← Back
Two stories - detached, small or mid-size
115-46 173 STREET
QUEENS · St. Albans · BIN 4268762
💬 Discuss this project
1920Year Built
2Stories
A1Building Class
R3XZoning
1,405 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 3,600 sf lot · 0.39 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbing
Floor 15p · 1 filing · 20 docs
Cellar7p · 1 filing · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
03/26/2024$600K—Private party → Private party$427/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
HUGH CHRYSLER ENGINEERING CO LLC504/03/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
HUGH CHRYSLER ENGINEERING1003/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
HUGH CHRYSLER ENGINEERINGGeneral Contractor303/21/2026
QBK PLUMBING & HTNG INCPlumbing207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HUGH CHRYSLER ENGINEERING4251504/03/2025
Building Lifecycle
All (40)Filed (5)Permit Issued (3)Signed Off (3)Inspection (5)Special Inspection (24)
09/03/2025
Signed off — Alteration
LEGALIZE 3-PIECE BATHROOM IN CELLAR, (2) PIECE BATHROOM ON 1ST FLOOR AND PLUMBING FIXTURES AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY IS INVOLVED UNDER THIS APPLICATION.
Q01118373-S3
09/03/2025
Signed off — Alteration
LEGALIZE 3-PIECE BATHROOM IN CELLAR, (2) PIECE BATHROOM ON 1ST FLOOR AND PLUMBING FIXTURES AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY IS INVOLVED UNDER THIS APPLICATION.
Q01118373-S1
09/03/2025
Signed off — Alteration
LEGALIZE 3-PIECE BATHROOM IN CELLAR, (2) PIECE BATHROOM ON 1ST FLOOR AND PLUMBING FIXTURES AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY IS INVOLVED UNDER THIS APPLICATION.
Q01118373-I1
07/07/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
06/03/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/20/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
04/25/2025
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
04/14/2025
Permit issued — Plumbing
Q01118373-S3-PL
04/03/2025
Filed — Alteration
LEGALIZE 3-PIECE BATHROOM IN CELLAR, (2) PIECE BATHROOM ON 1ST FLOOR AND PLUMBING FIXTURES AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY IS INVOLVED UNDER THIS APPLICATION.
Q01118373-S3
04/03/2025
Permit issued — Mechanical Systems
Q01118373-I1-GC-CX
03/28/2025
Special inspection requirement — Energy Code Compliance Inspections
HUGH CHRYSLER
03/28/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
HUGH CHRYSLER
03/28/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
HUGH CHRYSLER
03/28/2025
Special inspection requirement — HVAC-R and service water heating equipment
HUGH CHRYSLER
03/28/2025
Special inspection requirement — HVAC-R and service water heating system controls
HUGH CHRYSLER
03/18/2025
Filed — Alteration
LEGALIZE 3-PIECE BATHROOM IN CELLAR, (2) PIECE BATHROOM ON 1ST FLOOR AND PLUMBING FIXTURES AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY IS INVOLVED UNDER THIS APPLICATION.
Q01118373-S2
03/14/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
HUGH CHRYSLER
03/14/2025
Special inspection requirement — HVAC-R and service water heating equipment
HUGH CHRYSLER
03/14/2025
Special inspection requirement — HVAC-R and service water heating system controls
HUGH CHRYSLER
03/14/2025
Special inspection requirement — Energy Code Compliance Inspections
HUGH CHRYSLER
03/14/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
HUGH CHRYSLER
03/12/2025
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
01/08/2025
Filed — Alteration
LEGALIZE 3-PIECE BATHROOM IN CELLAR, (2) PIECE BATHROOM ON 1ST FLOOR AND PLUMBING FIXTURES AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY IS INVOLVED UNDER THIS APPLICATION.
Q01118373-P1
01/08/2025
Special inspection requirement — HVAC-R and service water heating system controls
HUGH CHRYSLER
01/08/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
HUGH CHRYSLER
01/08/2025
Special inspection requirement — Energy Code Compliance Inspections
HUGH CHRYSLER
01/08/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
HUGH CHRYSLER
01/08/2025
Special inspection requirement — HVAC-R and service water heating equipment
HUGH CHRYSLER
12/20/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
HUGH CHRYSLER
12/20/2024
Special inspection requirement — HVAC-R and service water heating system controls
HUGH CHRYSLER
12/20/2024
Special inspection requirement — HVAC-R and service water heating equipment
HUGH CHRYSLER
12/20/2024
Special inspection requirement — Energy Code Compliance Inspections
HUGH CHRYSLER
12/20/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
HUGH CHRYSLER
10/18/2024
Permit issued — Plumbing
Q01118373-S1-PL
10/15/2024
Filed — Alteration
LEGALIZE 3-PIECE BATHROOM IN CELLAR, (2) PIECE BATHROOM ON 1ST FLOOR AND PLUMBING FIXTURES AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY IS INVOLVED UNDER THIS APPLICATION.
Q01118373-S1
10/02/2024
Filed — Alteration
LEGALIZE 3-PIECE BATHROOM IN CELLAR, (2) PIECE BATHROOM ON 1ST FLOOR AND PLUMBING FIXTURES AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY IS INVOLVED UNDER THIS APPLICATION.
Q01118373-I1
09/27/2024
Special inspection requirement — Mechanical Systems
HUGH CHRYSLER
09/27/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
HUGH CHRYSLER
09/27/2024
Special inspection requirement — Final
HUGH CHRYSLER
09/27/2024
Special inspection requirement — Energy Code Compliance Inspections
HUGH CHRYSLER
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offSILVER STAR PLBG & HTG IN04/14/2025
DOB NOWMechanical SystemsSigned-offHUGH CHRYSLER ENGINEERING04/03/2025
DOB NOWPlumbingSigned-offSILVER STAR PLBG & HTG IN10/18/2024
BISOTISSUEDVENTURE HOME SOLAR LLC11/20/2018
1 project · most recent 04/03/2025
Gas Water/Sanitary
FiledStatusContractorScope
04/03/2025Signed-offQBK PLUMBING & HTNG INCGas, Water/Sanitary
2 projects · most recent 03/27/2019
FiledStatusContractorScope
03/27/2019CompleteVENTURE HOME SOLAR LLC—
03/27/2019CompleteVENTURE HOME SOLAR LLC1 meters, 1 new_meters
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
07/07/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/03/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/20/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
04/25/2025Fail-Final PL - Up to 3 Requested FloorsFailView ↗
03/12/2025Fail-Final PL - Up to 3 Requested FloorsFailView ↗
▾Special Inspection Requirements (DOB NOW) — 24
DateRequirementInspectorRole
03/28/2025Energy Code Compliance InspectionsHUGH CHRYSLERprogress
03/28/2025HVAC-R and service water piping design and insulationHUGH CHRYSLERenergy_progress
03/28/2025Fire-Resistant Penetrations and JointsHUGH CHRYSLERspecial
03/28/2025HVAC-R and service water heating equipmentHUGH CHRYSLERenergy_progress
03/28/2025HVAC-R and service water heating system controlsHUGH CHRYSLERenergy_progress
03/14/2025HVAC-R and service water piping design and insulationHUGH CHRYSLERenergy_progress
03/14/2025HVAC-R and service water heating equipmentHUGH CHRYSLERenergy_progress
03/14/2025HVAC-R and service water heating system controlsHUGH CHRYSLERenergy_progress
03/14/2025Energy Code Compliance InspectionsHUGH CHRYSLERprogress
03/14/2025Fire-Resistant Penetrations and JointsHUGH CHRYSLERspecial
01/08/2025HVAC-R and service water heating system controlsHUGH CHRYSLERenergy_progress
01/08/2025Fire-Resistant Penetrations and JointsHUGH CHRYSLERspecial
01/08/2025Energy Code Compliance InspectionsHUGH CHRYSLERprogress
01/08/2025HVAC-R and service water piping design and insulationHUGH CHRYSLERenergy_progress
01/08/2025HVAC-R and service water heating equipmentHUGH CHRYSLERenergy_progress
12/20/2024HVAC-R and service water piping design and insulationHUGH CHRYSLERenergy_progress
12/20/2024HVAC-R and service water heating system controlsHUGH CHRYSLERenergy_progress
12/20/2024HVAC-R and service water heating equipmentHUGH CHRYSLERenergy_progress
12/20/2024Energy Code Compliance InspectionsHUGH CHRYSLERprogress
12/20/2024Fire-Resistant Penetrations and JointsHUGH CHRYSLERspecial
09/27/2024Mechanical SystemsHUGH CHRYSLERspecial
09/27/2024Fire-Resistant Penetrations and JointsHUGH CHRYSLERspecial
09/27/2024FinalHUGH CHRYSLERprogress
09/27/2024Energy Code Compliance InspectionsHUGH CHRYSLERprogress
▾Documents — 64 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/21/2026Q01118373-S2Request digital key ↗
08/21/2026Q01118373-P1Request digital key ↗
08/21/2026Q01118373-S1Request digital key ↗
Showing 3 of 5 on file for this type
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
11/19/2018440522819Open ↗
▸BISWORK PERMIT APPLICATION1
11/19/2018440522819Open ↗
▸Seals & Professional Certifications32
▸DOB NOWProgress Inspector Seal & Signature18
09/26/2026Q01118373-S1Open ↗
09/26/2026Q01118373-S1Open ↗
09/26/2026Q01118373-S1Open ↗
Showing 3 of 18 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
09/26/2026Q01118373-S1Open ↗
08/30/2026Q01118373-I1Open ↗
08/30/2026Q01118373-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/21/2026Q01118373-S1Open ↗
08/13/2026Q01118373-I1Open ↗
08/13/2026Q01118373-P1Open ↗
Showing 3 of 5 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
11/19/2018440522819Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
11/19/2018440522819Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
11/19/2018440522819Open ↗
▸Safety & Tenant Protection1
▸BISTENANT PROTECTION PLAN AND NOTES1
11/19/2018440522819Open ↗
▸Environmental & Asbestos6
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
08/21/2026Q01118373-S1Open ↗
08/13/2026Q01118373-S3Open ↗
08/13/2026Q01118373-S2Open ↗
Showing 3 of 5 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
11/19/2018440522819Open ↗
▸Energy Compliance7
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
05/17/2019440522819Open ↗
11/19/2018440522819Open ↗
11/19/2018440522819Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
11/19/2018440522819Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
05/17/2019440522819Open ↗
▸BISSOLAR TAX ABATEMENT APPLICATION1
05/17/2019440522819Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
11/19/2018440522819Open ↗
▸Inspections & Test Reports5
▸BISTECHNICAL REPORT: RESPONSIBILITY4
05/17/2019440522819Open ↗
05/17/2019440522819Open ↗
11/19/2018440522819Open ↗
Showing 3 of 4 on file for this type
▸BISDIR-14 ID OF RESPONSIBILITY (TR1)1
11/19/2018440522819Open ↗
▸Approvals, Objections & Sign-offs2
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
05/17/2019440522819Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
05/17/2019440522819Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
05/17/2019440522819Open ↗
11/19/2018440522819Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
11/19/2018440522819Open ↗
▸Other Documents1
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
11/19/2018440522819Open ↗