| Owner | Filings | Most Recent |
|---|---|---|
| 835 WALTON | 14 | 03/21/2026 |
| RETTNER BUILDING MANAGEMENT | 9 | 07/08/2026 |
| 835 WEALTON | 5 | 03/21/2026 |
| LEVITES REALTY | 4 | 03/21/2026 |
| F C ACQUISITION ASSOC | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| SBLM ARCHITECTS, PC | 2 | 08/29/2024 |
| HNY CONSULTING ENGINEERS LLC | 2 | 08/29/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| DOMINION EXPEDITING | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CUSTOM COMMERCIAL CONSTRUCTION | General Contractor | 4 | 07/08/2026 |
| ARTECO AND DESIGN RESTORA | Electrical | 1 | 03/21/2026 |
| EDWARDS ROLAND | Electrical | 1 | 03/21/2026 |
| GLENFORD HARRINGTON | Electrical | 1 | 03/21/2026 |
| ROLAND EDWARDS | Electrical | 1 | 03/21/2026 |
| DUO PLUMBING & HTG CORP. | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CHOI ENGINEERING PLLC | 2264 | 1 | 08/29/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | DUO PLUMBING & HTG CORP. | 10/02/2024 |
| DOB NOW | General Construction | Signed-off | CUSTOM COMMERCIAL CONSTRU | 09/11/2024 |
| DOB NOW | Mechanical Systems | Signed-off | CUSTOM COMMERCIAL CONSTRU | 09/11/2024 |
| DOB NOW | General Construction | Signed-off | CUSTOM COMMERCIAL CONSTRU | 09/11/2024 |
| BIS | PL | ISSUED | CAPITAL CONTR P&H CORP | 08/23/2019 |
| BIS | PL | ISSUED | CAPITAL CONTR P&H CORP | 07/23/2019 |
| BIS | MH | ISSUED | ABCO MAINTENANCE INC | 07/17/2019 |
| BIS | MH | ISSUED | ABCO MAINTENANCE INC | 12/13/2018 |
| BIS | PL | ISSUED | CASINO MECHANICAL CORP | 08/15/2014 |
| BIS | MH | ISSUED | ABCO MAINTENANCE INC | 08/15/2014 |
| BIS | OT | ISSUED | MELITO CONSTRUCTION CORP | 06/27/2013 |
| BIS | — | ISSUED | NATIONAL MAINTENANCE, INC | 02/01/2012 |
| BIS | — | ISSUED | NATIONAL MAINTENANCE, INC | 02/01/2012 |
| BIS | — | ISSUED | NATIONAL MAINTENANCE, INC | 02/01/2012 |
| BIS | — | ISSUED | NATIONAL MAINTENANCE, INC | 02/01/2012 |
| BIS | MH | ISSUED | DU-RITE CONSTRUCTION INC | 05/02/2011 |
| BIS | PL | ISSUED | PARKVIEW P&H INC | 01/06/2011 |
| BIS | — | ISSUED | NATIONAL MAINTENANCE, INC | 08/26/2010 |
| BIS | OT | ISSUED | DU-RITE CONSTRUCTION INC | 05/14/2010 |
| BIS | OT | ISSUED | DU-RITE CONSTRUCTION INC | 05/14/2010 |
| BIS | MH | ISSUED | DU-RITE CONSTRUCTION INC | 05/14/2010 |
| BIS | SP | ISSUED | MANENGEERING BUREAU INC | 04/27/1999 |
| BIS | PL | ISSUED | CASINO MECHANICAL CORP | 11/20/1998 |
| BIS | PL | ISSUED | CASINO MECHANICAL CORP | 11/17/1998 |
| BIS | EQ | ISSUED | DISCOVER GENERAL CONTRACTING | 09/11/1998 |
| BIS | — | ISSUED | DISCOVER GENERAL CONTRACTING | 09/04/1998 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/06/2026 | Complete | FIRST CHOICE ELECTRICAL | General Wiring |
| 03/06/2026 | Complete | FIRST CHOICE ELECTRICAL | General Wiring |
| 01/22/2020 | Complete | ECLIPSE ELECTRIC CORP | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/26/2024 | Interior lighting power | Eugene Choi | energy_progress |
| 08/26/2024 | Lighting controls | Eugene Choi | energy_progress |
| 08/20/2024 | Final | Eugene Choi | progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| CVS Pharmacy | Retail | Floor 1 | Project S01091950 |