1925Year Built
2Stories
B2Building Class
R3AZoning
2,064 sfGross Floor Area
2Units
Two family frame · 3,000 sf lot · 0.69 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
1 job · most recent 12/14/2023
FiledStatusContractorScope
12/14/2023CompleteMAK ELECTRICAL CONTR CORP2 meters
Building Lifecycle
All (12)Filed (2)Permit Issued (1)Signed Off (1)Objection (4)Special Inspection (4)
03/13/2026
Signed off — Alteration
ROOFTOP SOLAR PANEL INSTALLATION
Q00989526-I1
11/11/2025
Filed — Alteration
ROOFTOP SOLAR PANEL INSTALLATION
Q00989526-P1
02/09/2024
Permit issued — Solar
Q00989526-I1-SL
01/31/2024
Objection resolved — Addressed
01/31/2024
Objection resolved — Addressed
01/23/2024
Objection raised — Other
01/23/2024
Objection raised — Other
01/18/2024
Filed — Alteration
ROOFTOP SOLAR PANEL INSTALLATION
Q00989526-I1
01/12/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
VYACHESLAV NECHAYEV
01/12/2024
Special inspection requirement — Energy Code Compliance Inspections
VYACHESLAV NECHAYEV
01/12/2024
Special inspection requirement — Final
VYACHESLAV NECHAYEV
01/12/2024
Special inspection requirement — Air barrier - visual inspection
VYACHESLAV NECHAYEV
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ETRECTE LLC211/11/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
PATRIOT ENERGY SOLUTIONS CORP403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MAK ELECTRICAL CONTR CORPElectrical103/22/2026
PATRIOT ENERGY SOL COGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ETRECTE LLC8116101/18/2024
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offPATRIOT ENERGY SOL CO02/09/2024
▾Special Inspection Requirements (DOB NOW) — 4
DateRequirementInspectorRole
01/12/2024Fire-Resistant Penetrations and JointsVYACHESLAV NECHAYEVspecial
01/12/2024Energy Code Compliance InspectionsVYACHESLAV NECHAYEVprogress
01/12/2024FinalVYACHESLAV NECHAYEVprogress
01/12/2024Air barrier - visual inspectionVYACHESLAV NECHAYEVenergy_progress
▾Documents — 8 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/23/2026Q00989526-I1Request digital key ↗
▸Seals & Professional Certifications5
▸DOB NOWProgress Inspector Seal & Signature3
08/26/2026Q00989526-I1Open ↗
08/26/2026Q00989526-I1Open ↗
08/26/2026Q00989526-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026Q00989526-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/26/2026Q00989526-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026Q00989526-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q00989526-I1Open ↗