← Back
One story - permanent living quarter
111-12 180 STREET
QUEENS · St. Albans · BIN 4219619
💬 Discuss this project
1950Year Built
1.5Stories
A2Building Class
R2Zoning
1,156 sfGross Floor Area
1Units
One story - permanent living quarter · 4,106 sf lot · 0.28 FAR built · Flood zone X
Locations of Work
Electrical
Roof4p · 1 filing · 13 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
02/03/2014$370K—Private party → Private party$320/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR202/10/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281202/10/2026
Building Lifecycle
All (12)Filed (2)Permit Issued (1)Signed Off (1)Special Inspection (8)
02/13/2026
Signed off — Alteration
Q01176505-I1
02/10/2026
Filed — Alteration
Q01176505-P1
02/10/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
02/10/2026
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
02/10/2026
Special inspection requirement — Final
Mina Makar
02/10/2026
Special inspection requirement — Air barrier - visual inspection
Mina Makar
02/10/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
02/10/2026
Special inspection requirement — Final
Mina Makar
02/10/2026
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
02/10/2026
Special inspection requirement — Air barrier - visual inspection
Mina Makar
02/07/2025
Permit issued — Solar
Q01176505-I1-SL
02/05/2025
Filed — Alteration
Q01176505-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offMOMENTUM SOLAR02/07/2025
1 project · most recent 02/05/2025
FiledStatusContractorScope
02/05/2025CompleteISLAND ELECTRIC CORP—
▾Special Inspection Requirements (DOB NOW) — 8
DateRequirementInspectorRole
02/10/2026Fire-Resistant Penetrations and JointsMina Makarspecial
02/10/2026Energy Code Compliance InspectionsMina Makarprogress
02/10/2026FinalMina Makarprogress
02/10/2026Air barrier - visual inspectionMina Makarenergy_progress
02/10/2026Fire-Resistant Penetrations and JointsMina Makarspecial
02/10/2026FinalMina Makarprogress
02/10/2026Energy Code Compliance InspectionsMina Makarprogress
02/10/2026Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 13 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/17/2026Q01176505-P1Request digital key ↗
08/17/2026Q01176505-I1Request digital key ↗
▸Seals & Professional Certifications8
▸DOB NOWProgress Inspector Seal & Signature4
09/01/2026Q01176505-P1Open ↗
09/01/2026Q01176505-P1Open ↗
08/28/2026Q01176505-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/17/2026Q01176505-P1Open ↗
08/17/2026Q01176505-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/01/2026Q01176505-P1Open ↗
08/28/2026Q01176505-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/17/2026Q01176505-P1Open ↗
08/17/2026Q01176505-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01176505-I1Open ↗