1920Year Built
1Stories
B1Building Class
R5Zoning
1,507 sfGross Floor Area
2Units
Two family brick · 2,500 sf lot · 0.6 FAR built · Flood zone X
Locations of Work
ArchitectureElectrical
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofRoof mounted solar energy system installation1p · 1 filing · 7 docs
Floor 1Unit PH13p · 1 filing · 6 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
03/30/2021$640K—Private party → Private party$425/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Green River Environmental Engineering105/27/2025
Chanda Engineering Consultant111/10/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NY State Solar203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Padma ContractingGeneral Contractor107/08/2026
NYSSspecialty_contractor203/21/2026
NYSSspecialty_contractor103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Green River Environmental7841105/27/2025
Chanda Engineering Consultant6842111/10/2024
Building Lifecycle
07/24/2025
Signed off — Alteration
INSTALLATION OF PHOTOVOLTAIC SOLAR ARRAY ON EXISTING ROOF SYSTEM AS PER PLANS
X01231671-I1
06/06/2025
Signed off — Alteration
PROPOSED ALTERATION AT FRONT ENTRANCE STAIR STOOP AREA IN 1ST FLOOR AS REQUEST FOR CORRECTIVE ACTION (RCA #2401213) FOR EXISTING TWO-FAMILY RESIDENTIAL BUILDING. NO CHANGE IN USE, EGRESS & OCCUPANCY WITH THIS APPLICATION.
X01137232-I1
05/29/2025
Permit issued — Solar
X01231671-I1-SL
05/27/2025
Filed — Alteration
INSTALLATION OF PHOTOVOLTAIC SOLAR ARRAY ON EXISTING ROOF SYSTEM AS PER PLANS
X01231671-I1
05/27/2025
Special inspection requirement — Air barrier - visual inspection
ROBERT MASONE
14 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offNYSS05/29/2025
DOB NOWGeneral ConstructionSigned-offPadma Contracting01/28/2025
1 project · most recent 07/09/2025
FiledStatusContractorScope
07/09/2025CompleteNY Solar Electrical—
▾Special Inspection Requirements (DOB NOW) — 8
DateRequirementInspectorRole
05/27/2025Air barrier - visual inspectionROBERT MASONEenergy_progress
05/27/2025Structural Stability – Alterations of existing buildingsROBERT MASONEspecial
05/27/2025Energy Code Compliance InspectionsROBERT MASONEprogress
05/27/2025FinalROBERT MASONEprogress
05/27/2025Fire-Resistant Penetrations and JointsROBERT MASONEspecial
11/10/2024FinalKARTIK CHANDAprogress
11/10/2024Fire-Resistance Rated ConstructionKARTIK CHANDAprogress
11/10/2024Fire-Resistant Penetrations and JointsKARTIK CHANDAspecial
12 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account