← Back
One family attached or semi-detached
112-06 DUNKIRK STREET
QUEENS · BIN 4219790
💬 Discuss this project
1950Year Built
2Stories
A5Building Class
R2Zoning
1,188 sfGross Floor Area
1Units
One family attached or semi-detached · 2,423 sf lot · 0.49 FAR built · Flood zone X
Locations of Work
Architecture
Roof1p · 1 filing · 7 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
GREEN RIVER ENVIRONMENTAL ENGINEERI106/24/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NY State Solar LLC203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NYSS LLCGeneral Contractor303/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
GREEN RIVER ENVIRONMENTAL7841106/24/2025
Building Lifecycle
All (8)Filed (1)Permit Issued (1)Signed Off (1)Special Inspection (5)
12/01/2025
Signed off — Alteration
INSTALLATION OF PHOTOVOLTAIC SOLAR ARRAY ON EXISTING ROOF SYSTEM AS PER PLANS.
Q01245872-I1
07/01/2025
Permit issued — Solar
Q01245872-I1-SL
06/24/2025
Filed — Alteration
INSTALLATION OF PHOTOVOLTAIC SOLAR ARRAY ON EXISTING ROOF SYSTEM AS PER PLANS.
Q01245872-I1
06/24/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
ROBERT MASONE
06/24/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
ROBERT MASONE
06/24/2025
Special inspection requirement — Energy Code Compliance Inspections
ROBERT MASONE
06/24/2025
Special inspection requirement — Final
ROBERT MASONE
06/24/2025
Special inspection requirement — Air barrier - visual inspection
ROBERT MASONE
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offNYSS LLC07/01/2025
1 project · most recent 08/11/2025
FiledStatusContractorScope
08/11/2025CompleteNY SOLAR ELECTRICAL LLC—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
06/24/2025Fire-Resistant Penetrations and JointsROBERT MASONEspecial
06/24/2025Structural Stability – Alterations of existing buildingsROBERT MASONEspecial
06/24/2025Energy Code Compliance InspectionsROBERT MASONEprogress
06/24/2025FinalROBERT MASONEprogress
06/24/2025Air barrier - visual inspectionROBERT MASONEenergy_progress
▾Documents — 7 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/19/2026Q01245872-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
08/23/2026Q01245872-I1Open ↗
08/23/2026Q01245872-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/19/2026Q01245872-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/23/2026Q01245872-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/19/2026Q01245872-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01245872-I1Open ↗