← Back
Two family frame
115-35 144 STREET
QUEENS · BIN 4259752
💬 Discuss this project
1955Year Built
2Stories
B2Building Class
R3AZoning
2,886 sfGross Floor Area
2Units
Two family frame · 4,000 sf lot · 0.72 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
07/09/2014$425K—— → —$147/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PARKER AND WEST ENGINEERING, PLLC109/25/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SUNRUN103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUNRUN INSTALLATION SVCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PARKER AND WEST ENGINEERI5272109/25/2025
Building Lifecycle
All (8)Filed (1)Permit Issued (1)Signed Off (1)Special Inspection (5)
05/28/2026
Signed off — Alteration
Q01292672-I1
10/02/2025
Permit issued — Solar
Q01292672-I1-SL
09/25/2025
Filed — Alteration
Q01292672-I1
09/24/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walid Abdulla
09/24/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Walid Abdulla
09/24/2025
Special inspection requirement — Energy Code Compliance Inspections
Walid Abdulla
09/24/2025
Special inspection requirement — Final
Walid Abdulla
09/24/2025
Special inspection requirement — Air barrier - visual inspection
Walid Abdulla
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSUNRUN INSTALLATION SVC10/02/2025
2 projects · most recent 10/29/2025
General Wiring
FiledStatusContractorScope
10/29/2025CompleteFORSURE ELECTRIC NY INCGeneral Wiring
09/25/2025CompleteSUNRUN SOLAR ELECTL CORP—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
09/24/2025Fire-Resistant Penetrations and JointsWalid Abdullaspecial
09/24/2025Structural Stability – Alterations of existing buildingsWalid Abdullaspecial
09/24/2025Energy Code Compliance InspectionsWalid Abdullaprogress
09/24/2025FinalWalid Abdullaprogress
09/24/2025Air barrier - visual inspectionWalid Abdullaenergy_progress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/18/2026Q01292672-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
08/25/2026Q01292672-I1Open ↗
08/25/2026Q01292672-I1Open ↗
08/25/2026Q01292672-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/25/2026Q01292672-I1Open ↗
08/25/2026Q01292672-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/18/2026Q01292672-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/18/2026Q01292672-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01292672-I1Open ↗