| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/03/2026 | Permit Issued | TARGET PIPING NY LLC | 60 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/03/2026 | Permit Issued | TARGET PIPING NY LLC | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/24/2026 | Complete | SOLAS ELECTRICAL CORP | — |
| 07/16/2025 | Complete | NAPSTAR ELECTRIC INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/08/2025 | Signed-off | AMBROSINO CONST CORP | Steel, Concrete, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/09/2025 | Signed-off | AMBROSINO CONST CORP | Fence |
| Owner | Filings | Most Recent |
|---|---|---|
| NEIGHBORHOOD RESTORE HDFC | 22 | 09/18/2026 |
| RESTORED HOMES HDFC | 4 | 07/08/2026 |
| OWNERS REP | 9 | 04/09/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ROSENTHAL ENGINEERING PLLC | 5 | 08/03/2026 |
| SONI ENGINEERING CONSULTING | 4 | 11/12/2025 |
| CITYSCAPE ENGINEERING, PLLC | 3 | 08/08/2025 |
| RICHARD WAINER ARCHITECT, PLLC | 1 | 06/09/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| BMB BUILDING CONSULTING | 10 | 03/21/2026 |
| AE DESIGN SOLUTION | 8 | 03/21/2026 |
| AMBROSINO CONSTRUCTION | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| AMBROSINO CONST CORP | General Contractor | 7 | 07/08/2026 |
| CORE SCAFFOLD SYSTEMS INC. | General Contractor | 6 | 04/09/2026 |
| TARGET PIPING NY LLC | Fire Protection | 2 | 09/17/2026 |
| B&B MECH PLBG & HTG LLC | Plumbing | 2 | 09/18/2026 |
| VINCENZO NAPOLITANO | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AMERICAN CONSTRUCTION TES | 9731 | 6 | 08/03/2026 |
| CROSSCHECK INSPECTION SER | 544 | 2 | 08/08/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | B&B MECH PLBG & HTG LLC | 09/17/2026 |
| DOB NOW | Plumbing | Permit Issued | TARGET PIPING NY LLC | 09/16/2026 |
| DOB NOW | Construction Fence | Signed-off | AMBROSINO CONST CORP | 06/16/2026 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | CORE SCAFFOLD SYSTEMS INC | 01/05/2026 |
| DOB NOW | Supported Scaffold | Signed-off | CORE SCAFFOLD SYSTEMS INC | 11/13/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | CORE SCAFFOLD SYSTEMS INC | 11/13/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | CORE SCAFFOLD SYSTEMS INC | 11/13/2025 |
| DOB NOW | Plumbing | Permit Issued | TARGET PIPING NY LLC | 09/04/2025 |
| DOB NOW | Plumbing | Permit Issued | TARGET PIPING NY LLC | 09/04/2025 |
| DOB NOW | Structural | Signed-off | AMBROSINO CONST | 06/13/2025 |
| DOB NOW | Construction Fence | Signed-off | AMBROSINO CONST | 06/10/2025 |
| DOB NOW | Mechanical Systems | Signed-off | AMBROSINO CONST | 06/09/2025 |
| BIS | — | ISSUED | AMBROSINO CONST CORP | 06/13/2025 |
| BIS | — | ISSUED | AMBROSINO CONST CORP | 06/13/2025 |
| BIS | EQ | ISSUED | HERITAGE V LLC | 06/23/2017 |
| BIS | — | ISSUED | HERITAGE V LLC | 06/23/2017 |
| BIS | — | ISSUED | HERITAGE V LLC | 06/23/2017 |
| BIS | EQ | ISSUED | SCALA CONTRACTING CO INC | 05/12/2006 |
| BIS | — | ISSUED | SCALA CONTRACTING CO INC | 05/12/2006 |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/02/2026 | Pass-Final SP - Up to 9 Requested Floors | Pass | View ↗ |
| 08/27/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/05/2026 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 10/29/2025 | Pass-Final PL - Underground | Pass | View ↗ |
| 09/12/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/13/2026 | Maintenance information | EDWIN HOPKINS | energy_progress |
| 08/13/2026 | HVAC-R and service water piping design and insulation | EDWIN HOPKINS | energy_progress |
| 08/13/2026 | Fire-Resistant Penetrations and Joints | EDWIN HOPKINS | special |
| 08/13/2026 | Sprinkler Systems | EDWIN HOPKINS | special |
| 08/13/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | EDWIN HOPKINS | special |
| 08/13/2026 | Energy Code Compliance Inspections | EDWIN HOPKINS | progress |
| 07/13/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | EDWIN HOPKINS | special |
| 07/13/2026 | Fire-Resistant Penetrations and Joints | EDWIN HOPKINS | special |
| 07/13/2026 | HVAC-R and service water piping design and insulation | EDWIN HOPKINS | energy_progress |
| 07/13/2026 | Maintenance information | EDWIN HOPKINS | energy_progress |
| 07/13/2026 | Energy Code Compliance Inspections | EDWIN HOPKINS | progress |
| 07/13/2026 | Sprinkler Systems | EDWIN HOPKINS | special |
| 04/24/2026 | Energy Code Compliance Inspections | EDWIN HOPKINS | progress |
| 04/24/2026 | Fire-Resistant Penetrations and Joints | EDWIN HOPKINS | special |
| 04/24/2026 | Maintenance information | EDWIN HOPKINS | energy_progress |
| 04/24/2026 | HVAC-R and service water heating system controls | EDWIN HOPKINS | energy_progress |
| 04/24/2026 | HVAC-R and service water heating equipment | EDWIN HOPKINS | energy_progress |
| 04/24/2026 | Shutoff dampers | EDWIN HOPKINS | energy_progress |
| 04/24/2026 | HVAC-R and service water piping design and insulation | EDWIN HOPKINS | energy_progress |
| 04/24/2026 | Final | EDWIN HOPKINS | progress |
| 04/24/2026 | Mechanical Systems | EDWIN HOPKINS | special |
| 04/02/2026 | HVAC-R and service water heating system controls | EDWIN HOPKINS | energy_progress |
| 04/02/2026 | Mechanical Systems | EDWIN HOPKINS | special |
| 04/02/2026 | Energy Code Compliance Inspections | EDWIN HOPKINS | progress |
| 04/02/2026 | Final | EDWIN HOPKINS | progress |