RoofUnder Construction3p · 6 filings · 13 docs
MechanicalPlumbing
Issued Permit Scope
Protection and Mechanical Methods · Supported Scaffold
INSTALLATION OF TEMPORARY PERSONNEL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
INSTALLATION OF TEMPORARY ENGINEERED ENCLOSURE SYSTEM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY
On file for this project
2 documents
Latest 3 of 6 filings on this floor.
Bulkhead2p · 1 filing · 11 docs
ArchitectureStructural
No filed description on record for this project.
On file for this project
11 documents · 2 drawing sheets
Floor 10Under Construction2 filings · 4 docs
Issued Permit Scope
Protection and Mechanical Methods · Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
INSTALLATION OF TEMPORARY ENGINEERED ENCLOSURE SYSTEM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY
On file for this project
2 documents
Floor 9Under Construction3 filings · 5 docs
Issued Permit Scope
Protection and Mechanical Methods · Supported Scaffold
INSTALLATION OF TEMPORARY PERSONNEL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
INSTALLATION OF TEMPORARY ENGINEERED ENCLOSURE SYSTEM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY
On file for this project
2 documents
Floor 8Under Construction3 filings · 5 docs
Issued Permit Scope
Protection and Mechanical Methods · Supported Scaffold
INSTALLATION OF TEMPORARY PERSONNEL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
INSTALLATION OF TEMPORARY ENGINEERED ENCLOSURE SYSTEM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY
On file for this project
2 documents
Floor 7Under Construction52p · 4 filings · 20 docs
ArchitectureMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods · Supported Scaffold
INSTALLATION OF TEMPORARY PERSONNEL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
UNDERPINNING SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION #B01341528-I1
On file for this project
56 documents · 5 drawing sheets
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Latest 3 of 4 filings on this floor.
Floor 6Under Construction51p · 4 filings · 20 docs
ArchitectureMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods · Supported Scaffold
INSTALLATION OF TEMPORARY PERSONNEL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
UNDERPINNING SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION #B01341528-I1
On file for this project
56 documents · 4 drawing sheets
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Latest 3 of 4 filings on this floor.
Floor 5Under Construction51p · 4 filings · 20 docs
ArchitectureMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods · Supported Scaffold
INSTALLATION OF TEMPORARY PERSONNEL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
UNDERPINNING SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION #B01341528-I1
On file for this project
56 documents · 4 drawing sheets
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Latest 3 of 4 filings on this floor.
Floor 4Under Construction51p · 4 filings · 20 docs
ArchitectureMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods · Supported Scaffold
INSTALLATION OF TEMPORARY PERSONNEL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
UNDERPINNING SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION #B01341528-I1
On file for this project
56 documents · 4 drawing sheets
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Latest 3 of 4 filings on this floor.
Floor 3Under Construction53p · 4 filings · 20 docs
ArchitectureMechanicalPlumbingStructuralZ
Issued Permit Scope
General Construction · Protection and Mechanical Methods · Supported Scaffold
INSTALLATION OF TEMPORARY PERSONNEL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
UNDERPINNING SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION #B01341528-I1
On file for this project
56 documents · 6 drawing sheets
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Latest 3 of 4 filings on this floor.
Floor 2Under Construction53p · 4 filings · 20 docs
ArchitectureDMMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Protection and Mechanical Methods · Supported Scaffold
INSTALLATION OF TEMPORARY PERSONNEL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
UNDERPINNING SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION #B01341528-I1
On file for this project
56 documents · 6 drawing sheets
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Latest 3 of 4 filings on this floor.
Floor 1Under Construction60p · 5 filings · 20 docs
ArchitectureGeneralLandscapeMechanicalPlumbingStructuralZ
Issued Permit Scope
General Construction · Protection and Mechanical Methods · Supported Scaffold
INSTALLATION OF TEMPORARY PERSONNEL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
1 document
UNDERPINNING SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION #B01341528-I1
On file for this project
56 documents · 12 drawing sheets
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
Latest 3 of 5 filings on this floor.
CellarUnder Construction101p · 2 filings · 20 docs
ArchitectureCivilDMMechanicalPlumbingStructural
Issued Permit Scope
Earth Work · Foundation · General Construction · Support of Excavation
UNDERPINNING SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION #B01341528-I1
On file for this project
56 documents · 7 drawing sheets
No filed description on record for this project.
On file for this project
11 documents · 2 drawing sheets
BasementUnder Construction55p · 3 filings · 20 docs
ArchitectureMechanicalPlumbingStructural
Issued Permit Scope
General Construction
UNDERPINNING SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION #B01341528-I1
On file for this project
56 documents · 5 drawing sheets
No filed description on record for this project.
On file for this project
11 documents · 1 drawing sheet
No filed description on record for this project.
On file for this project
3 documents · 2 drawing sheets