| Owner | Filings | Most Recent |
|---|---|---|
| BROWN HARRIS STEVENS | 26 | 09/13/2026 |
| 1105 PARK AVENUE | 114 | 03/22/2026 |
| 1105 PARK AVENUE REALTY C | 1 | 03/22/2026 |
| BROWN STEVEN HARRIS RESIDENTIAL LLC | 1 | 03/22/2026 |
| CITISTRUCTURE LLC | 1 | 03/21/2026 |
| MANAS TRUST | 3 | 03/21/2026 |
| 1105 PARK AVE CORP C O EVEREST | 2 | 03/21/2026 |
| 1105 PARK AVENUE CORP C O BHS | 11 | 03/21/2026 |
| 1105 PARK | 2 | 03/21/2026 |
| REALTO REALTY | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| SETH P. ROYE ARCHITECT PC | 3 | 06/23/2026 |
| A2 ARCHITECT, PC | 2 | 04/24/2026 |
| SAL V. TARTAGLIONE ARCHITECT, PC | 2 | 03/10/2026 |
| MATTHEW BAIRD ARCHITECT PLLC | 1 | 07/08/2024 |
| ABS ENGINEERING, PLLC | 1 | 07/08/2024 |
| PIER FINE ASSOCIATES | 2 | 03/06/2024 |
| M.ARCH ARCHITECTS | 4 | 07/18/2023 |
| MK ARCHITECTURE | 4 | 03/21/2023 |
| JACK GREEN ASSOCIATES | 3 | 08/10/2022 |
| RAWLINS DESIGN INC. | 1 | 04/08/2022 |
| PIRO STUDIO LLC | 3 | 03/18/2021 |
| DIRECT ACCESS EXPEDITING, INC | 5 | 10/15/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| CLARKE CONSTRUCTION CONSULTANTS | 5 | 03/21/2026 |
| LEWSAN CONSULTANTS | 4 | 03/21/2026 |
| JAM CONSULTANTS, INC. | 4 | 03/21/2026 |
| CODE | 8 | 03/21/2026 |
| MK ARCHITECTURE PC | 6 | 03/21/2026 |
| DIRECT ACCESS EXPEDITING, INC. | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| WEST NEW YORK RESTORATION OF CT | General Contractor | 14 | 07/08/2026 |
| RICHARD GRIMA | Electrical | 4 | 03/21/2026 |
| MCCORMACK CONTRACTING INC. | General Contractor | 3 | 07/08/2026 |
| METROTECH MECHANICAL CORP | Plumbing | 2 | 07/08/2026 |
| ZITO, ROCCO | Electrical | 2 | 03/21/2026 |
| LEONARD KRITZ | Electrical | 1 | 03/21/2026 |
| MANTEO, AGRIPPINO | Electrical | 1 | 03/21/2026 |
| VLAKANCIC, M | Electrical | 1 | 03/21/2026 |
| WALDEN, LEE | Electrical | 1 | 03/21/2026 |
| WILLIAMS, KEITH | Electrical | 1 | 03/21/2026 |
| ALCA RENOVATIONS INC | General Contractor | 1 | 07/08/2026 |
| ATTIC TO BASEMENT HOME | General Contractor | 1 | 07/28/2026 |
| CORTLANDT CONTRACTING CORP | General Contractor | 1 | 07/08/2026 |
| D&E REFRIGERATION & AIR C | General Contractor | 1 | 07/08/2026 |
| LENDI CONSTRUCTION LLC | General Contractor | 1 | 06/27/2026 |
| PAM AIR CONDITIONING INC | General Contractor | 1 | 04/09/2026 |
| ZACCO BUILDING CORP | General Contractor | 1 | 07/08/2026 |
| DYNAMIC BLUE WATER MECH | Plumbing | 1 | 08/20/2026 |
| HUDSON PLMBING & MCH, LLC | Plumbing | 1 | 07/08/2026 |
| MCMANUS MECH MAINT P&H INC | Plumbing | 1 | 07/08/2026 |
| M C M PLBG & HTG, INC | Plumbing | 1 | 07/08/2026 |
| RVM PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| DESIGNER'S HOME IMPROVEME | Electrical | 1 | 03/21/2026 |
| SAFEPIPE PLUMBING INC | Plumbing | 1 | 07/02/2026 |
| EIS ELECTRIC CORP DBA | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SETH P ROYE ARCHITECT PC | 8554 | 3 | 06/23/2026 |
| A2 ARCHITECT, PC | 2504 | 2 | 04/24/2026 |
| SGM ENGINEERING | 2366 | 1 | 04/24/2026 |
| EC SPECIAL INSPECTIONS | 8355 | 2 | 03/10/2026 |
| RYAN SPECIAL ENGINEERING | 2018 | 1 | 07/08/2024 |
| WINTON GROUP ARCHITECTURE | 4343 | 1 | 03/06/2024 |
| ALAN MARGOLIN & ASSOC | 423 | 1 | 03/06/2024 |
| MK ARCHITECTURE, PC | 476 | 3 | 03/21/2023 |
| JACK GREEN ASSOCIATES | 422 | 3 | 08/10/2022 |
| AK ENGINEERING PC | 678 | 1 | 04/08/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | DYNAMIC BLUE WATER MECH | 08/18/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | ATTIC TO BASEMENT HOME | 07/27/2026 |
| DOB NOW | Plumbing | Permit Issued | SAFEPIPE PLUMBING INC | 06/30/2026 |
| DOB NOW | General Construction | Permit Issued | LENDI CONSTRUCTION LLC | 06/25/2026 |
| DOB NOW | Mechanical Systems | Signed-off | PAM AIR CONDITIONING INC | 02/18/2026 |
| DOB NOW | Plumbing | Signed-off | HUDSON PLMBING & MCH, LLC | 04/01/2024 |
| DOB NOW | General Construction | Signed-off | ALCA RENOVATIONS INC | 03/19/2024 |
| DOB NOW | Plumbing | Signed-off | METROTECH MECHANICAL CORP | 05/09/2023 |
| DOB NOW | General Construction | Signed-off | MCCORMACK CONTRACTING INC | 05/08/2023 |
| DOB NOW | General Construction | Signed-off | CORTLANDT CONTRACTING COR | 04/26/2023 |
| DOB NOW | Plumbing | Signed-off | MCMANUS MECH MAINT P&H IN | 04/24/2023 |
| DOB NOW | General Construction | Signed-off | A. PETER LUGER CONST INC | 02/10/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | A. PETER LUGER CONST INC | 01/17/2023 |
| DOB NOW | Supported Scaffold | Signed-off | A. PETER LUGER CONST INC | 08/10/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | A. PETER LUGER CONST INC | 08/10/2022 |
| DOB NOW | Plumbing | Signed-off | RVM PLUMBING CORP | 06/30/2022 |
| DOB NOW | General Construction | Signed-off | MCCORMACK CONTRACTING INC | 05/20/2022 |
| DOB NOW | Mechanical Systems | Signed-off | D&E REFRIGERATION & AIR C | 05/02/2022 |
| DOB NOW | Plumbing | Signed-off | METROTECH MECHANICAL CORP | 04/28/2022 |
| DOB NOW | Mechanical Systems | Signed-off | ZACCO BUILDING CORP | 08/12/2020 |
| DOB NOW | Plumbing | Signed-off | M C M PLBG & HTG, INC | 08/03/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | A. PETER LUGER CONST INC | 04/02/2020 |
| DOB NOW | Supported Scaffold | Signed-off | A. PETER LUGER CONST INC | 04/02/2020 |
| DOB NOW | Supported Scaffold | Signed-off | A. PETER LUGER CONST INC | 04/18/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | A. PETER LUGER CONST INC | 04/16/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | A. PETER LUGER CONST INC | 03/21/2019 |
| DOB NOW | Supported Scaffold | Signed-off | A. PETER LUGER CONST INC | 03/21/2019 |
| BIS | OT | ISSUED | ZACCO BUILDING CORP | 08/11/2020 |
| BIS | OT | ISSUED | WEST NEW YORK RESTORATION OF CT | 04/20/2020 |
| BIS | EQ | ISSUED | WEST NEW YORK RESTORATION OF CT | 03/17/2020 |
| BIS | PL | ISSUED | TOP DOG PLBG & HTG CORP | 10/01/2019 |
| BIS | OT | ISSUED | WEST NEW YORK RESTORATION OF CT | 09/05/2019 |
| BIS | OT | ISSUED | WEST NEW YORK RESTORATION OF CT | 04/30/2019 |
| BIS | OT | ISSUED | WEST NEW YORK RESTORATION OF CT | 04/02/2019 |
| BIS | EQ | ISSUED | WEST NEW YORK RESTORATION OF CT | 03/25/2019 |
| BIS | MH | ISSUED | MBQ CONTRACTING CORP | 09/24/2018 |
| BIS | OT | ISSUED | MBQ CONTRACTING CORP | 09/24/2018 |
| BIS | PL | ISSUED | ZFM INC | 09/20/2018 |
| BIS | MH | ISSUED | MBQ CONTRACTING CORP | 08/29/2018 |
| BIS | OT | ISSUED | MBQ CONTRACTING CORP | 08/29/2018 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/23/2026 | Permit Issued | SAFEPIPE PLUMBING INC | Gas, Water/Sanitary |
| 07/08/2024 | — | — | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/19/2026 | Permit Issued | TRINITY ELECTRIC GROUP | General Wiring |
| 06/03/2026 | Complete | CONDUCTOR ELECL SVCS INC | — |
| 05/06/2026 | Complete | GLENDALE ELECTL CONTNG IN | — |
| 01/05/2026 | Permit Issued | K & G ELECTRIC CO., INC | HVAC Wiring |
| 07/08/2025 | Complete | RND ELECTRIC CORP | General Wiring |
| 12/10/2024 | Complete | P.S. MARCATO ELEV. CO INC | — |
| 12/10/2024 | Complete | P.S. MARCATO ELEV. CO INC | — |
| 11/09/2023 | Complete | T. MCCAFFREY-T. MCGOVERN | General Wiring |
| 08/10/2022 | Complete | NASH ELECTRIC SERVICES IN | — |
| 08/16/2021 | Complete | ACCURATE ELEC'L CORP. | General Wiring |
| 12/10/2020 | Complete | EIS ELECTRIC CORP DBA | General Wiring |
| 06/25/2020 | Complete | LEONE ELECTRIC CO. INC | General Wiring |
| 10/24/2019 | Complete | APOLLO ELECTRIC USA, INC | General Wiring |
| 03/26/2019 | Complete | NASH ELECTRIC SERVICES IN | — |
| 03/20/2019 | Complete | NASH ELECTRIC SERVICES IN | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/05/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 11/20/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/27/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/26/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/08/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/31/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/21/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/21/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/15/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/17/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/10/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 10/14/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/25/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/23/2026 | Fire-Resistant Penetrations and Joints | Seth Roye | special |
| 06/22/2026 | Energy Code Compliance Inspections | Seth Roye | progress |
| 06/22/2026 | Energy Code Compliance Inspections | Seth Roye | progress |
| 06/16/2026 | Fire-Resistant Penetrations and Joints | Seth Roye | special |
| 06/16/2026 | Masonry | Seth Roye | special |
| 06/08/2026 | Final | Seth Roye | progress |
| 06/01/2026 | Structural Stability – Alterations of existing buildings | steven Giammona | special |
| 03/31/2026 | Mechanical Systems | ABDALLAH ELCHERBINI | special |
| 03/31/2026 | Fire-Resistant Penetrations and Joints | ABDALLAH ELCHERBINI | special |
| 03/31/2026 | Final | ABDALLAH ELCHERBINI | progress |
| 03/31/2026 | Energy Code Compliance Inspections | Sal Tartaglione | progress |
| 03/31/2026 | HVAC-R and service water heating equipment | Sal Tartaglione | energy_progress |
| 03/31/2026 | HVAC-R and service water heating system controls | Sal Tartaglione | energy_progress |
| 03/31/2026 | HVAC-R and service water piping design and insulation | Sal Tartaglione | energy_progress |
| 03/31/2026 | Maintenance information | Sal Tartaglione | energy_progress |
| 03/31/2026 | Tenant Protection Plan Compliance | ABDALLAH ELCHERBINI | special |
| 03/30/2026 | Duct leakage testing, insulation and design | Ann Macklin | energy_progress |
| 03/30/2026 | Shutoff dampers | Ann Macklin | energy_progress |
| 03/27/2026 | Post-installed Anchors | Ann Macklin | special |
| 03/27/2026 | Fire-Resistance Rated Construction | Ann Macklin | progress |
| 03/17/2026 | Energy Code Compliance Inspections | Ann Macklin | progress |
| 03/17/2026 | Fire-Resistant Penetrations and Joints | Ann Macklin | special |
| 03/17/2026 | Lighting in dwelling units | Ann Macklin | energy_progress |
| 03/17/2026 | Fire-Resistant Penetrations and Joints | Ann Macklin | special |
| 03/16/2026 | Final | Ann Macklin | progress |