← Back
Two stories - detached, small or mid-size
110-11 207 STREET
QUEENS · Queens Village · BIN 4234421
💬 Discuss this project
1930Year Built
2.5Stories
A1Building Class
R3-2Zoning
1,248 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Two stories - detached, small or mid-size · 2,600 sf lot · 0.48 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalPlumbing
Roof1 filing · 7 docs
Attic4p · 1 filing · 9 docs
Floor 27p · 1 filing · 9 docs
Floor 17p · 1 filing · 9 docs
Cellar7p · 1 filing · 9 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
PRO BUILDERS R CONSTRUCTION903/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
02/24/2022$693K—— → —$555/sf building
04/13/2021$311K—Private party → 110-11 207TH STREET MGMT LLC$249/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
M-CON ENGINEERING, PC102/03/2025
ST DESIGN & CONSULTING INC.207/02/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
R H DRUMMOND EXP403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
PRO BUILDERS R CONSTRUCTIGeneral Contractor303/21/2026
SOURCE ELECTRIC INCElectrical103/22/2026
SUSTAINABLE STRATEGIESGeneral Contractor107/08/2026
HAROLD HEADLEY PLUMBINGPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
M-CON ENGINEERING7341102/03/2025
AR-TECH ENGINEERING, P.C.6659105/17/2021
Building Lifecycle
All (27)Filed (3)Permit Issued (3)Signed Off (3)Violation (5)Inspection (6)Special Inspection (7)
05/06/2025
Signed off — Alteration
INSTALLATION OF SOLAR ELECTRIC GENERATION SYSTEM FOR UTILITY INTERCONNECTION
Q01175361-I1
02/06/2025
Permit issued — Solar
Q01175361-I1-SL
02/03/2025
Filed — Alteration
INSTALLATION OF SOLAR ELECTRIC GENERATION SYSTEM FOR UTILITY INTERCONNECTION
Q01175361-I1
02/03/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Michelle Contri
02/03/2025
Special inspection requirement — Final
Michelle Contri
02/03/2025
Special inspection requirement — Air barrier - visual inspection
Michelle Contri
02/03/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Michelle Contri
02/03/2025
Special inspection requirement — Energy Code Compliance Inspections
Michelle Contri
01/04/2022
Signed off — Alteration
Application filed for interior renovation at cel, 1st, 2nd floor, and attic level, to remove non-load bearing partition walls, replacing and repairing wooden floor finish, ceiling, walls as necessary as per plan. To comply with ECB V# 35421929M.
Q00517093-I1
12/22/2021
Signed off — Alteration
Application filed for interior renovation at cel, 1st, 2nd floor, and attic level, to remove non-load bearing partition walls, replacing and repairing wooden floor finish, ceiling, walls as necessary as per plan. To comply with ECB V# 35421929M.
Q00517093-S1
12/13/2021
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
12/13/2021
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
12/03/2021
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
11/04/2021
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
10/26/2021
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
10/01/2021
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
08/30/2021
Permit issued — Plumbing
Q00517093-S1-PL
07/02/2021
Filed — Alteration
Application filed for interior renovation at cel, 1st, 2nd floor, and attic level, to remove non-load bearing partition walls, replacing and repairing wooden floor finish, ceiling, walls as necessary as per plan. To comply with ECB V# 35421929M.
Q00517093-S1
06/14/2021
Permit issued — General Construction
Q00517093-I1-GC
05/17/2021
Filed — Alteration
Application filed for interior renovation at cel, 1st, 2nd floor, and attic level, to remove non-load bearing partition walls, replacing and repairing wooden floor finish, ceiling, walls as necessary as per plan. To comply with ECB V# 35421929M.
Q00517093-I1
05/06/2021
Special inspection requirement — Lighting in dwelling units
SAMIR ABDALLA
05/06/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
ALBERTO ROMAN
07/11/2019
Violation issued (ECB, closed)
Construction
09/07/2011
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/17/2011
Violation issued (ECB, closed)
Unknown
06/14/2011
Violation issued (ECB, closed)
Quality of Life
06/14/2011
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSUSTAINABLE STRATEGIES02/06/2025
DOB NOWPlumbingSigned-offHAROLD HEADLEY PLUMBING08/30/2021
DOB NOWGeneral ConstructionSigned-offPRO BUILDERS R CONSTRUCTI06/14/2021
1 project · most recent 04/15/2025
FiledStatusContractorScope
04/15/2025CompleteSOURCE ELECTRIC INC1 meters
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
12/13/2021Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
12/13/2021Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/03/2021Pass-Final General Construction Non-Directive 14PassView ↗
11/04/2021Fail-Final General Construction Non-Directive 14FailView ↗
10/26/2021Pass-Final PL - Up to 3 Requested FloorsPassView ↗
10/01/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 7
DateRequirementInspectorRole
02/03/2025Structural Stability – Alterations of existing buildingsMichelle Contrispecial
02/03/2025FinalMichelle Contriprogress
02/03/2025Air barrier - visual inspectionMichelle Contrienergy_progress
02/03/2025Fire-Resistant Penetrations and JointsMichelle Contrispecial
02/03/2025Energy Code Compliance InspectionsMichelle Contriprogress
05/06/2021Lighting in dwelling unitsSAMIR ABDALLAenergy_progress
05/06/2021Fire-Resistant Penetrations and JointsALBERTO ROMANspecial
▾Documents — 24 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/27/2026Q00517093-I1Request digital key ↗
08/27/2026Q00517093-S1Request digital key ↗
08/21/2026Q01175361-I1Request digital key ↗
▸Applications & Permits1
▸BISPLAN / WORK APPROVAL APPLICATION1
04/23/2012420552743Open ↗
▸Seals & Professional Certifications9
▸DOB NOWProgress Inspector Seal & Signature3
08/24/2026Q00517093-I1Open ↗
08/23/2026Q01175361-I1Open ↗
08/23/2026Q01175361-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/27/2026Q00517093-I1Open ↗
08/27/2026Q00517093-S1Open ↗
08/21/2026Q01175361-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/24/2026Q00517093-I1Open ↗
08/23/2026Q01175361-I1Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
04/06/2012420552743Open ↗
▸Trade Schedules & Equipment1
▸BISSCHEDULE B - PLUMBING1
04/06/2012420552743Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/27/2026Q00517093-I1Open ↗
08/27/2026Q00517093-S1Open ↗
08/21/2026Q01175361-I1Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
04/06/2012420552743Open ↗
▸Energy Compliance2
▸BISTECHNICAL REPORT: ENERGY1
04/06/2012420552743Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026Q00517093-I1Open ↗
▸Approvals, Objections & Sign-offs2
▸BISADMINISTRATIVE OBJECTIONS1
04/06/2012420552743Open ↗
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01175361-I1Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
04/06/2012420552743Open ↗
▸Filing & Intake Forms1
▸BISEFILING COVER SHEET1
04/06/2012420552743Open ↗