| Owner | Filings | Most Recent |
|---|---|---|
| CORPORATE EQUITY RESOURCES LLC | 5 | 03/22/2026 |
| 160 QUINCY | 13 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| J&R DESIGN AND INSPECTION CORP. | 1 | 10/30/2023 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HIGH QUALITY CONSTRUCTION | General Contractor | 2 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| J&R DESIGN AND INSPECTION | 6637 | 1 | 10/30/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | HIGH QUALITY CONSTRUCTION | 11/06/2023 |
| BIS | PL | ISSUED | NCA PLUMBING&HEATING LLC | 08/14/2014 |
| BIS | MH | ISSUED | ARCO GENERAL CONTRACTOR INC | 08/16/2013 |
| BIS | EQ | ISSUED | PILKU CONSTRUCTION SERVIC | 08/02/2013 |
| BIS | SP | ISSUED | H.A.M. FIRE EQUIPMENT INC | 06/11/2013 |
| BIS | PL | ISSUED | JTP PLBING CONTRACTOR, LT | 05/03/2013 |
| BIS | EQ | ISSUED | BENTZY'S CONSTRUCTION INC | 05/02/2013 |
| BIS | — | ISSUED | ARCO GENERAL CONTRACTOR INC | 02/08/2013 |
| BIS | EQ | ISSUED | PILKU CONSTRUCTION SERVIC | 12/18/2012 |
| BIS | FP | ISSUED | FIRE COMMAND CO, INC | 01/16/2009 |
| BIS | PL | ISSUED | W.G.PLBG & HTNG | 05/18/2006 |
| BIS | OT | ISSUED | VP SEWER CLEANING | 05/04/2006 |
| BIS | PL | ISSUED | WAGNER PLBG & HTG | 06/30/2000 |
| BIS | FP | ISSUED | NEW YORK BUSINESS FIRE SYSTEM | 06/30/2000 |
| BIS | OT | ISSUED | TOP ONE CONST CO I NC | 05/09/2000 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/05/2024 | Complete | VILLAGE ELECTL CONTRS INC | 7 meters, 1 new_meters |
| 11/15/2023 | Complete | VILLAGE ELECTL CONTRS INC | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/30/2023 | Tenant Protection Plan Compliance | Robert Truskosky | special |
| 10/27/2023 | Fire-Resistant Penetrations and Joints | Robert Truskosky | special |
| 10/27/2023 | HVAC-R and service water heating system controls | Robert Truskosky | energy_progress |
| 10/27/2023 | HVAC-R and service water heating equipment | Robert Truskosky | energy_progress |
| 10/27/2023 | Shutoff dampers | Robert Truskosky | energy_progress |
| 10/27/2023 | Energy Code Compliance Inspections | Robert Truskosky | progress |
| 10/27/2023 | Fire-Resistance Rated Construction | Robert Truskosky | progress |
| 10/27/2023 | HVAC-R and service water piping design and insulation | Robert Truskosky | energy_progress |
| 10/25/2023 | Final | Robert Truskosky | progress |
| 10/25/2023 | Mechanical Systems | Robert Truskosky | special |