Roof2p · 2 filings · 20 docs
ArchitectureEquipment
Facade repairs to the East, West, South and North elevations as indicated on drawings
On file for this job
18 documents · 1 drawing sheet
Renewal for Facade Restoration via Suspended Scaffolds
On file for this job
3 documents · 1 drawing sheet
Floor 231p · 1 filing · 4 docs
Electrical
Exterior lighting energy compliance for lighting work on the cellar and 3rd floor and crown lighting on the 1st, 4th, 16th, 19th, 21st, 22d and 23rd floor as indicated on drawings
On file for this job
4 documents · 1 drawing sheet
Floor 22Under Construction16p · 3 filings · 20 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Construction work on the 17th through 22nd floor (AMC) as indicated on drawings.
On file for this job
8 documents
Mechanical work on the 17th through 22nd floor (AMC) as indicated on drawings.
On file for this job
9 documents · 2 drawing sheets
Sprinkler work on the 17th through 22nd floor (AMC) as indicated on drawings.
On file for this job
7 documents · 2 drawing sheets
Floor 21Under Construction17p · 4 filings · 20 docs
ArchitectureElectricalFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Construction work on the 17th through 22nd floor (AMC) as indicated on drawings.
On file for this job
8 documents
Mechanical work on the 17th through 22nd floor (AMC) as indicated on drawings.
On file for this job
9 documents · 2 drawing sheets
Sprinkler work on the 17th through 22nd floor (AMC) as indicated on drawings.
On file for this job
7 documents · 2 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 20Under Construction15p · 3 filings · 20 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Construction work on the 17th through 22nd floor (AMC) as indicated on drawings.
On file for this job
8 documents
Mechanical work on the 17th through 22nd floor (AMC) as indicated on drawings.
On file for this job
9 documents · 2 drawing sheets
Sprinkler work on the 17th through 22nd floor (AMC) as indicated on drawings.
On file for this job
7 documents · 1 drawing sheet
Floor 19Under Construction18p · 5 filings · 20 docs
ArchitectureElectricalFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Construction work on the 17th through 22nd floor (AMC) as indicated on drawings.
On file for this job
8 documents
Mechanical work on the 17th through 22nd floor (AMC) as indicated on drawings.
On file for this job
9 documents · 2 drawing sheets
Sprinkler work on the 17th through 22nd floor (AMC) as indicated on drawings.
On file for this job
7 documents · 2 drawing sheets
Latest 3 of 5 filings on this floor.
Floor 18Under Construction24p · 6 filings · 20 docs
ArchitectureElectricalFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Construction work on the 17th through 22nd floor (AMC) as indicated on drawings.
On file for this job
8 documents
Mechanical work on the 17th through 22nd floor (AMC) as indicated on drawings.
On file for this job
9 documents · 2 drawing sheets
Sprinkler work on the 17th through 22nd floor (AMC) as indicated on drawings.
On file for this job
7 documents · 2 drawing sheets
Latest 3 of 6 filings on this floor.
Floor 17Under Construction16p · 3 filings · 20 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Construction work on the 17th through 22nd floor (AMC) as indicated on drawings.
On file for this job
8 documents
Mechanical work on the 17th through 22nd floor (AMC) as indicated on drawings.
On file for this job
9 documents · 2 drawing sheets
Sprinkler work on the 17th through 22nd floor (AMC) as indicated on drawings.
On file for this job
7 documents · 2 drawing sheets
Floor 16Under Construction5p · 5 filings · 20 docs
ArchitectureCivilElectricalFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Replacement of air handling units on the 15th and 16th floor as indicated on drawings.
On file for this job
14 documents
GENERAL CONSTRUCTION MODIFICATIONS TAKING PLACE ON THE 15TH - 16TH FLOORS AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this job
5 documents
Removal of sprinkler heads and installation of temporary sprinkler loop on the 15th and 16th floor as indicated on drawings.
On file for this job
4 documents · 2 drawing sheets
Latest 3 of 5 filings on this floor.
Floor 15Under Construction2p · 3 filings · 20 docs
ArchitectureFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Replacement of air handling units on the 15th and 16th floor as indicated on drawings.
On file for this job
14 documents
GENERAL CONSTRUCTION MODIFICATIONS TAKING PLACE ON THE 15TH - 16TH FLOORS AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this job
5 documents
Removal of sprinkler heads and installation of temporary sprinkler loop on the 15th and 16th floor as indicated on drawings.
On file for this job
4 documents · 1 drawing sheet
Floor 1415p · 6 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
General construction modification within floors 11 to 14 as per plans filed herewith. No change in use, egress, or occupancy.
On file for this job
7 documents · 3 drawing sheets
Mechanical modification to floors 11 and 14 as per plans filed herewith. No change in use, egress, or occupancy.
On file for this job
13 documents · 4 drawing sheets
Sprinkler modification on floors 11 to 14 as per plans filed herewith. No change in use, egress, or occupancy.
On file for this job
4 documents · 2 drawing sheets
Latest 3 of 6 filings on this floor.
Floor 1316p · 9 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction
GENERAL CONSTRUCTION MODIFICATIONS TAKING PLACE ON THE 13TH FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this job
7 documents
MECHANICAL MODIFICATIONS TAKING PLACE ON THE 13TH FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this job
6 documents · 1 drawing sheet
General construction modification within floors 11 to 14 as per plans filed herewith. No change in use, egress, or occupancy.
On file for this job
7 documents · 3 drawing sheets
Latest 3 of 8 filings on this floor.
Floor 1214p · 6 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
General construction modification within floors 11 to 14 as per plans filed herewith. No change in use, egress, or occupancy.
On file for this job
7 documents · 3 drawing sheets
Mechanical modification to floors 11 and 14 as per plans filed herewith. No change in use, egress, or occupancy.
On file for this job
13 documents · 3 drawing sheets
Sprinkler modification on floors 11 to 14 as per plans filed herewith. No change in use, egress, or occupancy.
On file for this job
4 documents · 2 drawing sheets
Latest 3 of 6 filings on this floor.
Floor 1114p · 6 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
General construction modification within floors 11 to 14 as per plans filed herewith. No change in use, egress, or occupancy.
On file for this job
7 documents · 2 drawing sheets
Mechanical modification to floors 11 and 14 as per plans filed herewith. No change in use, egress, or occupancy.
On file for this job
13 documents · 3 drawing sheets
Sprinkler modification on floors 11 to 14 as per plans filed herewith. No change in use, egress, or occupancy.
On file for this job
4 documents · 2 drawing sheets
Latest 3 of 6 filings on this floor.
Floor 1016p · 7 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Facade repairs to the East, West, South and North elevations as indicated on drawings
On file for this job
18 documents · 1 drawing sheet
General construction modification on floors 9 & 10 per plans filed herewith. No change in use, egress nor occupancy.
On file for this job
8 documents · 4 drawing sheets
Standpipe modification on floors 9 & 10 per plans filed herewith. No change in use, egress nor occupancy.
On file for this job
3 documents · 1 drawing sheet
Latest 3 of 7 filings on this floor.
Floor 912p · 6 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
General construction modification on floors 9 & 10 per plans filed herewith. No change in use, egress nor occupancy.
On file for this job
8 documents · 2 drawing sheets
Standpipe modification on floors 9 & 10 per plans filed herewith. No change in use, egress nor occupancy.
On file for this job
3 documents · 1 drawing sheet
Plumbing modification on floors 9 & 10 per plans filed herewith. No change in use, egress nor occupancy.
On file for this job
3 documents · 2 drawing sheets
Latest 3 of 6 filings on this floor.
Floor 813p · 10 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
PLUMBING MODIFICATIONS TAKING PLACE ON THE 8TH FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this job
3 documents · 1 drawing sheet
GENERAL CONSTRUCTION MODIFICATIONS TAKING PLACE ON THE 8TH FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this job
5 documents · 2 drawing sheets
SPRINLER MODIFICATIONS TAKING PLACE ON THE 8TH FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this job
4 documents · 1 drawing sheet
Latest 3 of 8 filings on this floor.
Floor 710p · 3 filings · 20 docs
ArchitectureMechanicalPlumbing
Plumbing modification on floors 5 through 7 as per plans filed herewith. No change in use, egress, or occupancy.
On file for this job
6 documents · 1 drawing sheet
General construction modification on floors 5 through 7 as per plans filed herewith. No change in use, egress, or occupancy.
On file for this job
10 documents · 6 drawing sheets
Mechanical modification on floors 5 through 7 as per plans filed herewith. No change in use, egress, or occupancy.
On file for this job
12 documents · 3 drawing sheets
Floor 611p · 3 filings · 20 docs
ArchitectureDMMechanicalPlumbing
Plumbing modification on floors 5 through 7 as per plans filed herewith. No change in use, egress, or occupancy.
On file for this job
6 documents · 1 drawing sheet
General construction modification on floors 5 through 7 as per plans filed herewith. No change in use, egress, or occupancy.
On file for this job
10 documents · 7 drawing sheets
Mechanical modification on floors 5 through 7 as per plans filed herewith. No change in use, egress, or occupancy.
On file for this job
12 documents · 3 drawing sheets
Floor 5Under Construction12p · 5 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
STRUCTURAL MODIFICATIONS TAKING PLACE ON THE 4TH FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this job
3 documents · 1 drawing sheet
Plumbing modification on floors 5 through 7 as per plans filed herewith. No change in use, egress, or occupancy.
On file for this job
6 documents · 1 drawing sheet
Sprinkler modifications on floors 5 through 7 as per plans filed herewith. No change in use, egress, or occupancy.
On file for this job
10 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Floor 4Under Construction59p · 12 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
GENERAL CONSTRUCTION MODIFICATIONS TAKING PLACE ON THE 4TH FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this job
6 documents · 3 drawing sheets
PLUMBING MODIFICATIONS TAKING PLACE ON THE 4TH FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this job
3 documents · 2 drawing sheets
MECHANICAL MODIFICATIONS TAKING PLACE ON THE 4TH FLOOR AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this job
3 documents · 3 drawing sheets
Latest 3 of 8 filings on this floor.
Floor 311p · 5 filings · 20 docs
ArchitectureDMGeneralMechanicalStructural
Issued Permit Scope
Mechanical Systems
Mechanical modifications taking place on 3rd floor as per plans filed herewith. No change in use, egress or occupancy.
On file for this job
14 documents · 1 drawing sheet
General Construction Modification of 3rd floor per plans filed herewith. No change in egress, use, or occupancy.
On file for this job
3 documents · 1 drawing sheet
General construction to the 3rd floor as per plans filed herewith. No change in use, egress, or occupancy.
On file for this job
5 documents · 2 drawing sheets
Latest 3 of 5 filings on this floor.
Floor 2Under Construction13p · 6 filings · 20 docs
ArchitectureElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Structural
Structural work to infill floor slab on the 2nd floor as indicated on drawings.
On file for this job
5 documents
Plumbing work on the 1st floor (Talea) as indicated on drawings
On file for this job
3 documents · 1 drawing sheet
Mechanical work on the 2nd and 18th floor (AMC) as indicated on drawings
On file for this job
4 documents · 2 drawing sheets
Latest 3 of 6 filings on this floor.
Floor 130p · 15 filings · 20 docs
ArchitectureDMElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Structural
Removal MSG sign supporting structure and minor facade repair as indicated on drawings
On file for this job
5 documents
Mechanical work on the 1st floor (Talea) as indicated on drawings.
On file for this job
6 documents · 1 drawing sheet
removal of non-bearing partitions, millwork & finishes. no change in use, egress or occupancy.
On file for this job
3 documents · 1 drawing sheet
Latest 3 of 8 filings on this floor.
MezzanineUnder Construction1p · 1 filing · 4 docs
GeneralStructural
Issued Permit Scope
Structural
Structural work to remove the 2nd floor mezzanine as indicated on drawings.
On file for this job
4 documents · 1 drawing sheet
Basement4p · 2 filings · 8 docs
MechanicalOther
Interior demolition of non load bearing partitions on the basement and 1st floor as indicated on drawings.
On file for this job
4 documents · 1 drawing sheet
Chiller replacement on sub-cellar 2 as indicated on drawings
On file for this job
4 documents · 3 drawing sheets
Sub-BasementUnder Construction1 filing · 4 docs
Architecture
Issued Permit Scope
General Construction
Interior demolition of non load bearing partitions on the basement level and 1st floor as indicated on drawings.
On file for this job
4 documents