| Owner | Filings | Most Recent |
|---|---|---|
| NYCHA | 34 | 07/08/2026 |
| NYC HOUSING AUTHORITY | 3 | 03/22/2026 |
| NYC HOUSING AUTHORITY 9 | 1 | 03/22/2026 |
| NYCHA 99 | 1 | 03/22/2026 |
| SKYWORX CONTRACTING | 1 | 03/22/2026 |
| NEELAM CONSTRUCTION CORP | 1 | 03/21/2026 |
| TALICO CONTRACTING | 4 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ZI ENGINEERING, P.C | 2 | 09/24/2025 |
| BITOPI CONSULTANTS LLC | 4 | 10/24/2024 |
| AK CONSULTING SERVICES, INC | 2 | 10/24/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| AK CONSULTING SERVICES | 16 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MNK ENTERPRISES LLC | General Contractor | 24 | 07/08/2026 |
| SKYWORX CONTRACTING INC | General Contractor | 6 | 07/08/2026 |
| CHARNJIT SINGH | Electrical | 3 | 03/21/2026 |
| LADIKOS, DIMITRIOS | Electrical | 1 | 03/21/2026 |
| LIT MODE ELECL CONTG INC | Electrical | 1 | 03/22/2026 |
| P & K CONTRACTING INC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TECTONIC ENGINEERING CONS | 106 | 2 | 09/24/2025 |
| AK CONSULTING SERVICES, I | 6198 | 2 | 02/26/2025 |
| BITOPI CONSULTANTS LLC | 7036 | 1 | 10/24/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Signed-off | MNK ENTERPRISES LLC | 06/27/2025 |
| DOB NOW | Supported Scaffold | Signed-off | MNK ENTERPRISES LLC | 06/27/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | MNK ENTERPRISES LLC | 06/27/2025 |
| DOB NOW | General Construction | Signed-off | P & K CONTRACTING INC | 03/27/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | D&N CONST & CONSULTNG INC | 11/19/2024 |
| DOB NOW | Construction Fence | Signed-off | MNK ENTERPRISES LLC | 10/28/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | MNK ENTERPRISES LLC | 10/28/2024 |
| DOB NOW | Supported Scaffold | Signed-off | MNK ENTERPRISES LLC | 10/28/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | MNK ENTERPRISES LLC | 07/02/2024 |
| DOB NOW | Construction Fence | Permit Issued | MNK ENTERPRISES LLC | 06/28/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | MNK ENTERPRISES LLC | 02/01/2024 |
| DOB NOW | Construction Fence | Permit Issued | MNK ENTERPRISES LLC | 01/31/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | MNK ENTERPRISES LLC | 03/02/2023 |
| DOB NOW | Construction Fence | Permit Issued | MNK ENTERPRISES LLC | 03/01/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | SKYWORX CONTRACTING INC | 08/20/2022 |
| DOB NOW | Construction Fence | Permit Issued | SKYWORX CONTRACTING INC | 04/07/2022 |
| DOB NOW | Construction Fence | Permit Issued | SKYWORX CONTRACTING INC | 06/22/2021 |
| DOB NOW | Construction Fence | Permit Issued | SKYWORX CONTRACTING INC | 06/03/2020 |
| BIS | EQ | ISSUED | SKYWORX CONTRACTING INC | 10/11/2022 |
| BIS | EQ | ISSUED | SKYWORX CONTRACTING INC | 09/30/2021 |
| BIS | EQ | ISSUED | SKYWORX CONTRACTING INC | 10/21/2020 |
| BIS | EQ | ISSUED | SKYWORX CONTRACTING INC | 10/15/2019 |
| BIS | EQ | ISSUED | SKYWORX CONTRACTING INC | 10/12/2018 |
| BIS | EQ | ISSUED | TALICO CONTRACTING INC | 01/12/2018 |
| BIS | EQ | ISSUED | TALICO CONTRACTING INC | 01/19/2017 |
| BIS | EQ | ISSUED | ROMA SCAFFOLDING INC | 04/14/2016 |
| BIS | EQ | ISSUED | AKRO GENERAL CONTRACTING | 12/04/2014 |
| BIS | EQ | ISSUED | AKRO GENERAL CONTRACTING | 11/12/2013 |
| BIS | EQ | ISSUED | AKRO GENERAL CONTRACTING | 07/11/2013 |
| BIS | PL | ISSUED | DUAL FUEL PLUBING & HTING | 02/26/2007 |
| BIS | EQ | ISSUED | AMC UNITED INC | 09/07/2001 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/09/2025 | Complete | LIT MODE ELECL CONTG INC | — |
| 10/09/2025 | Complete | LIT MODE ELECL CONTG INC | — |
| 07/15/2025 | Complete | LIT MODE ELECL CONTG INC | — |
| 05/20/2020 | Permit Issued | AMIN ELECTRICAL CORP | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/25/2025 | Masonry | GEORGE GHEBRYAL | special |
| 09/25/2025 | Structural Stability – Alterations of existing buildings | GEORGE GHEBRYAL | special |
| 09/25/2025 | Tenant Protection Plan Compliance | GEORGE GHEBRYAL | special |
| 09/25/2025 | Final | GEORGE GHEBRYAL | progress |
| 07/15/2025 | Final | GEORGE GHEBRYAL | progress |
| 07/15/2025 | Masonry | GEORGE GHEBRYAL | special |
| 07/15/2025 | Structural Stability – Alterations of existing buildings | GEORGE GHEBRYAL | special |
| 07/15/2025 | Tenant Protection Plan Compliance | GEORGE GHEBRYAL | special |
| 02/27/2025 | Post-installed Anchors | MAHFUZAR RAHMAN | special |
| 02/27/2025 | Structural Stability – Alterations of existing buildings | MAHFUZAR RAHMAN | special |
| 02/26/2025 | Post-installed Anchors | MAHFUZAR RAHMAN | special |
| 02/26/2025 | Structural Stability – Alterations of existing buildings | MAHFUZAR RAHMAN | special |