| Firm | Filings | Most Recent |
|---|---|---|
| MLS COMPLETE ENGINEERING | 7 | 07/24/2026 |
| EDWARD C. HICKS RA | 5 | 06/09/2024 |
| EYAL LEVITT ARCHITECT PC | 1 | 10/06/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| BLOK ASSOCIATES | 11 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SB RENOVATION & MODELING | General Contractor | 8 | 03/21/2026 |
| ALL PRO PLBG & HTG INC | Plumbing | 2 | 07/08/2026 |
| ALL PRO PLBG & HTG INC | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CONCEPT ENGINEERING SERVI | 2562 | 4 | 07/24/2026 |
| CITISCAPE CONSULTING LTD | 762 | 1 | 10/06/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | ALL PRO PLBG & HTG INC | 03/11/2025 |
| DOB NOW | Sprinklers | Signed-off | ALL PRO PLBG & HTG INC | 02/19/2025 |
| DOB NOW | Construction Fence | Signed-off | SB RENOVATION & MODELING | 08/15/2024 |
| DOB NOW | General Construction | Permit Issued | SB RENOVATION & MODELING | 08/15/2024 |
| DOB NOW | Plumbing | Signed-off | ALL PRO PLBG & HTG INC | 02/20/2024 |
| DOB NOW | Foundation | Permit Issued | SB RENOVATION & MODELING | 08/24/2023 |
| DOB NOW | Construction Fence | Signed-off | SB RENOVATION & MODELING | 08/23/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/24/2026 | Signed-off | ALL PRO PLBG & HTG INC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/30/2025 | Complete | KINGS ELECTRIC CO., INC. | 1 meters, 1 new_meters |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/24/2026 | Signed-off | ALL PRO PLBG & HTG INC | Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/12/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/13/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/19/2025 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 02/27/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 02/25/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/14/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/28/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/07/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 03/07/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/24/2026 | Concrete - Cast-In-Place | Mansoor Sheikh | special |
| 07/24/2026 | Construction Operations Influencing Adjacent Structures | Mansoor Sheikh | special |
| 07/24/2026 | Excavations - Sheeting, Shoring, and Bracing | Mansoor Sheikh | special |
| 07/24/2026 | Fire-Resistant Penetrations and Joints | Mansoor Sheikh | special |
| 07/24/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | Mansoor Sheikh | special |
| 07/24/2026 | Structural Stability – Alterations of existing buildings | Mansoor Sheikh | special |
| 07/24/2026 | Subgrade Inspections | Mansoor Sheikh | special |
| 07/24/2026 | Final | Joe Lieberman | progress |
| 07/24/2026 | Fire-Resistance Rated Construction | Joe Lieberman | progress |
| 07/24/2026 | Footing and Foundation | Joe Lieberman | progress |
| 07/24/2026 | Structural Wood Frame | Joe Lieberman | progress |
| 07/24/2026 | Fenestration air leakage | Joe Lieberman | energy_progress |
| 07/24/2026 | Insulation placement and R values | Joe Lieberman | energy_progress |
| 07/24/2026 | Fenestration areas | Joe Lieberman | energy_progress |
| 07/24/2026 | Air barrier - visual inspection | Joe Lieberman | energy_progress |
| 07/24/2026 | Fenestration and door U-factor and product ratings | Joe Lieberman | energy_progress |
| 07/24/2026 | Lighting in dwelling units | Joe Lieberman | energy_progress |
| 05/26/2026 | Excavations - Sheeting, Shoring, and Bracing | Mansoor Sheikh | special |
| 05/26/2026 | Structural Stability – Alterations of existing buildings | Mansoor Sheikh | special |
| 05/26/2026 | Construction Operations Influencing Adjacent Structures | Mansoor Sheikh | special |
| 05/26/2026 | Subgrade Inspections | Mansoor Sheikh | special |
| 05/26/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | Mansoor Sheikh | special |
| 05/26/2026 | Fire-Resistant Penetrations and Joints | Mansoor Sheikh | special |
| 05/26/2026 | Concrete - Cast-In-Place | Mansoor Sheikh | special |
| 05/26/2026 | Final | Joe Lieberman | progress |