← Back
Elevator apt, fireproof with stores
First Houses (NYCHA)
112 EAST 3 STREET · East Village · BIN 1077952
💬 Discuss this project
1920Year Built
4Stories
D6Building Class
R8BZoning
101,908 sfGross Floor Area
262Units
LL97 Covered0 Open Violations
Elevator apt, fireproof with stores · Owner of record: NYC HOUSING AUTHORITY · 53,562 sf lot · 1.9 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalGeneralOther
Roof3p · 1 filing · 14 docs
Bulkhead1p · 1 filing · 14 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYCHA1207/08/2026
NEW YORK CITY HOUSING AUTHORITY803/22/2026
NYCHA CAPITAL PROJECTS PM TEAM1203/21/2026
NYC HOUSING AUTHORITY403/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
JOEL PHAGOO P.E. PLLC507/30/2024
SUPERSTRUCTURES ENG. + ARCH.308/22/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SUPERSTRUCTURES ENG + ARCH303/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
RAVEN CONSTRUCTION SERVICGeneral Contractor707/08/2026
JAMES MAGRIPLESElectrical503/21/2026
ADAM'S EUROPEAN CONTRACTINGGeneral Contractor203/21/2026
JEMCO ELECTRICAL CONT INCGeneral Contractor203/21/2026
SKYLINE P & H INCPlumbing203/22/2026
RIQUE CONSRUCTION INCElectrical103/21/2026
JEMCO ELECT. CONTRS INCElectrical103/22/2026
QUINTANA, DAVIDElectrical103/21/2026
CHETRAM, RISHIRAMElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
JOEL PHAGOO ,PE, PLLC2416207/30/2024
MT GROUP798208/22/2023
Building Lifecycle
All (31)Filed (8)Permit Issued (5)Signed Off (5)Violation (2)Special Inspection (11)
06/17/2025
Signed off — Alteration
NYCHA 1st Houses Bldg 04, Interior repairs per plans filed, including: Repair of damaged interior ceiling and wall plaster.
M00921199-I1
03/24/2025
Signed off — Alteration
NYCHA 1st Houses Bldg 04, Exterior & Roof repairs per plans filed, including: Removal /replacement/ repairs to roofing system, bulkhead door, masonry, lintels, parapet & roof drains. Install new guard rails.
M00840357-I1
02/24/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY CHAIN LINK FENCE AS PER PLANS. CHAIN LINK FENCE SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M01041151-I1
02/24/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M01041155-I1
02/05/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M01041144-I1
01/23/2025
Permit issued — General Construction
M00921199-I1-GC
07/30/2024
Filed — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M01041155-P1
07/30/2024
Special inspection requirement — Post-installed Anchors
JOEL PHAGOO
06/25/2024
Permit issued — Structural
M00840357-I1-GC-CX
06/17/2024
Filed — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M01041144-P1
04/30/2024
Filed — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M01041144-I1
04/30/2024
Permit issued — Sidewalk Shed
M01041144-I1-SH
04/25/2024
Filed — Alteration
INSTALLATION OF TEMPORARY CHAIN LINK FENCE AS PER PLANS. CHAIN LINK FENCE SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M01041151-I1
04/25/2024
Filed — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M01041155-I1
04/25/2024
Permit issued — Construction Fence
M01041151-I1-FN
04/25/2024
Permit issued — Supported Scaffold
M01041155-I1-SF
08/22/2023
Filed — Alteration
NYCHA 1st Houses Bldg 04, Exterior & Roof repairs per plans filed, including: Removal /replacement/ repairs to roofing system, bulkhead door, masonry, lintels, parapet & roof drains. Install new guard rails.
M00840357-P1
08/21/2023
Filed — Alteration
NYCHA 1st Houses Bldg 04, Interior repairs per plans filed, including: Repair of damaged interior ceiling and wall plaster.
M00921199-I1
08/18/2023
Special inspection requirement — Masonry
Marisa Harte
08/18/2023
Special inspection requirement — Post-installed Anchors
Marisa Harte
08/18/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
Marisa Harte
08/18/2023
Special inspection requirement — Structural Steel - Details
Marisa Harte
08/18/2023
Special inspection requirement — Tenant Protection Plan Compliance
08/18/2023
Special inspection requirement — Final
Paul Millman
08/18/2023
Special inspection requirement — Structural Wood Frame
Marisa Harte
08/18/2023
Special inspection requirement — Insulation placement and R values
Marisa Harte
08/18/2023
Special inspection requirement — Structural Steel - High Strength Bolting
Marisa Harte
08/17/2023
Special inspection requirement — Final
Paul Millman
05/02/2023
Filed — Alteration
NYCHA 1st Houses Bldg 04, Exterior & Roof repairs per plans filed, including: Removal /replacement/ repairs to roofing system, bulkhead door, masonry, lintels, parapet & roof drains. Install new guard rails.
M00840357-I1
01/17/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/12/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offJEMCO ELECTRICAL CONT01/23/2025
DOB NOWStructuralSigned-offADAM'S EUROPEAN CONTRACTING06/25/2024
DOB NOWSidewalk ShedSigned-offRAVEN CONSTRUCTION SERVIC04/30/2024
DOB NOWConstruction FenceSigned-offRAVEN CONSTRUCTION SERVIC04/25/2024
DOB NOWSupported ScaffoldSigned-offRAVEN CONSTRUCTION SERVIC04/25/2024
BISPLISSUEDQMB PLUMBING & HEATING INC01/24/2018
BISPLISSUEDORBIT PLBG & HTG INC10/04/2017
BISOTRE-ISSUEDWEST STREET INTERIORS INC09/29/2017
BISOTISSUEDPOLYSTRUCT INC05/19/2014
BISEQISSUEDBILTMORE GENERAL CONTRACTORS06/17/2013
BISPLISSUEDBBM PLUMBING & HTNG INC11/16/2008
BISPLISSUEDDELPHI PLBG. & HTG., INC06/13/2006
BISPLISSUEDV. C. VITANZA SONS INC10/06/2003
BISOTISSUEDV.C. VITANZA SONS INC04/04/2003
BISEQISSUEDZHN CONTRACTING CORP06/07/2002
BISOTISSUEDV.C. VITANZA SONS INC03/26/2002
BISPLISSUEDV. C. VITANZA SONS INC11/05/2001
BISOTISSUEDV.C. VITANZA SONS INC08/23/2001
BISOTISSUEDV.C. VITANZA SONS INC10/18/2000
BISOTISSUEDV.C. VITANZA SONS INC10/19/1999
BISPLISSUEDV. C. VITANZA SONS INC10/06/1999
BISOTISSUEDV.C. VITANZA SONS INC07/09/1998
BISPLISSUEDV. C. VITANZA SONS INC07/09/1998
8 projects · most recent 08/25/2026
General Wiring Lighting
FiledStatusContractorScope
08/25/2026CompleteASSET ELECTRIC CORP—
07/03/2025CompleteJEMCO ELECT. CONTRS INCGeneral Wiring
07/03/2025CompleteJEMCO ELECT. CONTRS INCGeneral Wiring
07/03/2025CompleteJEMCO ELECT. CONTRS INCGeneral Wiring
07/03/2025CompleteJEMCO ELECT. CONTRS INCGeneral Wiring
06/14/2024CompleteTRI-STATE ELECL & MECHL IGeneral Wiring
04/30/2024CompleteARCADIA ELECT'L CO. INC.General Wiring
08/17/2018CompleteMAC FHIONNGHAILE & SONSGeneral Wiring, Lighting
▾Special Inspection Requirements (DOB NOW) — 11
DateRequirementInspectorRole
07/30/2024Post-installed AnchorsJOEL PHAGOOspecial
08/18/2023MasonryMarisa Hartespecial
08/18/2023Post-installed AnchorsMarisa Hartespecial
08/18/2023Structural Stability – Alterations of existing buildingsMarisa Hartespecial
08/18/2023Structural Steel - DetailsMarisa Hartespecial
08/18/2023Tenant Protection Plan Compliance—special
08/18/2023FinalPaul Millmanprogress
08/18/2023Structural Wood FrameMarisa Harteprogress
08/18/2023Insulation placement and R valuesMarisa Harteenergy_progress
08/18/2023Structural Steel - High Strength BoltingMarisa Hartespecial
08/17/2023FinalPaul Millmanprogress
▾Documents — 93 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch8
08/29/2026M00921199-I1Request digital key ↗
08/29/2026M00840357-I1Request digital key ↗
08/29/2026M00840357-P1Request digital key ↗
Showing 3 of 8 on file for this type
▸Applications & Permits16
▸BISWORK PERMIT APPLICATION8
01/26/2018122836574Open ↗
01/25/2018122836574Open ↗
10/05/2017122836574Open ↗
Showing 3 of 8 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION5
04/29/2019123805463Open ↗
09/26/2017122836574Open ↗
05/08/2014121999016Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWLPC Approval/Permit3
08/13/2026M00921199-I1Open ↗
08/13/2026M00840357-I1Open ↗
08/13/2026M00840357-P1Open ↗
▸Seals & Professional Certifications26
▸DOB NOWDPL-1: Design Professional Seal & Signature8
08/29/2026M00921199-I1Open ↗
08/27/2026M01041155-I1Open ↗
08/27/2026M01041144-I1Open ↗
Showing 3 of 8 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION5
04/29/2019123805463Open ↗
09/26/2017122836574Open ↗
05/08/2014121999016Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
08/26/2026M00921199-I1Open ↗
08/25/2026M00840357-P1Open ↗
08/25/2026M00840357-P1Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
05/08/2014121999016Open ↗
06/17/2013140088722Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST2
05/08/2014121999016Open ↗
05/27/2008110176345Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/01/2026M01041155-P1Open ↗
08/25/2026M00840357-P1Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
06/17/2013140088722Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
06/17/2013140088722Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
05/27/2008110176345Open ↗
▸Trade Schedules & Equipment3
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
09/26/2017122836574Open ↗
▸BISSCHEDULE B - PLUMBING1
05/27/2008110176345Open ↗
▸BISSELF-CERT PLUMBING NOTICE1
02/19/2009110176345Open ↗
▸Safety & Tenant Protection2
▸BISTenant Protection Plan and Notes2
04/29/2019123805463Open ↗
09/26/2017122836574Open ↗
▸Environmental & Asbestos6
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/29/2026M00921199-I1Open ↗
08/13/2026M00840357-I1Open ↗
08/13/2026M00840357-P1Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
09/26/2017122836574Open ↗
05/08/2014121999016Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
05/27/2008110176345Open ↗
▸Energy Compliance3
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
04/29/2019123805463Open ↗
09/26/2017122836574Open ↗
05/08/2014121999016Open ↗
▸Approvals, Objections & Sign-offs16
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter8
08/27/2026M01041155-I1Open ↗
08/27/2026M01041144-I1Open ↗
08/13/2026M00921199-I1Open ↗
Showing 3 of 8 on file for this type
▸BISLANDMARKS APPROVAL4
01/06/2020123805463Open ↗
09/26/2017122836574Open ↗
05/14/2014121999016Open ↗
Showing 3 of 4 on file for this type
▸BISADMINISTRATIVE OBJECTIONS1
05/27/2008110176345Open ↗
▸BISSUPERSEDING LETTER1
01/25/2018122836574Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
04/13/2009110176345Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
01/26/2018122836574Open ↗
▸Cost, Insurance & Ownership5
▸BISCOST AFFIDAVIT5
04/29/2019123805463Open ↗
09/26/2017122836574Open ↗
05/08/2014121999016Open ↗
Showing 3 of 5 on file for this type
▸Filing & Intake Forms6
▸BISEFILING COVER SHEET4
04/29/2019123805463Open ↗
09/26/2017122836574Open ↗
05/08/2014121999016Open ↗
Showing 3 of 4 on file for this type
▸BISADDITIONAL INFORMATION1
01/06/2020123805463Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
06/17/2013140088722Open ↗
▸Other Documents2
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION2
04/29/2019123805463Open ↗
05/08/2014121999016Open ↗