| Owner | Filings | Most Recent |
|---|---|---|
| RUSSELL SAGE FOUNDATION | 35 | 07/08/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| THORNTON TOMASETTI | 1 | 03/06/2025 |
| PLAN B ARCHITECTS P.C. | 2 | 09/21/2023 |
| BENDIX ENGINEERING, P.C. | 1 | 04/27/2022 |
| SOCOTEC, INC. | 1 | 04/27/2022 |
| STANTEC | 2 | 07/20/2021 |
| EDWARDS AND ZUCK | 2 | 08/05/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| FRAMEWORK CONSULTANTS | 2 | 03/21/2026 |
| RIZZO GROUP | 4 | 03/21/2026 |
| EXPEDITION NYC | 2 | 03/21/2026 |
| ANDRA CONSTANTIN EXPEDITER | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HOLT CONSTRUCTION CORP | General Contractor | 5 | 07/08/2026 |
| PRAT ENTERPRISES CORP | General Contractor | 2 | 07/08/2026 |
| LAWRENCE J. LEVINE | Fire Protection | 2 | 03/21/2026 |
| LAB PLBG & HTG CO INC | Plumbing | 1 | 07/08/2026 |
| PAUL BOCCIA | Electrical | 1 | 03/21/2026 |
| PAR PLUMBING CO., INC | Plumbing | 1 | 07/08/2026 |
| PAR FIRE PROTECTION LLC | Fire Protection | 1 | 07/08/2026 |
| DONNELLY MECHANICAL CORP | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ALAN MARGOLIN & ASSOC | 423 | 1 | 09/21/2023 |
| BENDIX ENGINEERING, P.C. | 4293 | 1 | 04/27/2022 |
| SOCOTEC ENGINEERING | 4983 | 1 | 04/27/2022 |
| SKYLINE ENGINEERING, PLLC | 267 | 2 | 07/20/2021 |
| MEP INSPECTIONS, INC | 1102 | 2 | 08/05/2019 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | PRAT ENTERPRISES CORP | 04/13/2026 |
| DOB NOW | General Construction | Signed-off | PRAT ENTERPRISES CORP | 04/15/2025 |
| DOB NOW | General Construction | Permit Issued | HOLT CONSTRUCTION CORP | 04/26/2024 |
| DOB NOW | General Construction | Signed-off | DONNELLY MECHANICAL CORP | 03/26/2024 |
| DOB NOW | Plumbing | Signed-off | PAR PLUMBING CO., INC | 07/07/2022 |
| DOB NOW | General Construction | Permit Issued | HOLT CONSTRUCTION CORP | 07/06/2022 |
| DOB NOW | Mechanical Systems | Signed-off | HOLT CONSTRUCTION CORP | 07/06/2022 |
| DOB NOW | Plumbing | Signed-off | LAB PLBG & HTG CO INC | 01/28/2021 |
| DOB NOW | Mechanical Systems | Signed-off | HOLT CONSTRUCTION CORP | 10/16/2019 |
| DOB NOW | Sprinklers | Signed-off | LAWRENCE J. LEVINE | 08/15/2019 |
| BIS | OT | ISSUED | HOLT CONSTRUCTION CORP | 02/22/2021 |
| BIS | OT | ISSUED | HOLT CONSTRUCTION CORP | 12/17/2020 |
| BIS | SP | ISSUED | SIRINA FIRE PROT CORP | 07/16/2015 |
| BIS | MH | ISSUED | HOLT CONSTRUCTION CORP | 06/19/2015 |
| BIS | OT | ISSUED | HOLT CONSTRUCTION CORP | 06/19/2015 |
| BIS | OT | ISSUED | VMMA CONSTRUCTION LLC | 12/10/2012 |
| BIS | OT | ISSUED | VMMA CONSTRUCTION LLC | 08/20/2012 |
| BIS | FP | ISSUED | MASTER FIRE SYSTEMS, INC | 08/09/2002 |
| BIS | OT | ISSUED | A.W. & S. CONSTRUCTION CO | 07/11/2002 |
| BIS | SP | ISSUED | ASCO SPRINKLER CO.,INC | 07/10/2002 |
| BIS | OT | ISSUED | A.W. & S. CONSTRUCTION CO | 03/25/2002 |
| BIS | OT | ISSUED | PROGRESSIVE CONTRUCTION ,INC. | 07/17/1996 |
| BIS | MH | ISSUED | JOHNSON CONTROLS INC | 03/02/1993 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/27/2022 | Signed-off | PAR PLUMBING CO., INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/07/2024 | Complete | BIGMAN BROS., INC. | General Wiring |
| 07/13/2022 | Permit Issued | BIGMAN BROS., INC. | General Wiring, Lighting |
| 04/28/2021 | Complete | MONTGOMERY ELEC'L CONTR'G | General Wiring |
| 11/18/2020 | Complete | LIVE WIRE ELECTRIC 1 LLC | General Wiring |
| 05/13/2020 | Complete | P.S. MARCATO ELEV. CO INC | — |
| 08/07/2019 | Complete | VERDE ELECTRIC CORP. | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/08/2023 | Post-installed Anchors | Young Suh | special |
| 08/24/2023 | Final | MATTHEW BROWER | progress |
| 04/26/2022 | HVAC-R and service water heating system controls | ALEXIS SCHLESSINGERMAN | energy_progress |
| 04/26/2022 | Maintenance information | ALEXIS SCHLESSINGERMAN | energy_progress |
| 04/26/2022 | Shutoff dampers | ALEXIS SCHLESSINGERMAN | energy_progress |
| 04/26/2022 | Ventilation and air distribution system | ALEXIS SCHLESSINGERMAN | energy_progress |
| 04/26/2022 | HVAC-R and service water piping design and insulation | ALEXIS SCHLESSINGERMAN | energy_progress |
| 04/26/2022 | Fire-Resistance Rated Construction | ALEXIS SCHLESSINGERMAN | progress |
| 04/26/2022 | HVAC-R and service water heating equipment | ALEXIS SCHLESSINGERMAN | energy_progress |
| 04/26/2022 | Energy Code Compliance Inspections | ALEXIS SCHLESSINGERMAN | progress |
| 02/11/2022 | Fire-Resistant Penetrations and Joints | Matthew Bendix | special |
| 02/08/2022 | Mechanical Systems | ALEXIS SCHLESSINGERMAN | special |
| 02/08/2022 | Final | ALEXIS SCHLESSINGERMAN | progress |
| 06/25/2021 | Fire-Resistant Penetrations and Joints | Matthew Wavro | special |
| 07/16/2019 | HVAC and service water heating system controls | Nicolas Crosetto | energy_progress |
| 07/16/2019 | Fire-Resistant Penetrations and Joints | Nicolas Crosetto | special |
| 07/16/2019 | Mechanical Systems | Nicolas Crosetto | special |
| 07/16/2019 | Fire-Resistant Penetrations and Joints | Nicolas Crosetto | special |
| 07/16/2019 | Final | Nicolas Crosetto | progress |
| 07/16/2019 | HVAC insulation and sealing | Nicolas Crosetto | energy_progress |
| 07/16/2019 | Sprinkler Systems | Nicolas Crosetto | special |