← Back
Two family frame
114-08 89 AVENUE
QUEENS · Richmond Hill · BIN 4195707
💬 Discuss this project
1920Year Built
2.5Stories
B2Building Class
R4AZoning
2,371 sfGross Floor Area
2Units
0 Open ViolationsFDNY Report ↗
Two family frame · 3,325 sf lot · 0.71 FAR built · Flood zone X
Locations of Work
Electrical
Roof1 filing · 6 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR102/03/2025
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281102/03/2025
Building Lifecycle
All (8)Filed (1)Permit Issued (1)Violation (1)Special Inspection (5)
02/05/2025
Permit issued — Solar
Q01174236-I1-SL
02/03/2025
Filed — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 9 Panels, 3.69 kW
Q01174236-I1
01/30/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
01/30/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
01/30/2025
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
01/30/2025
Special inspection requirement — Final
Mina Makar
01/30/2025
Special inspection requirement — Air barrier - visual inspection
Mina Makar
08/31/1994
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedMOMENTUM SOLAR02/05/2025
BISOTISSUEDNYC WATERPROOFING CO12/30/1994
1 project · most recent 02/06/2025
FiledStatusContractorScope
02/06/2025CompleteISLAND ELECTRIC CORP—
1 project · most recent 02/03/2025
FiledStatusContractorScope
02/03/2025Permit IssuedMOMENTUM SOLAR9 panels, 3.69 kw, 159 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
01/30/2025Fire-Resistant Penetrations and JointsMina Makarspecial
01/30/2025Structural Stability – Alterations of existing buildingsMina Makarspecial
01/30/2025Energy Code Compliance InspectionsMina Makarprogress
01/30/2025FinalMina Makarprogress
01/30/2025Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 6 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/21/2026Q01174236-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
08/27/2026Q01174236-I1Open ↗
08/27/2026Q01174236-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/21/2026Q01174236-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/27/2026Q01174236-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/21/2026Q01174236-I1Open ↗