| Owner | Filings | Most Recent |
|---|---|---|
| JERRICK ASSOCIATES | 21 | 07/08/2026 |
| NEW BEDFORD MANAGEMENT | 14 | 07/08/2026 |
| HLZIMMERMAN ARCHITECTS | 6 | 04/09/2026 |
| EMPIRE STATE LOFTS LIMITED | 36 | 03/22/2026 |
| YORK RESTORATION CORP | 1 | 03/22/2026 |
| ABC REALTY | 12 | 03/22/2026 |
| OWNER OF 11 W 30 ST | 1 | 03/22/2026 |
| EMPIRE LOFTS LIMITED | 5 | 03/21/2026 |
| ABC MANAGEMENT | 2 | 03/21/2026 |
| HI-CONSTRUCTION | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ABS ENGINEERING, PLLC | 2 | 08/06/2026 |
| ENV ARCHITECTS, DPC | 2 | 08/03/2026 |
| PIRO STUDIO LLC | 15 | 06/18/2026 |
| RYALL SHERIDAN CARROLL ARCHITECTS | 3 | 06/09/2026 |
| BEN HERZOG ARCHITECT PC | 2 | 03/09/2026 |
| HOWARD L ZIMMERMAN ARCH & ENG DPC | 6 | 12/11/2025 |
| STUDIO NYANDAK ARCHITECTURE AND ENG | 3 | 09/04/2025 |
| HUAN DESIGN INC. | 2 | 08/28/2025 |
| HIGH LINE ENGINEERING PC | 2 | 05/12/2025 |
| PAUL PERDEK, PROF. ENG. PLLC | 7 | 10/29/2024 |
| J. MEDINA ENGINEERING LLC | 1 | 03/25/2024 |
| VINCENT J. LIOTTA P.E. | 1 | 01/22/2024 |
| LEE ALTO DESIGN LLC | 2 | 12/04/2023 |
| ALLEN + KILLCOYNE ARCHITECTS LLP | 1 | 07/13/2021 |
| JACK STONE ENGINEERS, PC | 2 | 07/12/2021 |
| ALL MAKES HEATING AND AC CORP. | 1 | 03/10/2020 |
| MITCHELL OWEN ARCHITECTURE, PLLC | 1 | 02/14/2020 |
| ALLEN SHINFELD, P.E. PLLC | 1 | 08/23/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| DI DIO ARCHITECTURE, PC | 26 | 03/21/2026 |
| DYNAMIC BUILDING CONSULTANTS | 4 | 03/21/2026 |
| RIGHT WAY SERVICES NYC | 8 | 03/21/2026 |
| HLZAE | 6 | 03/21/2026 |
| AE DESIGN SOLUTION | 14 | 03/21/2026 |
| DOMANI CONSULTING | 3 | 03/21/2026 |
| MUNICIPAL BUILDING CONSULTANTS | 1 | 03/21/2026 |
| YOUN DESIGN CORP | 2 | 03/21/2026 |
| LEE ALTO DESIGN | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JERRICK ASSOCIATES INC | General Contractor | 9 | 07/08/2026 |
| SOHOME WORK INC | General Contractor | 6 | 07/08/2026 |
| ABCAT ASSOCIATES INC | General Contractor | 4 | 04/09/2026 |
| PREMIER COOLING SERVICES | General Contractor | 3 | 03/21/2026 |
| P.T. CONSTRUCTION GROUP | General Contractor | 3 | 03/21/2026 |
| PETER DANIELSSON | Electrical | 3 | 03/21/2026 |
| LOCAL UNION 40 | Electrical | 2 | 03/21/2026 |
| WG PROJECT MANAGEMENT INC | General Contractor | 2 | 04/09/2026 |
| WINSON CONSTRUCTION INC | General Contractor | 2 | 04/09/2026 |
| NORBERT KOCAN | General Contractor | 2 | 03/21/2026 |
| VAN VASSELL | Electrical | 2 | 03/21/2026 |
| KORMAN, NEIL | Electrical | 2 | 03/21/2026 |
| CERTIFIED SERVICES AND | Plumbing | 1 | 07/08/2026 |
| DV PLUMBING INC | Plumbing | 1 | 07/10/2026 |
| GBL MECHANICAL INC | Plumbing | 1 | 07/08/2026 |
| JOHN FITZGERALD PLBG &HTG | Plumbing | 1 | 07/08/2026 |
| DUNWELL ELEVATOR ELEC | Electrical | 1 | 03/22/2026 |
| VAND MECHANICAL INC | Plumbing | 1 | 06/28/2026 |
| HINKE, WILLIAM | Electrical | 1 | 03/21/2026 |
| JACKUS, STEVE | Electrical | 1 | 03/21/2026 |
| NICHOLAS BLASONE | Electrical | 1 | 03/21/2026 |
| SANG CHEUNG | Electrical | 1 | 03/21/2026 |
| CROSSFIELD PLBG.&HTG.CORP | Fire Protection | 1 | 07/08/2026 |
| RRP PLUMBING CORP | Fire Protection | 1 | 07/08/2026 |
| AA CAPRI CONSTRUCTION | General Contractor | 1 | 06/28/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ABS ENGINEERING, PLLC | 4835 | 2 | 08/06/2026 |
| PIRO STUDIO LLC | 7503 | 14 | 06/15/2026 |
| ALAN MARGOLIN & ASSOC | 423 | 2 | 03/09/2026 |
| HOWARD L ZIMMERMAN ARCHIT | 1712 | 8 | 12/31/2025 |
| STUDIO NYANDAK ARCHITECTU | 8378 | 3 | 09/04/2025 |
| ADAL ENGINEERING PLLC | 4205 | 1 | 08/28/2025 |
| HUAN DESIGN INC | 7669 | 1 | 08/27/2025 |
| HIGH LINE ENGINEERING PC | 2920 | 2 | 05/12/2025 |
| J. MEDINA ENGINEERING LLC | 7034 | 1 | 03/25/2024 |
| VINCENT J. LIOTTA P. E. | 1974 | 1 | 01/22/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | FRANCHISE INTERIOR DEVELO | 09/24/2026 |
| DOB NOW | Plumbing | Permit Issued | DV PLUMBING INC | 07/08/2026 |
| DOB NOW | General Construction | Permit Issued | AA CAPRI CONSTRUCTION | 06/26/2026 |
| DOB NOW | General Construction | Signed-off | MIDTOWN INTERIOR RESOURCE | 02/10/2026 |
| DOB NOW | Sprinklers | Permit Issued | VAND MECHANICAL INC | 01/09/2026 |
| DOB NOW | Sprinklers | Permit Issued | RALPH W. LANDOLFI JR. | 01/08/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | ABCAT ASSOCIATES INC | 12/16/2025 |
| DOB NOW | General Construction | Permit Issued | ABCAT ASSOCIATES INC | 12/09/2025 |
| DOB NOW | General Construction | Signed-off | WG PROJECT MANAGEMENT INC | 12/02/2025 |
| DOB NOW | Mechanical Systems | Signed-off | WG PROJECT MANAGEMENT INC | 11/21/2025 |
| DOB NOW | General Construction | Signed-off | WINSON CONSTRUCTION INC | 11/07/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | COOLING CONTROLS CORP | 10/31/2025 |
| DOB NOW | Plumbing | Signed-off | JOHN FITZGERALD PLBG &HTG | 08/01/2025 |
| DOB NOW | General Construction | Signed-off | WINSON CONSTRUCTION INC | 06/05/2025 |
| DOB NOW | General Construction | Signed-off | GE 2A CONSTRUCTION | 04/02/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | JERRICK ASSOCIATES, INC | 02/03/2025 |
| DOB NOW | Supported Scaffold | Signed-off | GE 2A CONSTRUCTION | 01/13/2025 |
| DOB NOW | Construction Fence | Permit Issued | GE 2A CONSTRUCTION | 12/20/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | GE 2A CONSTRUCTION | 11/19/2024 |
| DOB NOW | Plumbing | Signed-off | CERTIFIED SERVICES AND | 07/25/2024 |
| DOB NOW | General Construction | Permit Issued | P.T. CONSTRUCTION GROUP | 07/24/2024 |
| DOB NOW | General Construction | Signed-off | GE 2A CONSTRUCTION | 04/03/2024 |
| DOB NOW | Mechanical Systems | Signed-off | PREMIER COOLING SERVICES | 03/14/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | JERRICK ASSOCIATES, INC | 02/14/2024 |
| DOB NOW | Supported Scaffold | Signed-off | GE 2A CONSTRUCTION | 01/18/2024 |
| DOB NOW | Plumbing | Signed-off | A.M.N. CORPORATION | 01/02/2024 |
| DOB NOW | General Construction | Signed-off | NORBERT KOCAN | 12/19/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | GE 2A CONSTRUCTION | 11/29/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | SOHOME WORK INC | 02/17/2022 |
| DOB NOW | General Construction | Signed-off | SOHOME WORK INC | 02/17/2022 |
| DOB NOW | General Construction | Signed-off | SOHOME WORK INC | 11/05/2021 |
| DOB NOW | Mechanical Systems | Permit Issued | SOHOME WORK INC | 10/13/2021 |
| DOB NOW | General Construction | Signed-off | SOHOME WORK INC | 10/08/2021 |
| DOB NOW | Sprinklers | Signed-off | CROSSFIELD PLBG.&HTG.CORP | 09/29/2021 |
| DOB NOW | Plumbing | Signed-off | LIQUID TECH PLBG&HTG,INC | 10/01/2020 |
| BIS | PL | ISSUED | GARMAD PLBG & HTG INC | 03/15/2023 |
| BIS | OT | ISSUED | MODAZ CONSTRUCTION CORP | 12/10/2019 |
| BIS | OT | ISSUED | JERRICK ASSOCIATES INC | 07/10/2018 |
| BIS | SP | ISSUED | ACCURATE MECHANICAL INC | 06/20/2018 |
| BIS | — | ISSUED | NEPTUNE SIGNS&AWNINGS INC | 11/15/2017 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/06/2026 | Permit Issued | FRANCHISE INTERIOR DEVELO | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric PURY-EM144TXU-A 144,000 BTU · Vrf Outdoor ×1 |
| 06/15/2026 | — | — | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric PEFY-P24-NMHU-E 27,000 BTU · Vrf Indoor ×8 MXZ-SM48-NAM-U1 54,000 BTU · Condensing Unit ×4 |
| 03/09/2026 | Permit Issued | ABCAT ASSOCIATES INC | Heating and Air Conditioning Systems | Heat / Cool Daikin RXTQ60TAVJU 57,500 BTU · Vrf Outdoor ×1 |
| 03/10/2020 | — | — | Air Conditioning Systems | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/05/2026 | — | — | — |
| 03/09/2026 | Permit Issued | RRP PLUMBING CORP | Sprinkler System |
| 05/05/2025 | — | — | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/05/2026 | — | — | Water/Sanitary |
| 06/09/2026 | Permit Issued | DV PLUMBING INC | Gas, Water/Sanitary |
| 03/09/2026 | Permit Issued | VAND MECHANICAL INC | Gas, Water/Sanitary |
| 09/04/2025 | Signed-off | JOHN FITZGERALD PLBG &HTG | Gas, Water/Sanitary |
| 03/17/2025 | Signed-off | CERTIFIED SVCS & RPRS | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/19/2025 | Permit Issued | AL-LECTRIC ELECT'L CONTRG | General Wiring |
| 04/11/2025 | Permit Issued | EMPIRE LIC ELECL CONTRS | General Wiring |
| 07/11/2024 | Complete | VMA ELECTRICAL CORP. | General Wiring |
| 04/19/2024 | Complete | ARGON ELECTRICAL CORP | General Wiring |
| 11/14/2023 | Permit Issued | BOROWIDE ELECT'L CONTR'S | — |
| 10/05/2023 | Permit Issued | ALLIANCE ELEVATOR COMPANY | — |
| 10/28/2022 | Permit Issued | DUNWELL ELEVATOR ELEC | — |
| 06/16/2022 | Complete | W 8 ELECTRIC CORP | General Wiring |
| 12/16/2020 | Complete | DUNWELL ELEVATOR ELEC | — |
| 11/20/2020 | Complete | BRUNI ELECTRIC INC | General Wiring |
| 08/06/2018 | Complete | JONG HYUN KIM | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/09/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/17/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/08/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/03/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/24/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/24/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/03/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/28/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/05/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/29/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 08/29/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/24/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/15/2024 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 03/29/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 03/22/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/01/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/08/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/05/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/05/2022 | Certified Sprinkler - SP - Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/29/2026 | Energy Code Compliance Inspections | — | progress |
| 07/27/2026 | Lighting controls | — | energy_progress |
| 07/27/2026 | Interior lighting power | — | energy_progress |
| 07/27/2026 | Maintenance information | — | energy_progress |
| 07/27/2026 | Fire-Resistance Rated Construction | — | progress |
| 07/27/2026 | Post-installed Anchors | — | special |
| 07/27/2026 | Tenant Protection Plan Compliance | — | special |
| 07/27/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 07/10/2026 | Fire-Resistant Penetrations and Joints | PIETRO ROSATO | special |
| 07/10/2026 | Energy Code Compliance Inspections | PIETRO ROSATO | progress |
| 07/10/2026 | Final | PIETRO ROSATO | progress |
| 07/10/2026 | Fire-Resistance Rated Construction | PIETRO ROSATO | progress |
| 07/10/2026 | Lighting in dwelling units | PIETRO ROSATO | energy_progress |
| 07/10/2026 | Insulation placement and R values | PIETRO ROSATO | energy_progress |
| 06/12/2026 | Final | PIETRO ROSATO | progress |
| 06/12/2026 | Energy Code Compliance Inspections | PIETRO ROSATO | progress |
| 06/12/2026 | Fire-Resistant Penetrations and Joints | PIETRO ROSATO | special |
| 06/12/2026 | Energy Code Compliance Inspections | PIETRO ROSATO | progress |
| 06/12/2026 | Mechanical Systems | PIETRO ROSATO | special |
| 06/12/2026 | Insulation placement and R values | PIETRO ROSATO | energy_progress |
| 06/12/2026 | Lighting in dwelling units | PIETRO ROSATO | energy_progress |
| 06/12/2026 | Fire-Resistance Rated Construction | PIETRO ROSATO | progress |
| 06/12/2026 | Final | PIETRO ROSATO | progress |
| 06/12/2026 | HVAC-R and service water heating system controls | PIETRO ROSATO | energy_progress |
| 06/12/2026 | HVAC-R and service water heating equipment | PIETRO ROSATO | energy_progress |