1899Year Built
2Stories
B2Building Class
R6Zoning
2,088 sfGross Floor Area
2Units
10 Active Violations 1 likely answered ▸FDNY Report ↗
Two family frame · Owner of record: 1128 BSD · 2,379 sf lot · 0.88 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofProposed 4 Story & Cellar Residential / Community Facility BUnder Construction41p · 3 filings · 20 docs
BulkheadProposed 4 Story & Cellar Residential / Community Facility BUnder Construction2p · 1 filing · 20 docs
Floor 4Proposed 4 Story & Cellar Residential / Community Facility BUnder Construction38p · 2 filings · 20 docs
Floor 3Proposed 4 Story & Cellar Residential / Community Facility BUnder Construction37p · 2 filings · 20 docs
Floor 2Proposed 4 Story & Cellar Residential / Community Facility BUnder Construction42p · 3 filings · 20 docs
Floor 1Proposed 4 Story & Cellar Residential / Community Facility BUnder Construction36p · 2 filings · 20 docs
Mezzanine1p · 1 filing · 12 docs
CellarProposed 4 Story & Cellar Residential / Community Facility BUnder Construction42p · 2 filings · 20 docs
Site & exteriorHeavy duty sidewalk shed installationUnder Construction12p · 3 filings · 6 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
1128BSD2808/27/2026
Brightstone Developers404/09/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
04/24/2025$1.7M—— → —$814/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Vasilios Artemiou PE303/18/2026
Ashraf203/17/2026
SH Engineering411/26/2025
NY Building Associates108/28/2025
South Bay Engineering207/17/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Moses Katz Associates1403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Lionstone DevelopersGeneral Contractor608/26/2026
J & G Construction ServicesScaffold306/27/2026
Lionstone DevelopersScaffold207/08/2026
Tap PlumbingPlumbing107/08/2026
Power Direct ElectricElectrical103/22/2026
Wiz Fire SprinklersFire Protection107/02/2026
N Tech Design of AmericaGeneral Contractor104/09/2026
Plumbing NYCPlumbing108/27/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Shahrish Shuvo Engineering8524703/18/2026
South Bay Engineering PLL6682103/27/2025
Building Lifecycle
All (150)Filed (12)Permit Issued (15)Signed Off (7)Violation (14)Inspection (2)Objection (70)Special Inspection (30)
08/27/2026
Signed off — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
B01368297-I1
08/27/2026
Signed off — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B01368299-I1
08/26/2026
Signed off — New Building
Plumbing & Sprinkler application filed in conjunction to job #B01278627-I1.
B01278627-S1
08/26/2026
Permit issued — Sprinklers
B99517517-S3-PL
08/20/2026
Signed off — New Building
Plumbing & Sprinkler application filed in conjunction to job #B01278627-I1.
B01278627-S5
08/08/2026
Violation issued (ECB, open)
Unknown
08/08/2026
Violation issued (ECB, open)
Unknown
07/16/2026
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
07/14/2026
Permit issued — Mechanical Systems
B01278627-S4-MS
07/14/2026
Violation issued (ECB, open)
Construction
07/14/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
06/30/2026
Permit issued — Sprinklers
B01278627-S3-EW-SP
06/25/2026
Permit issued — Sidewalk Shed
B01368297-I1-SH
06/17/2026
Permit issued — Plumbing
B01278627-S3-PL
05/11/2026
Signed off — New Building
Plumbing & Sprinkler application filed in conjunction to job #B01278627-I1.
B01278627-S6
05/11/2026
Signed off — New Building
Plumbing & Sprinkler application filed in conjunction to job #B01278627-I1.
B01278627-S2
04/23/2026
Permit issued — Foundation
B01278627-S1-FO-EA
04/23/2026
Permit issued — Structural
B01278627-S5-ST
04/21/2026
Permit issued — General Construction
B01278627-I1-GC
04/20/2026
Permit issued — Support of Excavation
B01278627-S2-SE
04/20/2026
Permit issued — Foundation
B01278627-S6-FO
03/27/2026
Special inspection requirement — Energy Code Compliance Inspections
Shahrish Shuvo
03/27/2026
Special inspection requirement — Maintenance information
Shahrish Shuvo
03/27/2026
Special inspection requirement — HVAC-R and service water heating system controls
Shahrish Shuvo
03/27/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Shahrish Shuvo
03/27/2026
Special inspection requirement — HVAC-R and service water heating equipment
Shahrish Shuvo
03/27/2026
Special inspection requirement — Sprinkler Systems
Shahrish Shuvo
03/27/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Shahrish Shuvo
03/27/2026
Special inspection requirement — Post-installed Anchors
Shahrish Shuvo
03/27/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Shahrish Shuvo
03/19/2026
Permit issued — Sidewalk Shed
B01368297-I1-SH
03/18/2026
Filed — New Building
Plumbing & Sprinkler application filed in conjunction to job #B01278627-I1.
B01278627-P1
03/17/2026
Filed — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
B01368297-I1
03/16/2026
Permit issued — Supported Scaffold
B01368299-I1-SF
03/14/2026
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B01368299-I1
02/19/2026
Objection raised — Other
02/19/2026
Objection resolved — Addressed
02/19/2026
Objection resolved — Addressed
02/19/2026
Objection resolved — Addressed
02/10/2026
Objection resolved — Addressed
02/05/2026
Objection resolved — Addressed
01/27/2026
Objection raised — Other
01/22/2026
Filed — New Building
Plumbing & Sprinkler application filed in conjunction to job #B01278627-I1.
B01278627-S3
01/21/2026
Objection resolved — Addressed
01/20/2026
Objection resolved — Addressed
01/16/2026
Objection raised — Energy
01/16/2026
Objection raised — Other
01/16/2026
Objection resolved — Addressed
01/16/2026
Objection raised — Other
01/12/2026
Filed — New Building
Plumbing & Sprinkler application filed in conjunction to job #B01278627-I1.
B01278627-S4
01/09/2026
Objection resolved — Addressed
01/08/2026
Objection raised — Other
01/06/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Shahrish Shuvo
01/06/2026
Special inspection requirement — Post-installed Anchors
Shahrish Shuvo
01/06/2026
Special inspection requirement — Fire-Resistance Rated Construction
Shahrish Shuvo
01/06/2026
Special inspection requirement — HVAC-R and service water heating system controls
Shahrish Shuvo
01/06/2026
Special inspection requirement — HVAC-R and service water heating equipment
Shahrish Shuvo
01/06/2026
Special inspection requirement — Maintenance information
Shahrish Shuvo
01/06/2026
Special inspection requirement — Duct leakage testing, insulation and design
Shahrish Shuvo
01/06/2026
Special inspection requirement — Shutoff dampers
Shahrish Shuvo
Latest 60 of 150 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedPlumbing NYC08/26/2026
DOB NOWMechanical SystemsPermit IssuedLionstone Developers07/14/2026
DOB NOWSprinklersPermit IssuedWiz Fire Sprinklers06/30/2026
DOB NOWSidewalk ShedSigned-offJ & G Construction Services06/25/2026
DOB NOWPlumbingPermit IssuedTap Plumbing06/17/2026
DOB NOWFoundationSigned-offLionstone Developers04/23/2026
DOB NOWStructuralSigned-offLionstone Developers04/23/2026
DOB NOWGeneral ConstructionPermit IssuedLionstone Developers04/21/2026
DOB NOWSupport of ExcavationSigned-offLionstone Developers04/20/2026
DOB NOWFoundationSigned-offLionstone Developers04/20/2026
DOB NOWSidewalk ShedSigned-offJ & G Construction Services03/19/2026
DOB NOWSupported ScaffoldSigned-offJ & G Construction Services03/16/2026
DOB NOWConstruction FencePermit IssuedLionstone Developers11/03/2025
DOB NOWFull DemolitionSigned-offN Tech Design of America09/18/2025
DOB NOWConstruction FencePermit IssuedLionstone Developers07/21/2025
1 project · most recent 03/18/2026
Heating and Air Conditioning Systems Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
03/18/2026Permit IssuedLionstone DevelopersHeating and Air Conditioning Systems, Heating Systems, Ventilation Systems
Heat / Cool
Daikin RXTQ60AAVJU 57,500 BTU · Vrf Outdoor ×5
Heating
Qmark LFK-151F 175 CFM · Electric Heater ×5
Ventilation
Nutone PTE511RK 50 CFM · Exhaust Fan ×8
PTEL511RK 100 CFM · Exhaust Fan ×5
1 project · most recent 03/18/2026
Sprinkler System
FiledStatusContractorScope
03/18/2026Permit IssuedWiz Fire SprinklersSprinkler System
1 project · most recent 03/18/2026
Gas Storm Water/Sanitary
FiledStatusContractorScope
03/18/2026Permit IssuedComplete PH DesignGas, Storm, Water/Sanitary
3 projects · most recent 10/08/2026
General Wiring
FiledStatusContractorScope
10/08/2026Permit IssuedPower Direct ElectricGeneral Wiring
03/06/2026CompleteRichard Neu—
12/18/2025Permit IssuedPower Direct Electric—
1 project · most recent 03/18/2026
Steel Concrete
FiledStatusContractorScope
03/18/2026Permit IssuedLionstone DevelopersSteel, Concrete
3 projects · most recent 03/17/2026
Sidewalk Shed Scaffold Fence
FiledStatusContractorScope
03/17/2026Signed-offJ & G Construction ServicesSidewalk Shed
03/14/2026Signed-offJ & G Construction ServicesScaffold
07/17/2025Permit IssuedLionstone DevelopersFence
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
07/16/2026Pass-Final PL - Up to 9 Requested FloorsPassView ↗
07/14/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 42
DateRequirementInspectorRole
03/27/2026Energy Code Compliance InspectionsShahrish Shuvoprogress
03/27/2026Maintenance informationShahrish Shuvoenergy_progress
03/27/2026HVAC-R and service water heating system controlsShahrish Shuvoenergy_progress
03/27/2026HVAC-R and service water piping design and insulationShahrish Shuvoenergy_progress
03/27/2026HVAC-R and service water heating equipmentShahrish Shuvoenergy_progress
03/27/2026Sprinkler SystemsShahrish Shuvospecial
03/27/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationShahrish Shuvospecial
03/27/2026Post-installed AnchorsShahrish Shuvospecial
03/27/2026Fire-Resistant Penetrations and JointsShahrish Shuvospecial
01/06/2026HVAC-R and service water piping design and insulationShahrish Shuvoenergy_progress
01/06/2026Post-installed AnchorsShahrish Shuvospecial
01/06/2026Fire-Resistance Rated ConstructionShahrish Shuvoprogress
01/06/2026HVAC-R and service water heating system controlsShahrish Shuvoenergy_progress
01/06/2026HVAC-R and service water heating equipmentShahrish Shuvoenergy_progress
01/06/2026Maintenance informationShahrish Shuvoenergy_progress
01/06/2026Duct leakage testing, insulation and designShahrish Shuvoenergy_progress
01/06/2026Shutoff dampersShahrish Shuvoenergy_progress
11/26/2025Concrete - Cast-In-PlaceShahrish Shuvospecial
11/18/2025Structural Cold-Formed SteelShahrish Shuvospecial
11/18/2025Structural Steel - WeldingShahrish Shuvospecial
11/18/2025Subsurface Investigations (Borings/Test Pits)Bin Lispecial
11/18/2025Subgrade InspectionsShahrish Shuvospecial
11/18/2025Structural Steel - WeldingShahrish Shuvospecial
11/18/2025Structural Steel - DetailsShahrish Shuvospecial
11/18/2025Post-installed AnchorsShahrish Shuvospecial
Latest 25 of 42.
▾Documents — 70 on file (BIS + DOB NOW)
▸Plans & Drawings12
▸DOB NOWPlans/Sketch12
08/22/2026B01181079-I1Request digital key ↗
08/21/2026B01252738-I1Request digital key ↗
08/19/2026B01278627-P1Request digital key ↗
Showing 3 of 12 on file for this type
▸Zoning, Tax Lot & Property Records3
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B01278627-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
08/13/2026B01278627-I1Open ↗
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026B01278627-I1Open ↗
▸Seals & Professional Certifications30
▸DOB NOWDPL-1: Design Professional Seal & Signature12
08/22/2026B01181079-I1Open ↗
08/21/2026B01252738-I1Open ↗
08/19/2026B01278627-P1Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature9
09/23/2026B01278627-S5Open ↗
09/01/2026B01278627-S3Open ↗
08/31/2026B01278627-S6Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWProgress Inspector Seal & Signature9
09/23/2026B01278627-S5Open ↗
09/01/2026B01278627-S3Open ↗
09/01/2026B01278627-S3Open ↗
Showing 3 of 9 on file for this type
▸Trade Schedules & Equipment5
▸DOB NOWElectric Cut-Off1
08/13/2026B01181079-I1Open ↗
▸DOB NOWWater Cut-Off1
08/13/2026B01181079-I1Open ↗
▸DOB NOWGas Cut-Off1
08/13/2026B01181079-I1Open ↗
▸DOB NOWSewer Cut-Off1
08/13/2026B01181079-I1Open ↗
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)1
08/13/2026B01278627-I1Open ↗
▸Safety & Tenant Protection2
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B01278627-I1Open ↗
▸DOB NOWStreet Tree Checklist1
08/15/2026B01278627-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWRodent Control1
08/13/2026B01181079-I1Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/22/2026B01181079-I1Open ↗
▸Inspections & Test Reports7
▸DOB NOWSOIL REPORT3
08/13/2026B01278627-S6Open ↗
08/13/2026B01278627-S1Open ↗
08/13/2026B01278627-S2Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram3
08/14/2026B01278627-S1Open ↗
08/14/2026B01278627-S2Open ↗
08/13/2026B01278627-S6Open ↗
▸DOB NOWTR4: Test Report and Plot Diagram1
08/13/2026B01278627-S2Open ↗
▸Other Documents9
▸DOB NOWProperty Ownership Certification2
08/22/2026B01181079-I1Open ↗
08/15/2026B01278627-I1Open ↗
▸DOB NOWAdjoining Owners Notification2
08/14/2026B01278627-S1Open ↗
08/14/2026B01278627-S2Open ↗
▸DOB NOWFull Demo: 10-Day Notice1
08/13/2026B01181079-I1Open ↗
▸DOB NOWStructure Photographs1
08/13/2026B01181079-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026B01278627-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026B01278627-I1Open ↗
▸DOB NOWCommunity Board Notification1
08/13/2026B01181079-I1Open ↗