← Back
Two family converted from one family
114-56 142 STREET
QUEENS · Baisley Park · BIN 4259181
💬 Discuss this project
1955Year Built
1.5Stories
B3Building Class
R3AZoning
1,020 sfGross Floor Area
2Units
Two family converted from one family · 4,000 sf lot · 0.26 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
A PETER LUGER CONSTRUCTION407/08/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
RAS PE CONSULTING ENGINEERS107/10/2020
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
A PETER LUGER CONSTRUC INGeneral Contractor107/08/2026
Building Lifecycle
All (4)Filed (1)Permit Issued (1)Signed Off (1)Special Inspection (1)
11/09/2020
Signed off — Alteration
Herewith Filing Construction fence drawings to install 8'-0" high construction fence around the lot line. Installation of fence is to facilitate Demolition work. This job is being filed in conjunction with DM application filed under job number 421732003
Q00368577-I1
07/21/2020
Permit issued — Construction Fence
Q00368577-I1-FN
07/10/2020
Filed — Alteration
Herewith Filing Construction fence drawings to install 8'-0" high construction fence around the lot line. Installation of fence is to facilitate Demolition work. This job is being filed in conjunction with DM application filed under job number 421732003
Q00368577-I1
07/09/2020
Special inspection requirement — Final
Rizwan Salam
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWConstruction FenceSigned-offA PETER LUGER CONSTRUC IN07/21/2020
BISEQISSUEDHEERA & G BUILDERS INC09/29/2020
BIS—ISSUEDHEERA & G BUILDERS INC09/02/2020
BISOTISSUEDSUNRUN INSTALLATION SVC06/02/2016
1 project · most recent 07/14/2020
FiledStatusContractorScope
07/14/2020Permit IssuedAUJLA ELECTRIC CORP—
▾Special Inspection Requirements (DOB NOW) — 1
DateRequirementInspectorRole
07/09/2020FinalRizwan Salamprogress
▾Documents — 47 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch - Construction Fence1
08/28/2026Q00368577-I1Request digital key ↗
▸Applications & Permits6
▸BISPLAN / WORK APPROVAL APPLICATION3
07/30/2019421732003Open ↗
03/20/2019421740012Open ↗
05/31/2016440314492Open ↗
▸BISWORK PERMIT APPLICATION3
10/20/2020421732003Open ↗
10/20/2020421732003Open ↗
05/31/2016440314492Open ↗
▸Seals & Professional Certifications5
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
05/31/2016440314492Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
05/31/2016440314492Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
05/31/2016440314492Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/28/2026Q00368577-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature1
08/29/2026Q00368577-I1Open ↗
▸Trade Schedules & Equipment3
▸BISGAS CUT-OFF1
11/04/2020421732003Open ↗
▸BISELECTRIC CUT-OFF1
11/04/2020421732003Open ↗
▸BISSEWER CUT-OFF1
11/04/2020421732003Open ↗
▸Safety & Tenant Protection2
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE1
11/04/2020421732003Open ↗
▸BISTENANT PROTECTION PLAN AND NOTES1
05/31/2016440314492Open ↗
▸Environmental & Asbestos2
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
11/04/2020421732003Open ↗
05/31/2016440314492Open ↗
▸Energy Compliance7
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
02/02/2017440314492Open ↗
05/31/2016440314492Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
02/02/2017440314492Open ↗
▸BISSOLAR TAX ABATEMENT APPLICATION1
02/02/2017440314492Open ↗
▸BISNYCECC ANALYSIS1
05/31/2016440314492Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
05/31/2016440314492Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
05/31/2016440314492Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
02/02/2017440314492Open ↗
05/31/2016440314492Open ↗
▸Approvals, Objections & Sign-offs10
▸BISLETTERS - SUPPORTING DOCUMENTATION6
11/04/2020421732003Open ↗
11/04/2020421732003Open ↗
11/04/2020421732003Open ↗
Showing 3 of 6 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
02/02/2017440314492Open ↗
▸BISTAP LETTER - DOM SVC : DEP-DOM1
11/04/2020421732003Open ↗
▸BISLANDMARKS APPROVAL1
11/04/2020421732003Open ↗
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
02/02/2017440314492Open ↗
▸Cost, Insurance & Ownership3
▸BISCOST AFFIDAVIT2
02/24/2017440314492Open ↗
05/31/2016440314492Open ↗
▸BISPROJECT-SPECIFIC GL INSURANCE1
11/04/2020421732003Open ↗
▸Filing & Intake Forms5
▸BISEFILING COVER SHEET2
07/30/2019421732003Open ↗
03/20/2019421740012Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
05/31/2016440314492Open ↗
▸BISADDITIONAL INFORMATION1
06/29/2016440314492Open ↗
▸BISBOROUGH INTAKE FORM1
10/20/2020421732003Open ↗
▸Other Documents1
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
08/02/2019421740012Open ↗