← Back
Primarily 2 family with 1 store or office
113-65 SPRINGFIELD BLVD
QUEENS · BIN 4242123
💬 Discuss this project
1935Year Built
2Stories
S2Building Class
R3-2Zoning
2,400 sfGross Floor Area
3Units
Rent Stabilized0 Open ViolationsFDNY Report ↗
Primarily 2 family with 1 store or office · Owner of record: QN 96 LLC · 2,000 sf lot · 1.2 FAR built · Flood zone X
Locations of Work
Architecture
Roof1p · 1 filing · 15 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
QN 48807/08/2026
BLACKSTONE REAL GROUP607/08/2026
QN 96 LLC103/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/05/2023$46K—Private party → QN 96 LLC$19/sf building
12/05/2023$282K—Private party → QN 96 LLC$118/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
J.K.DESIGN402/12/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
BLACKSTONE REAL GROUP403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NY CITY CONSTRUCTION*General Contractor407/08/2026
ROCK E SMALL PLBG&HTG INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP5616302/12/2025
Building Lifecycle
All (109)Filed (4)Permit Issued (3)Signed Off (3)Violation (48)Inspection (5)Objection (16)Special Inspection (30)
03/04/2025
Signed off — Alteration
Interior renovation of an existing two stories mixed use building. First floor store ,second floor two dwelling units. New drywall partitions ,plumbing fixtures ,and all finish materials as per plans. No change in use .egress or occupancy.
Q01000125-I1
03/03/2025
Signed off — Alteration
Q01013856-I1
03/03/2025
Signed off — Alteration
Installation of new gas fired equipment and plumbing fixtures for the renovation of the existing building. Filed in conjunction with ALT II application #Q01000125-I1
Q01061681-I1
02/27/2025
Special inspection requirement — Permanent certificate
FAHAD FATEH
02/27/2025
Special inspection requirement — Fenestration air leakage
FAHAD FATEH
02/27/2025
Special inspection requirement — Air barrier - visual inspection
FAHAD FATEH
02/27/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
FAHAD FATEH
02/27/2025
Special inspection requirement — Interior lighting power
FAHAD FATEH
02/27/2025
Special inspection requirement — Fenestration areas
FAHAD FATEH
02/27/2025
Special inspection requirement — Wood – Seismic Resistance
FAHAD FATEH
02/27/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
02/27/2025
Special inspection requirement — Structural Wood Frame
FAHAD FATEH
02/27/2025
Special inspection requirement — Final
jacob Kanner
02/27/2025
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
02/27/2025
Special inspection requirement — Fire-Resistance Rated Construction
FAHAD FATEH
02/12/2025
Filed — Alteration
Interior renovation of an existing two stories mixed use building. First floor store ,second floor two dwelling units. New drywall partitions ,plumbing fixtures ,and all finish materials as per plans. No change in use .egress or occupancy.
Q01000125-P1
02/12/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
02/12/2025
Special inspection requirement — Wood – Seismic Resistance
02/12/2025
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
02/12/2025
Special inspection requirement — Final
jacob Kanner
02/12/2025
Special inspection requirement — Fire-Resistance Rated Construction
FAHAD FATEH
02/12/2025
Special inspection requirement — Structural Wood Frame
FAHAD FATEH
02/12/2025
Special inspection requirement — Fenestration air leakage
FAHAD FATEH
02/12/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
FAHAD FATEH
02/12/2025
Special inspection requirement — Air barrier - visual inspection
FAHAD FATEH
02/12/2025
Special inspection requirement — Fenestration areas
FAHAD FATEH
02/12/2025
Special inspection requirement — Permanent certificate
FAHAD FATEH
02/12/2025
Special inspection requirement — Interior lighting power
FAHAD FATEH
12/16/2024
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
06/26/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
06/26/2024
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
06/26/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
06/26/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
06/17/2024
Permit issued — Plumbing
Q01061681-I1-PL
06/12/2024
Filed — Alteration
Installation of new gas fired equipment and plumbing fixtures for the renovation of the existing building. Filed in conjunction with ALT II application #Q01000125-I1
Q01061681-I1
06/05/2024
Special inspection requirement — Maintenance information
FAHAD FATEH
06/05/2024
Special inspection requirement — HVAC-R and service water heating system controls
FAHAD FATEH
06/05/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
FAHAD FATEH
06/05/2024
Special inspection requirement — HVAC-R and service water heating equipment
FAHAD FATEH
06/05/2024
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
06/05/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
05/22/2024
Permit issued — Construction Fence
Q01013856-I1-FN
04/16/2024
Permit issued — General Construction
Q01000125-I1-GC-CX
03/29/2024
Objection resolved — Addressed
03/28/2024
Objection resolved — Addressed
03/28/2024
Objection resolved — Addressed
03/28/2024
Objection resolved — Addressed
03/18/2024
Objection resolved — Addressed
03/18/2024
Objection resolved — Addressed
03/16/2024
Objection resolved — Addressed
03/15/2024
Objection raised — Fire_Protection
03/15/2024
Objection raised — Other
03/15/2024
Objection raised — Other
03/15/2024
Objection raised — Fire_Protection
03/15/2024
Objection raised — Other
03/15/2024
Objection raised — Other
03/05/2024
Filed — Alteration
Q01013856-I1
03/04/2024
Objection resolved — Addressed
03/01/2024
Objection raised — Scope
03/01/2024
Objection raised — Scope
Latest 60 of 109 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offROCK E SMALL PLBG&HTG INC06/17/2024
DOB NOWConstruction FenceSigned-offNY CITY CONSTRUCTION*05/22/2024
DOB NOWGeneral ConstructionSigned-offNY CITY CONSTRUCTION*04/16/2024
BISFPISSUEDALL-BORO FIRE AND SAFETY EQUIP08/18/1998
1 project · most recent 01/17/2024
General Wiring
FiledStatusContractorScope
01/17/2024CompleteRONEY ELECTRIC INCGeneral Wiring
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
12/16/2024Fail-Final PL - Up to 3 Requested FloorsFailView ↗
06/26/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
06/26/2024Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
06/26/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/26/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 30
DateRequirementInspectorRole
02/27/2025Permanent certificateFAHAD FATEHenergy_progress
02/27/2025Fenestration air leakageFAHAD FATEHenergy_progress
02/27/2025Air barrier - visual inspectionFAHAD FATEHenergy_progress
02/27/2025Fenestration and door U-factor and product ratingsFAHAD FATEHenergy_progress
02/27/2025Interior lighting powerFAHAD FATEHenergy_progress
02/27/2025Fenestration areasFAHAD FATEHenergy_progress
02/27/2025Wood – Seismic ResistanceFAHAD FATEHspecial
02/27/2025Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
02/27/2025Structural Wood FrameFAHAD FATEHprogress
02/27/2025Finaljacob Kannerprogress
02/27/2025Energy Code Compliance InspectionsFAHAD FATEHprogress
02/27/2025Fire-Resistance Rated ConstructionFAHAD FATEHprogress
02/12/2025Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
02/12/2025Wood – Seismic Resistance—special
02/12/2025Energy Code Compliance InspectionsFAHAD FATEHprogress
02/12/2025Finaljacob Kannerprogress
02/12/2025Fire-Resistance Rated ConstructionFAHAD FATEHprogress
02/12/2025Structural Wood FrameFAHAD FATEHprogress
02/12/2025Fenestration air leakageFAHAD FATEHenergy_progress
02/12/2025Fenestration and door U-factor and product ratingsFAHAD FATEHenergy_progress
02/12/2025Air barrier - visual inspectionFAHAD FATEHenergy_progress
02/12/2025Fenestration areasFAHAD FATEHenergy_progress
02/12/2025Permanent certificateFAHAD FATEHenergy_progress
02/12/2025Interior lighting powerFAHAD FATEHenergy_progress
06/05/2024Maintenance informationFAHAD FATEHenergy_progress
Latest 25 of 30.
▾Documents — 23 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/23/2026Q01000125-P1Request digital key ↗
08/23/2026Q01000125-I1Request digital key ↗
08/23/2026Q01013856-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸Seals & Professional Certifications16
▸DOB NOWProgress Inspector Seal & Signature8
08/31/2026Q01000125-I1Open ↗
08/31/2026Q01000125-I1Open ↗
08/31/2026Q01000125-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/23/2026Q01000125-I1Open ↗
08/13/2026Q01013856-I1Open ↗
08/13/2026Q01061681-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/31/2026Q01000125-I1Open ↗
08/31/2026Q01000125-I1Open ↗
08/29/2026Q01000125-P1Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/23/2026Q01000125-I1Open ↗
08/13/2026Q01000125-P1Open ↗
08/13/2026Q01061681-I1Open ↗