 PSF SIDEWALK SHED, OVERHEAD PROTECTION, AND ROOF PROTECTION AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
4 documents · 9 drawing sheets
installation plywood fence in conjunction with demo job#421790574.
On file for this project
2 documents