| Owner | Filings | Most Recent |
|---|---|---|
| OWNERS REP | 8 | 07/08/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 01/17/2020 | $2.1M | — | 1119 42 LLC → Private party | — not available |
| 07/25/2019 | $1.7M | — | Private party → 1119 42 LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| ADVANCED ENGINEERING & INSPECT. PLL | 9 | 07/07/2026 |
| ASHER ARCHITECT | 5 | 03/16/2026 |
| PAUL PERDEK, PROF. ENG. PLLC | 4 | 11/21/2025 |
| R & O ENGINEERING | 13 | 04/22/2025 |
| SOLOMON ROSENZWEIG P.E P.C. | 1 | 09/13/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| BINYAN EXPEDITING | 2 | 03/21/2026 |
| NYC PERMIT SERVICES | 28 | 03/21/2026 |
| ADVANCED BUILDERS SERVICES | 9 | 03/21/2026 |
| AE DESIGN SOLUTION | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BB EMPIRE CORP | General Contractor | 37 | 08/26/2026 |
| CORE SCAFFOLD SYSTEMS INC. | General Contractor | 3 | 07/08/2026 |
| NESS MECHANICAL P & H INC | Plumbing | 3 | 07/22/2026 |
| QUALITY PIPING, INC | Fire Protection | 1 | 07/03/2026 |
| DESIGN N SAFETY INC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 25 | 07/07/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | BB EMPIRE CORP | 08/25/2026 |
| DOB NOW | General Construction | Permit Issued | BB EMPIRE CORP | 07/27/2026 |
| DOB NOW | Plumbing | Permit Issued | NESS MECHANICAL P & H INC | 07/20/2026 |
| DOB NOW | Sidewalk Shed | Signed-off | CORE SCAFFOLD SYSTEMS INC. | 04/22/2026 |
| DOB NOW | Construction Fence | Signed-off | BB EMPIRE CORP | 04/14/2026 |
| DOB NOW | Construction Fence | Signed-off | BB EMPIRE CORP | 03/31/2026 |
| DOB NOW | Support of Excavation | Signed-off | BB EMPIRE CORP | 02/12/2026 |
| DOB NOW | Foundation | Signed-off | BB EMPIRE CORP | 02/11/2026 |
| DOB NOW | Structural | Signed-off | BB EMPIRE CORP | 02/10/2026 |
| DOB NOW | Foundation | Signed-off | BB EMPIRE CORP | 02/05/2026 |
| DOB NOW | Boiler Equipment | Signed-off | NESS MECHANICAL P & H INC | 02/03/2026 |
| DOB NOW | General Construction | Permit Issued | BB EMPIRE CORP | 10/31/2025 |
| DOB NOW | General Construction | Permit Issued | BB EMPIRE CORP | 08/26/2025 |
| DOB NOW | Sprinklers | Signed-off | QUALITY PIPING, INC | 08/01/2025 |
| DOB NOW | Plumbing | Permit Issued | NESS MECHANICAL P & H INC | 07/22/2025 |
| DOB NOW | Mechanical Systems | Signed-off | BB EMPIRE CORP | 07/16/2025 |
| DOB NOW | Supported Scaffold | Signed-off | CORE SCAFFOLD SYSTEMS INC | 06/11/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | CORE SCAFFOLD SYSTEMS INC | 04/28/2025 |
| DOB NOW | Support of Excavation | Signed-off | BB EMPIRE CORP | 03/18/2025 |
| DOB NOW | Structural | Signed-off | BB EMPIRE CORP | 03/18/2025 |
| DOB NOW | Construction Fence | Signed-off | BB EMPIRE CORP | 03/10/2025 |
| DOB NOW | Foundation | Signed-off | BB EMPIRE CORP | 03/05/2025 |
| DOB NOW | Foundation | Signed-off | BB EMPIRE CORP | 03/05/2025 |
| DOB NOW | General Construction | Permit Issued | BB EMPIRE CORP | 03/04/2025 |
| DOB NOW | Structural | Signed-off | BB EMPIRE CORP | 12/09/2024 |
| DOB NOW | Support of Excavation | Signed-off | BB EMPIRE CORP | 12/05/2024 |
| DOB NOW | Foundation | Signed-off | BB EMPIRE CORP | 12/05/2024 |
| DOB NOW | General Construction | Permit Issued | BB EMPIRE CORP | 11/12/2024 |
| DOB NOW | Support of Excavation | Signed-off | BB EMPIRE CORP | 11/08/2024 |
| DOB NOW | Foundation | Signed-off | BB EMPIRE CORP | 11/08/2024 |
| DOB NOW | Foundation | Signed-off | BB EMPIRE CORP | 11/08/2024 |
| DOB NOW | General Construction | Permit Issued | BB EMPIRE CORP | 11/07/2024 |
| DOB NOW | Foundation | Signed-off | BB EMPIRE CORP | 11/06/2024 |
| DOB NOW | Foundation | Signed-off | BB EMPIRE CORP | 05/29/2024 |
| DOB NOW | Support of Excavation | Signed-off | BB EMPIRE CORP | 05/29/2024 |
| DOB NOW | Foundation | Signed-off | BB EMPIRE CORP | 05/07/2024 |
| DOB NOW | General Construction | Permit Issued | BB EMPIRE CORP | 03/12/2024 |
| DOB NOW | Construction Fence | Signed-off | BB EMPIRE CORP | 03/08/2024 |
| DOB NOW | Construction Fence | Signed-off | DESIGN N SAFETY INC | 10/04/2021 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/07/2026 | Permit Issued | BB EMPIRE CORP | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric MXZ-SM60NAM2 60,000 BTU · Condensing Unit ×8 MXZ-SM36NAM2 36,000 BTU · Condensing Unit ×2 MXZ-SM48NAM2 48,000 BTU · Condensing Unit ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/07/2026 | Permit Issued | QUALITY PIPING, INC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/06/2026 | Complete | ADD ELECTRICAL CONTRG INC | General Wiring |
| 04/25/2025 | Complete | SOLAS ELECTRICAL CORP | — |
| 07/09/2024 | Complete | TRUE POWER ELECL CONT LLC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/07/2026 | Permit Issued | BB EMPIRE CORP | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/07/2026 | Permit Issued | BB EMPIRE CORP | Fence |
| 11/21/2025 | Signed-off | CORE SCAFFOLD SYSTEMS INC | Scaffold |
| 05/15/2025 | Signed-off | CORE SCAFFOLD SYSTEMS INC | Sidewalk Shed |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/28/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/27/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/27/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/16/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/18/2025 | Certified StandPipe - SD - Hydrostatic 63/09 Test (100 Foot Increments) | Certified | View ↗ |
| 11/17/2025 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 09/16/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 08/25/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 08/25/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 08/04/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 11/15/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 11/15/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/04/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/02/2026 | Sprinkler Systems | FAHAD FATEH | special |
| 07/02/2026 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 06/18/2026 | Sprinkler Systems | FAHAD FATEH | special |
| 06/18/2026 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 06/10/2026 | HVAC-R and service water heating equipment | FAHAD FATEH | energy_progress |
| 06/10/2026 | HVAC-R and service water heating system controls | FAHAD FATEH | energy_progress |
| 06/10/2026 | Heating Systems | FAHAD FATEH | special |
| 06/10/2026 | HVAC-R and service water piping design and insulation | FAHAD FATEH | energy_progress |
| 06/10/2026 | Maintenance information | FAHAD FATEH | energy_progress |
| 06/10/2026 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 05/29/2026 | Lighting controls | FAHAD FATEH | energy_progress |
| 05/29/2026 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 05/29/2026 | HVAC-R and service water heating equipment | FAHAD FATEH | energy_progress |
| 05/29/2026 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 05/29/2026 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 05/29/2026 | Masonry | FAHAD FATEH | special |
| 05/29/2026 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 05/29/2026 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 05/29/2026 | Metering | FAHAD FATEH | energy_progress |
| 05/29/2026 | Lighting in dwelling units | FAHAD FATEH | energy_progress |
| 05/29/2026 | Fenestration areas | FAHAD FATEH | energy_progress |
| 05/29/2026 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 05/29/2026 | Maintenance information | FAHAD FATEH | energy_progress |
| 05/29/2026 | Interior lighting power | FAHAD FATEH | energy_progress |
| 05/29/2026 | Exterior lighting power | FAHAD FATEH | energy_progress |