← Back
Elevator apt, fireproof with stores
First Houses (NYCHA)
112 EAST 3 STREET · East Village · BIN 1077944
💬 Discuss this project
1920Year Built
4Stories
D6Building Class
R8BZoning
101,908 sfGross Floor Area
262Units
LL97 Covered0 Open Violations
Elevator apt, fireproof with stores · Owner of record: NYC HOUSING AUTHORITY · 53,562 sf lot · 1.9 FAR built · Flood zone X
Locations of Work
ArchitectureStructural
Roof4p · 1 filing · 20 docs
Bulkhead1p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYCHA2607/08/2026
NYC HOUSING AUTHORITY303/22/2026
NYC HOUSING AUTHORITY 996203/22/2026
NYCHA CAPITAL PROJECTS PM TEAM1203/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
LGML GROUP503/21/2026
HOWARD I SHAPIRO ASSOCIATES403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
RAVEN CONSTRUCTION SERVICGeneral Contractor1907/08/2026
ADAM'S EUROPEAN CONTRACTINGGeneral Contractor607/08/2026
JAMES MAGRIPLESElectrical403/21/2026
SKYLINE P & H INCPlumbing203/22/2026
OMAR MAHMOUDElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MT GROUP798712/11/2024
JOEL PHAGOO ,PE, PLLC2416105/10/2023
Building Lifecycle
All (68)Filed (12)Permit Issued (13)Signed Off (4)Violation (3)Objection (6)Special Inspection (30)
01/21/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M00867994-I1
01/21/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY CHAIN LINK FENCE AS PER PLANS. CHAIN LINK FENCE SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M00868000-I1
01/21/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M00868046-I1
01/14/2025
Signed off — Alteration
BUILDING #8: MEANS & METHODS FOR PARTIAL DEMOLITION AT 5TH FLOOR AND ROOF LEVEL, INSTALLATION OF SHORING & BRACING, AND REPLACEMENT AS PER PLANS.
M00831787-I1
12/17/2024
Special inspection requirement — Structural Steel - Details
Marisa Harte
12/17/2024
Special inspection requirement — Construction Operations Influencing Adjacent Structures
Marisa Harte
12/17/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Marisa Harte
12/17/2024
Special inspection requirement — Concrete - Cast-In-Place
Marisa Harte
12/17/2024
Special inspection requirement — Wood – Seismic Resistance
CHRISTOPHER BEHLE
12/17/2024
Special inspection requirement — Masonry
Marisa Harte
12/17/2024
Special inspection requirement — Concrete - Precast
Marisa Harte
12/17/2024
Special inspection requirement — Structural Steel - High Strength Bolting
Marisa Harte
12/17/2024
Special inspection requirement — Tenant Protection Plan Compliance
CHRISTOPHER BEHLE
12/17/2024
Special inspection requirement — Post-installed Anchors
Marisa Harte
12/17/2024
Special inspection requirement — Construction Utilizing CLT or SCL, Type IV
Marisa Harte
12/17/2024
Special inspection requirement — Structural Steel - Welding
Marisa Harte
12/17/2024
Special inspection requirement — Fire-Resistance Rated Construction
Marisa Harte
12/17/2024
Special inspection requirement — Final
MICHAEL KALINOWSKI
12/17/2024
Special inspection requirement — Structural Wood Frame
Marisa Harte
12/11/2024
Filed — Alteration
BUILDING #8: MEANS & METHODS FOR PARTIAL DEMOLITION AT 5TH FLOOR AND ROOF LEVEL, INSTALLATION OF SHORING & BRACING, AND REPLACEMENT AS PER PLANS.
M00831787-P5
11/08/2024
Objection resolved — Addressed
10/11/2024
Special inspection requirement — Construction Utilizing CLT or SCL, Type IV
09/12/2024
Permit issued — Construction Fence
M00868000-I1-FN
08/02/2024
Permit issued — Construction Fence
M00868000-I1-FN
08/02/2024
Permit issued — Supported Scaffold
M00868046-I1-SF
07/01/2024
Permit issued — Structural
M00831787-I1-ST
06/26/2024
Permit issued — Structural
M00831787-I1-GC
05/07/2024
Permit issued — Sidewalk Shed
M00867994-I1-SH
10/10/2023
Objection resolved — Addressed
10/10/2023
Objection resolved — Addressed
10/05/2023
Special inspection requirement — Structural Steel - Welding
CHRISTOPHER BEHLE
10/05/2023
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
CHRISTOPHER BEHLE
10/05/2023
Special inspection requirement — Final
James Scheld
10/05/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
CHRISTOPHER BEHLE
10/05/2023
Special inspection requirement — Tenant Protection Plan Compliance
CHRISTOPHER BEHLE
10/05/2023
Special inspection requirement — Masonry
CHRISTOPHER BEHLE
10/03/2023
Objection raised — Other
10/03/2023
Objection raised — Other
10/03/2023
Objection raised — Other
09/28/2023
Filed — Alteration
BUILDING #8: MEANS & METHODS FOR PARTIAL DEMOLITION AT 5TH FLOOR AND ROOF LEVEL, INSTALLATION OF SHORING & BRACING, AND REPLACEMENT AS PER PLANS.
M00831787-P4
09/25/2023
Filed — Alteration
BUILDING #8: MEANS & METHODS FOR PARTIAL DEMOLITION AT 5TH FLOOR AND ROOF LEVEL, INSTALLATION OF SHORING & BRACING, AND REPLACEMENT AS PER PLANS.
M00831787-P3
09/22/2023
Filed — Alteration
BUILDING #8: MEANS & METHODS FOR PARTIAL DEMOLITION AT 5TH FLOOR AND ROOF LEVEL, INSTALLATION OF SHORING & BRACING, AND REPLACEMENT AS PER PLANS.
M00831787-S1
08/08/2023
Permit issued — Construction Fence
M00868000-I1-FN
08/08/2023
Permit issued — Supported Scaffold
M00868046-I1-SF
08/03/2023
Special inspection requirement — Structural Wood Frame
Marisa Harte
08/03/2023
Special inspection requirement — Concrete - Cast-In-Place
Marisa Harte
08/03/2023
Special inspection requirement — Concrete - Precast
Marisa Harte
08/03/2023
Special inspection requirement — Construction Operations Influencing Adjacent Structures
Marisa Harte
08/03/2023
Special inspection requirement — Masonry
Marisa Harte
08/03/2023
Special inspection requirement — Post-installed Anchors
Marisa Harte
08/03/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
Marisa Harte
08/03/2023
Special inspection requirement — Structural Steel - Details
Marisa Harte
07/13/2023
Filed — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M00867994-P1
07/13/2023
Filed — Alteration
INSTALLATION OF TEMPORARY CHAIN LINK FENCE AS PER PLANS. CHAIN LINK FENCE SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M00868000-P1
07/05/2023
Permit issued — Structural
M00831787-I1-ST
07/05/2023
Permit issued — General Construction
M00831787-I1-GC
06/13/2023
Filed — Alteration
BUILDING #8: MEANS & METHODS FOR PARTIAL DEMOLITION AT 5TH FLOOR AND ROOF LEVEL, INSTALLATION OF SHORING & BRACING, AND REPLACEMENT AS PER PLANS.
M00831787-P2
05/11/2023
Permit issued — Construction Fence
M00868000-I1-FN
05/11/2023
Permit issued — Sidewalk Shed
M00867994-I1-SH
05/11/2023
Permit issued — Supported Scaffold
M00868046-I1-SF
Latest 60 of 68 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWConstruction FenceSigned-offRAVEN CONSTRUCTION SERVIC09/12/2024
DOB NOWConstruction FenceSigned-offRAVEN CONSTRUCTION SERVIC08/02/2024
DOB NOWSupported ScaffoldSigned-offRAVEN CONSTRUCTION SERVIC08/02/2024
DOB NOWStructuralSigned-offADAM'S EUROPEAN CONTRACTING07/01/2024
DOB NOWStructuralSigned-offADAM'S EUROPEAN CONTRACTING06/26/2024
DOB NOWSidewalk ShedSigned-offRAVEN CONSTRUCTION SERVIC05/07/2024
DOB NOWConstruction FenceSigned-offRAVEN CONSTRUCTION SERVIC08/08/2023
DOB NOWSupported ScaffoldSigned-offRAVEN CONSTRUCTION SERVIC08/08/2023
DOB NOWStructuralSigned-offADAM'S EUROPEAN CONTRACTING07/05/2023
DOB NOWGeneral ConstructionSigned-offADAM'S EUROPEAN CONTRACTING07/05/2023
DOB NOWConstruction FenceSigned-offRAVEN CONSTRUCTION SERVIC05/11/2023
DOB NOWSidewalk ShedSigned-offRAVEN CONSTRUCTION SERVIC05/11/2023
DOB NOWSupported ScaffoldSigned-offRAVEN CONSTRUCTION SERVIC05/11/2023
BISEQISSUEDREGIONAL SCAFFOLD & HOISTING12/10/1998
BISEQISSUEDREGIONAL SCAFFOLD & HOISTING04/30/1998
BISEQISSUEDREGIONAL SCAFFOLD & HOISTING12/02/1997
8 projects · most recent 05/24/2024
General Wiring Lighting
FiledStatusContractorScope
05/24/2024CompleteTRI-STATE ELECL & MECHL IGeneral Wiring
02/28/2024CompleteJEMCO ELECT. CONTRS INCGeneral Wiring
02/28/2024CompleteJEMCO ELECT. CONTRS INCGeneral Wiring
02/28/2024CompleteJEMCO ELECT. CONTRS INCGeneral Wiring
02/28/2024CompleteJEMCO ELECT. CONTRS INCGeneral Wiring
07/14/2023CompleteARCADIA ELECT'L CO. INC.—
05/10/2023CompleteARCADIA ELECT'L CO. INC.—
08/17/2018CompleteMAC FHIONNGHAILE & SONSGeneral Wiring, Lighting
1 project · most recent 12/11/2024
Steel Concrete Wood
FiledStatusContractorScope
12/11/2024Signed-offADAM'S EUROPEAN CONTRACTISteel, Concrete, Wood
▾Special Inspection Requirements (DOB NOW) — 51
DateRequirementInspectorRole
12/17/2024Structural Steel - DetailsMarisa Hartespecial
12/17/2024Construction Operations Influencing Adjacent StructuresMarisa Hartespecial
12/17/2024Structural Stability – Alterations of existing buildingsMarisa Hartespecial
12/17/2024Concrete - Cast-In-PlaceMarisa Hartespecial
12/17/2024Wood – Seismic ResistanceCHRISTOPHER BEHLEspecial
12/17/2024MasonryMarisa Hartespecial
12/17/2024Concrete - PrecastMarisa Hartespecial
12/17/2024Structural Steel - High Strength BoltingMarisa Hartespecial
12/17/2024Tenant Protection Plan ComplianceCHRISTOPHER BEHLEspecial
12/17/2024Post-installed AnchorsMarisa Hartespecial
12/17/2024Construction Utilizing CLT or SCL, Type IVMarisa Hartespecial
12/17/2024Structural Steel - WeldingMarisa Hartespecial
12/17/2024Fire-Resistance Rated ConstructionMarisa Harteprogress
12/17/2024FinalMICHAEL KALINOWSKIprogress
12/17/2024Structural Wood FrameMarisa Harteprogress
10/11/2024Construction Utilizing CLT or SCL, Type IV—special
10/05/2023Structural Steel - WeldingCHRISTOPHER BEHLEspecial
10/05/2023Alternative Materials - OTCR Buildings Bulletin NumberCHRISTOPHER BEHLEspecial
10/05/2023FinalJames Scheldprogress
10/05/2023Structural Stability – Alterations of existing buildingsCHRISTOPHER BEHLEspecial
10/05/2023Tenant Protection Plan ComplianceCHRISTOPHER BEHLEspecial
10/05/2023MasonryCHRISTOPHER BEHLEspecial
08/03/2023Structural Wood FrameMarisa Harteprogress
08/03/2023Concrete - Cast-In-PlaceMarisa Hartespecial
08/03/2023Concrete - PrecastMarisa Hartespecial
Latest 25 of 51.
▾Documents — 87 on file (BIS + DOB NOW)
▸Plans & Drawings12
▸DOB NOWPlans/Sketch12
08/31/2026M00831787-P1Request digital key ↗
08/31/2026M00831787-P5Request digital key ↗
08/31/2026M00831787-I1Request digital key ↗
Showing 3 of 12 on file for this type
▸Applications & Permits8
▸DOB NOWLPC Approval/Permit7
08/13/2026M00831787-P3Open ↗
08/13/2026M00831787-I1Open ↗
08/13/2026M00831787-P1Open ↗
Showing 3 of 7 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION1
04/29/2019123805506Open ↗
▸Seals & Professional Certifications29
▸DOB NOWDPL-1: Design Professional Seal & Signature12
08/31/2026M00831787-I1Open ↗
08/31/2026M00831787-P5Open ↗
08/31/2026M00831787-P1Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature9
09/28/2026M00831787-I1Open ↗
09/28/2026M00831787-I1Open ↗
09/28/2026M00831787-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWProgress Inspector Seal & Signature7
09/28/2026M00831787-I1Open ↗
09/28/2026M00831787-I1Open ↗
09/01/2026M00831787-P2Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
04/29/2019123805506Open ↗
▸Safety & Tenant Protection1
▸BISTenant Protection Plan and Notes1
04/29/2019123805506Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/31/2026M00831787-P4Open ↗
08/31/2026M00831787-S1Open ↗
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form1
08/31/2026M00831787-I1Open ↗
▸Energy Compliance1
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
04/29/2019123805506Open ↗
▸Approvals, Objections & Sign-offs18
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter12
08/13/2026M00868046-I1Open ↗
08/13/2026M00831787-P1Open ↗
08/13/2026M00831787-P3Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)5
08/13/2026M00831787-P5Open ↗
08/13/2026M00831787-I1Open ↗
08/13/2026M00831787-P1Open ↗
Showing 3 of 5 on file for this type
▸BISLANDMARKS APPROVAL1
01/07/2020123805506Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
04/29/2019123805506Open ↗
▸Filing & Intake Forms2
▸BISADDITIONAL INFORMATION1
01/07/2020123805506Open ↗
▸BISEFILING COVER SHEET1
04/29/2019123805506Open ↗
▸Other Documents12
▸DOB NOWProof of Historic Building5
08/13/2026M00831787-I1Open ↗
08/13/2026M00831787-P1Open ↗
08/13/2026M00831787-P2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone5
08/13/2026M00831787-P1Open ↗
08/13/2026M00831787-I1Open ↗
08/13/2026M00831787-P3Open ↗
Showing 3 of 5 on file for this type
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION2
01/07/2020123805506Open ↗
04/29/2019123805506Open ↗