| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/19/2025 | Permit Issued | SIGNORE & SONS PLBG CORP | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/03/2024 | Permit Issued | FALCO ELEC'L SERVICES INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/26/2025 | Permit Issued | MORELL BUILDERS INC | Wood |
| 06/25/2025 | — | — | Wood |
| Owner | Filings | Most Recent |
|---|---|---|
| 718 DESIGN PRO | 10 | 08/07/2026 |
| SHASHA DESIGN NYC, LLC | 2 | 03/22/2026 |
| FALCO ELEC'L SERVICES INC | 1 | 03/22/2026 |
| 718 HOME IMPROVEMENT | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/03/2023 | $750K | — | FLUSHING FLORDIA, LLC → SHASHA DESIGN NYC, LLC | $429/sf building |
| 03/11/2020 | $290K | — | Private party → FLUSHING FLORIDA LLC | $166/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| INGA CONSULTING ENGINEERS | 2 | 08/26/2025 |
| CL ENGINEERING P.C. | 2 | 06/25/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| LAVB DESIGN CONSULTANTS | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MORELL BUILDERS INC | General Contractor | 3 | 03/21/2026 |
| SIGNORE & SONS PLBG CORP | Plumbing | 1 | 08/07/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CL ENGINEERING P.C. | 6781 | 3 | 08/26/2025 |
| ASR ENGINEERING PC | 8404 | 1 | 03/19/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | SIGNORE & SONS PLBG CORP | 08/06/2026 |
| DOB NOW | Structural | Permit Issued | MORELL BUILDERS INC | 08/28/2025 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/20/2025 | Structural Stability – Alterations of existing buildings | CHRISTIAN LOZADA | special |
| 08/20/2025 | Fire-Resistant Penetrations and Joints | CHRISTIAN LOZADA | special |
| 08/20/2025 | Structural Wood Frame | Andrew Inga | progress |
| 08/20/2025 | Final | Andrew Inga | progress |
| 08/20/2025 | Energy Code Compliance Inspections | Andrew Inga | progress |
| 08/20/2025 | Fire-Resistance Rated Construction | Andrew Inga | progress |
| 08/20/2025 | Fenestration air leakage | Andrew Inga | energy_progress |
| 08/20/2025 | Lighting in dwelling units | Andrew Inga | energy_progress |
| 08/20/2025 | Interior lighting power | Andrew Inga | energy_progress |
| 08/20/2025 | Fenestration areas | Andrew Inga | energy_progress |
| 08/20/2025 | Fenestration and door U-factor and product ratings | Andrew Inga | energy_progress |
| 08/20/2025 | Air barrier - visual inspection | Andrew Inga | energy_progress |
| 08/20/2025 | Insulation placement and R values | Andrew Inga | energy_progress |
| 08/20/2025 | Permanent certificate | Andrew Inga | energy_progress |
| 08/20/2025 | Metering | Andrew Inga | energy_progress |