← Back
Elevator apt, fireproof with stores
First Houses (NYCHA)
112 EAST 3 STREET · East Village · BIN 1077949
💬 Discuss this project
1920Year Built
4Stories
D6Building Class
R8BZoning
101,908 sfGross Floor Area
262Units
LL97 Covered0 Open Violations
Elevator apt, fireproof with stores · Owner of record: NYC HOUSING AUTHORITY · 53,562 sf lot · 1.9 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalEquipmentGeneralOther
Roof20p · 3 filings · 20 docs
Floor 53p · 2 filings · 20 docs
Floor 41p · 1 filing · 18 docs
Floor 31p · 1 filing · 18 docs
Floor 21p · 1 filing · 18 docs
Floor 11p · 1 filing · 18 docs
Site & exterior25p · 3 filings · 15 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYCHA1207/08/2026
NEW YORK CITY HOUSING AUTHORITY703/22/2026
NYCHA CAPITAL PROJECTS PM TEAM1203/21/2026
NYC HOUSING203/21/2026
NYC Housing Authority103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
JOEL PHAGOO P.E. PLLC508/26/2024
SUPERSTRUCTURES ENG. + ARCH.308/22/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SUPERSTRUCTURES ENG + ARCH303/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
RAVEN CONSTRUCTION SERVICGeneral Contractor707/08/2026
JAMES MAGRIPLESElectrical503/21/2026
ADAM'S EUROPEAN CONTRACTINGGeneral Contractor203/21/2026
JEMCO ELECTRICAL CONT INCGeneral Contractor203/21/2026
SKYLINE P & H INCPlumbing203/22/2026
RIQUE CONSRUCTION INCElectrical103/21/2026
BILLS, ANTHONYElectrical103/21/2026
CONWAY, JR, WILLIAMElectrical103/21/2026
GEORGE BASSOLINOElectrical103/21/2026
AURICCHIO, ANNIELLEElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
JOEL PHAGOO ,PE, PLLC2416208/26/2024
MT GROUP798208/22/2023
Building Lifecycle
All (39)Filed (8)Permit Issued (7)Signed Off (5)Violation (4)Special Inspection (15)
10/24/2025
Signed off — Alteration
M01041164-I1
10/24/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY CHAIN LINK FENCE AS PER PLANS. CHAIN LINK FENCE SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M01041160-I1
06/18/2025
Signed off — Alteration
NYCHA 1st Houses Bldg 05, Exterior & Roof repairs per plans filed, including: Removal /replacement/ repairs to roofing system, bulkhead door, masonry, lintels, parapet & roof drains. Install new guard rails.
M00840376-I1
06/17/2025
Signed off — Alteration
NYCHA 1st Houses Bldg 05, Interior repairs per plans filed, including: Repair of damaged interior ceiling and wall plaster.
M00921313-I1
04/14/2025
Permit issued — Supported Scaffold
M01041164-I1-SF
04/03/2025
Permit issued — Construction Fence
M01041160-I1-FN
02/05/2025
Signed off — Alteration
M01041159-I1
01/30/2025
Permit issued — General Construction
M00921313-I1-GC
08/26/2024
Filed — Alteration
M01041164-P1
08/13/2024
Permit issued — Structural
M00840376-I1-GC-CX
06/23/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/17/2024
Filed — Alteration
M01041159-P1
04/30/2024
Filed — Alteration
M01041159-I1
04/30/2024
Permit issued — Sidewalk Shed
M01041159-I1-SH
04/25/2024
Filed — Alteration
M01041164-I1
04/25/2024
Filed — Alteration
INSTALLATION OF TEMPORARY CHAIN LINK FENCE AS PER PLANS. CHAIN LINK FENCE SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M01041160-I1
04/25/2024
Permit issued — Construction Fence
M01041160-I1-FN
04/25/2024
Permit issued — Supported Scaffold
M01041164-I1-SF
08/22/2023
Filed — Alteration
NYCHA 1st Houses Bldg 05, Exterior & Roof repairs per plans filed, including: Removal /replacement/ repairs to roofing system, bulkhead door, masonry, lintels, parapet & roof drains. Install new guard rails.
M00840376-P1
08/22/2023
Special inspection requirement — Insulation placement and R values
CHRISTOPHER BEHLE
08/22/2023
Special inspection requirement — Post-installed Anchors
CHRISTOPHER BEHLE
08/22/2023
Special inspection requirement — Masonry
CHRISTOPHER BEHLE
08/22/2023
Special inspection requirement — Tenant Protection Plan Compliance
CHRISTOPHER BEHLE
08/22/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
CHRISTOPHER BEHLE
08/22/2023
Special inspection requirement — Structural Wood Frame
CHRISTOPHER BEHLE
08/22/2023
Special inspection requirement — Final
Paul Millman
08/21/2023
Filed — Alteration
NYCHA 1st Houses Bldg 05, Interior repairs per plans filed, including: Repair of damaged interior ceiling and wall plaster.
M00921313-I1
08/18/2023
Special inspection requirement — Insulation placement and R values
Marisa Harte
08/18/2023
Special inspection requirement — Masonry
Marisa Harte
08/18/2023
Special inspection requirement — Post-installed Anchors
Marisa Harte
08/18/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
Marisa Harte
08/18/2023
Special inspection requirement — Tenant Protection Plan Compliance
08/18/2023
Special inspection requirement — Final
Paul Millman
08/18/2023
Special inspection requirement — Structural Wood Frame
Marisa Harte
08/17/2023
Special inspection requirement — Final
Paul Millman
05/02/2023
Filed — Alteration
NYCHA 1st Houses Bldg 05, Exterior & Roof repairs per plans filed, including: Removal /replacement/ repairs to roofing system, bulkhead door, masonry, lintels, parapet & roof drains. Install new guard rails.
M00840376-I1
04/22/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/20/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/01/1996
Violation issued (ECB, closed)
Elevators
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSupported ScaffoldSigned-offRAVEN CONSTRUCTION SERVIC04/14/2025
DOB NOWConstruction FenceSigned-offRAVEN CONSTRUCTION SERVIC04/03/2025
DOB NOWGeneral ConstructionSigned-offJEMCO ELECTRICAL CONT01/30/2025
DOB NOWStructuralSigned-offADAM'S EUROPEAN CONTRACTING08/13/2024
DOB NOWSidewalk ShedSigned-offRAVEN CONSTRUCTION SERVIC04/30/2024
DOB NOWConstruction FenceSigned-offRAVEN CONSTRUCTION SERVIC04/25/2024
DOB NOWSupported ScaffoldSigned-offRAVEN CONSTRUCTION SERVIC04/25/2024
BISPLISSUEDDELPHI PLBG. & HTG., INC06/13/2006
BISPLISSUEDV. C. VITANZA SONS INC10/06/2003
BISOTISSUEDV.C. VITANZA SONS INC04/04/2003
BISOTISSUEDV.C. VITANZA SONS INC03/26/2002
BISPLISSUEDV. C. VITANZA SONS INC11/05/2001
BISOTISSUEDV.C. VITANZA SONS INC08/23/2001
BISOTISSUEDV.C. VITANZA SONS INC10/18/2000
BISPLISSUEDV. C. VITANZA SONS INC10/18/2000
BISPLISSUEDV. C. VITANZA SONS INC09/22/1999
BISOTISSUEDV.C. VITANZA SONS INC09/22/1999
BISOTISSUEDV.C. VITANZA SONS INC07/09/1998
7 projects · most recent 07/03/2025
General Wiring Lighting
FiledStatusContractorScope
07/03/2025CompleteJEMCO ELECT. CONTRS INCGeneral Wiring
07/03/2025CompleteJEMCO ELECT. CONTRS INCGeneral Wiring
07/03/2025CompleteJEMCO ELECT. CONTRS INCGeneral Wiring
07/03/2025CompleteJEMCO ELECT. CONTRS INCGeneral Wiring
06/14/2024CompleteTRI-STATE ELECL & MECHL IGeneral Wiring
04/30/2024CompleteARCADIA ELECT'L CO. INC.General Wiring
08/17/2018CompleteMAC FHIONNGHAILE & SONSGeneral Wiring, Lighting
▾Special Inspection Requirements (DOB NOW) — 15
DateRequirementInspectorRole
08/22/2023Insulation placement and R valuesCHRISTOPHER BEHLEenergy_progress
08/22/2023Post-installed AnchorsCHRISTOPHER BEHLEspecial
08/22/2023MasonryCHRISTOPHER BEHLEspecial
08/22/2023Tenant Protection Plan ComplianceCHRISTOPHER BEHLEspecial
08/22/2023Structural Stability – Alterations of existing buildingsCHRISTOPHER BEHLEspecial
08/22/2023Structural Wood FrameCHRISTOPHER BEHLEprogress
08/22/2023FinalPaul Millmanprogress
08/18/2023Insulation placement and R valuesMarisa Harteenergy_progress
08/18/2023MasonryMarisa Hartespecial
08/18/2023Post-installed AnchorsMarisa Hartespecial
08/18/2023Structural Stability – Alterations of existing buildingsMarisa Hartespecial
08/18/2023Tenant Protection Plan Compliance—special
08/18/2023FinalPaul Millmanprogress
08/18/2023Structural Wood FrameMarisa Harteprogress
08/17/2023FinalPaul Millmanprogress
▾Documents — 48 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch8
08/29/2026M00921313-I1Request digital key ↗
08/29/2026M00840376-I1Request digital key ↗
08/29/2026M00840376-P1Request digital key ↗
Showing 3 of 8 on file for this type
▸Applications & Permits3
▸DOB NOWLPC Approval/Permit3
08/13/2026M00840376-P1Open ↗
08/13/2026M00921313-I1Open ↗
08/13/2026M00840376-I1Open ↗
▸Seals & Professional Certifications18
▸DOB NOWDPL-1: Design Professional Seal & Signature8
08/29/2026M00840376-P1Open ↗
08/29/2026M00840376-I1Open ↗
08/27/2026M01041164-P1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWProgress Inspector Seal & Signature7
08/25/2026M00840376-P1Open ↗
08/25/2026M00840376-P1Open ↗
08/25/2026M00840376-P1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature2
08/25/2026M00840376-P1Open ↗
08/25/2026M00840376-I1Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
04/29/2019123805472Open ↗
▸Safety & Tenant Protection1
▸BISTenant Protection Plan and Notes1
04/29/2019123805472Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/29/2026M00840376-P1Open ↗
08/29/2026M00840376-I1Open ↗
08/13/2026M00921313-I1Open ↗
▸Energy Compliance1
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
04/29/2019123805472Open ↗
▸Approvals, Objections & Sign-offs9
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter8
08/27/2026M01041164-I1Open ↗
08/27/2026M01041164-P1Open ↗
08/27/2026M01041159-P1Open ↗
Showing 3 of 8 on file for this type
▸BISLANDMARKS APPROVAL1
01/06/2020123805472Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
04/29/2019123805472Open ↗
▸Filing & Intake Forms3
▸BISEFILING COVER SHEET2
04/29/2019123805472Open ↗
04/29/2019123805472Open ↗
▸BISADDITIONAL INFORMATION1
01/06/2020123805472Open ↗
▸Other Documents1
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
04/29/2019123805472Open ↗