| Owner | Filings | Most Recent |
|---|---|---|
| DEAN ST REALTY | 54 | 07/08/2026 |
| OWNER'S REP | 7 | 03/22/2026 |
| YATZIV | 5 | 03/22/2026 |
| MMM VENTURES GROUP LLC C/ | 1 | 03/22/2026 |
| HOUSING PRESERVATION DEVELOPME | 4 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 08/15/2022 | $426K | — | MMM VENTURES GROUP LLC → 1148 REALTY LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| ASHER ARCHITECT | 10 | 11/01/2024 |
| AUTOMATED DESIGN ENGINEERING, PLLC | 3 | 09/14/2023 |
| FL&M ENGINEERING DESIGN &INSPECTION | 1 | 05/25/2023 |
| WALTER HOLLIEN ARCHITECT | 1 | 06/02/2022 |
| STRUCTURAL ENGINEERING TECHNOLOGIES | 1 | 05/26/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| ADVANCED BUILDERS SERVICES | 10 | 03/21/2026 |
| ELLIPSES DESIGN | 4 | 03/21/2026 |
| GREEN STUDIO | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| YATZIV CORP | General Contractor | 25 | 07/08/2026 |
| GWT ENTERPRISES INC | General Contractor | 6 | 03/21/2026 |
| BRUCHE MECHANICAL NY LLC | Fire Protection | 1 | 07/08/2026 |
| PLBG P & H INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 11 | 11/01/2024 |
| AUTOMATED DESIGN CONSULTA | 895 | 1 | 09/14/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Support of Excavation | Signed-off | YATZIV CORP | 06/21/2024 |
| DOB NOW | Mechanical Systems | Signed-off | YATZIV CORP | 09/15/2023 |
| DOB NOW | Construction Fence | Signed-off | YATZIV CORP | 08/31/2023 |
| DOB NOW | General Construction | Permit Issued | YATZIV CORP | 08/31/2023 |
| DOB NOW | Sprinklers | Signed-off | BRUCHE MECHANICAL NY LLC | 07/12/2023 |
| DOB NOW | General Construction | Permit Issued | YATZIV CORP | 07/12/2023 |
| DOB NOW | Plumbing | Signed-off | PLBG P & H INC | 07/11/2023 |
| DOB NOW | Construction Fence | Signed-off | YATZIV CORP | 06/30/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | GWT ENTERPRISES INC | 05/25/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | GWT ENTERPRISES INC | 05/25/2023 |
| DOB NOW | General Construction | Permit Issued | YATZIV CORP | 05/22/2023 |
| DOB NOW | Foundation | Signed-off | YATZIV CORP | 12/29/2022 |
| DOB NOW | General Construction | Permit Issued | YATZIV CORP | 11/09/2022 |
| DOB NOW | Earth Work | Signed-off | YATZIV CORP | 06/14/2022 |
| DOB NOW | Construction Fence | Signed-off | YATZIV CORP | 06/14/2022 |
| BIS | — | ISSUED | GATEWAY DEMO/CIVIL CORP | 06/19/2012 |
| BIS | EQ | ISSUED | GATEWAY DEMO/CIVIL CORP | 06/18/2012 |
| BIS | EQ | ISSUED | CHOHAN CONST. INC | 10/20/1998 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 11/01/2024 | Signed-off | YATZIV CORP | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Mitsubishi Electric MXZ-2C24NAHZ 18,000 BTU · Heat Pump Outdoor ×6 MUZ-FS12NAH 12,000 BTU · Heat Pump Outdoor ×3 King LPW1227T 5,115 BTU · Electric Heater ×3 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/01/2024 | Signed-off | PLBG P & H INC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/01/2024 | Signed-off | BRUCHE MECHANICAL NY LLC | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/13/2023 | Complete | SHTRAL ELECT'L CONT'G COR | General Wiring |
| 06/07/2023 | Complete | SHTRAL ELECT'L CONT'G COR | — |
| 05/25/2023 | Complete | SOLAS ELECTRICAL CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/01/2024 | Signed-off | YATZIV CORP | 1 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/01/2024 | Signed-off | YATZIV CORP | Earthwork |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/28/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/27/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/30/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/19/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/17/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/29/2024 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 03/29/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 09/21/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 08/25/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 08/25/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/06/2024 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 11/06/2024 | Maintenance information | FAHAD FATEH | energy_progress |
| 11/06/2024 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 11/06/2024 | HVAC-R and service water heating equipment | FAHAD FATEH | energy_progress |
| 11/06/2024 | Metering | FAHAD FATEH | energy_progress |
| 11/06/2024 | Exterior lighting power | FAHAD FATEH | energy_progress |
| 11/06/2024 | Subgrade Inspections | FAHAD FATEH | special |
| 11/06/2024 | Concrete - Cast-In-Place | FAHAD FATEH | special |
| 11/06/2024 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | FAHAD FATEH | special |
| 11/06/2024 | Sprayed fire-resistant materials | FAHAD FATEH | special |
| 11/06/2024 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 11/06/2024 | Masonry | FAHAD FATEH | special |
| 11/06/2024 | Seismic Isolation Systems | FAHAD FATEH | special |
| 11/06/2024 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 11/06/2024 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 11/06/2024 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 11/06/2024 | HVAC-R and service water piping design and insulation | FAHAD FATEH | energy_progress |
| 11/06/2024 | Lighting controls | FAHAD FATEH | energy_progress |
| 11/06/2024 | Air barrier — testing | FAHAD FATEH | energy_progress |
| 11/06/2024 | HVAC-R and service water heating system controls | FAHAD FATEH | energy_progress |
| 11/06/2024 | Lighting in dwelling units | FAHAD FATEH | energy_progress |
| 11/06/2024 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 11/06/2024 | Fenestration areas | FAHAD FATEH | energy_progress |
| 11/06/2024 | Interior lighting power | FAHAD FATEH | energy_progress |
| 11/06/2024 | Protection of exposed foundation insulation | FAHAD FATEH | energy_progress |