| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/02/2022 | Complete | V-MAR ELECTRIC LTD. | General Wiring |
| 11/02/2021 | Complete | ILLUMINOUS ELECTRIC CORP. | — |
| 08/27/2019 | Complete | DEFALCO ASSOCIATES, LLC./ | General Wiring |
| Owner | Filings | Most Recent |
|---|---|---|
| TRI BOROUGH SCAFFOLDING | 7 | 07/08/2026 |
| PMG CONSTRUCTION GROUP LL | 6 | 03/22/2026 |
| TYE VOREA CONSTRUCTION CO | 2 | 03/22/2026 |
| CALIENTE CAR PARK LLC | 1 | 03/22/2026 |
| PMG LEROY STREET DEVELOPMENT | 2 | 03/21/2026 |
| PROPERTY MARKETS GROUP | 17 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/03/2021 | $10.0M | — | PMG LEROY STREET DEVELOPMENT LLC → SHINOBI 115L LLC | $2,905/sf building |
| 05/05/2014 | $19.0M | — | KMG PMA LEROY, LLC → PMG LEROY STREET LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| LEVIN ENGINEERING PLLC | 1 | 11/18/2021 |
| BAILEYS ENGINEERING PC | 1 | 12/26/2017 |
| Representative | Filings | Most Recent |
|---|---|---|
| LEVIN ENGINEERING PLLC | 2 | 03/21/2026 |
| AE DESIGN SOLUTION | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| TRI BOROUGH SCAFFOLDING | General Contractor | 5 | 07/08/2026 |
| DONATO PLUMBING, INC | Plumbing | 2 | 03/22/2026 |
| MJM ASSOCIATES CONSTR LLC | General Contractor | 1 | 03/22/2026 |
| DMITRY LEVIN | Electrical | 1 | 03/21/2026 |
| MMI PLUMBING & HEATING INC. | Plumbing | 1 | 07/08/2026 |
| MMI PLUMBING HEATING IN | General Contractor | 1 | 03/22/2026 |
| THOMAS J ZOLI | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AA BUILDING & INSPECTION | 1519 | 1 | 11/18/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Boiler Equipment | Signed-off | MICHAEL ITSKOVICH | 03/09/2022 |
| DOB NOW | Supported Scaffold | Signed-off | TRI BOROUGH SCAFFOLDING | 11/25/2019 |
| DOB NOW | Supported Scaffold | Signed-off | TRI BOROUGH SCAFFOLDING | 11/26/2018 |
| DOB NOW | Supported Scaffold | Signed-off | TRI BOROUGH SCAFFOLDING | 05/14/2018 |
| DOB NOW | Supported Scaffold | Signed-off | TRI BOROUGH SCAFFOLDING | 03/30/2018 |
| DOB NOW | Supported Scaffold | Signed-off | TRI BOROUGH SCAFFOLDING | 12/27/2017 |
| BIS | SP | ISSUED | M&D FIRE SPRINKLER INC | 12/10/2021 |
| BIS | EQ | ISSUED | DYNAMIC INSTALLATION CORP. | 10/19/2021 |
| BIS | PL | ISSUED | MMI PLUMBING & HEATING INC. | 09/27/2021 |
| BIS | — | ISSUED | MJM ASSOCIATES CONSTR LLC | 09/21/2021 |
| BIS | — | ISSUED | MJM ASSOCIATES CONSTR LLC | 09/21/2021 |
| BIS | EQ | ISSUED | MJM ASSOCIATES CONSTR LLC | 09/20/2021 |
| BIS | SP | ISSUED | R & G MECHANICAL CORP | 03/11/2021 |
| BIS | PL | ISSUED | R&A HEATING & CONTRG CO.I | 03/01/2021 |
| BIS | — | ISSUED | THE VOREA CONSTRUCTION CO | 09/17/2020 |
| BIS | — | ISSUED | THE VOREA CONSTRUCTION CO | 09/17/2020 |
| BIS | — | ISSUED | THE VOREA CONSTRUCTION CO | 06/05/2020 |
| BIS | — | ISSUED | THE VOREA CONSTRUCTION CO | 06/05/2020 |
| BIS | — | ISSUED | THE VOREA CONSTRUCTION CO | 03/04/2020 |
| BIS | — | ISSUED | THE VOREA CONSTRUCTION CO | 03/04/2020 |
| BIS | — | ISSUED | THE VOREA CONSTRUCTION CO | 10/01/2019 |
| BIS | — | ISSUED | THE VOREA CONSTRUCTION CO | 10/01/2019 |
| BIS | — | ISSUED | THE VOREA CONSTRUCTION CO | 10/01/2019 |
| BIS | PL | ISSUED | PRIME PIPING & HEATING IN | 06/03/2019 |
| BIS | SP | ISSUED | PRIME PIPING & HEATING IN | 06/03/2019 |
| BIS | — | ISSUED | THE VOREA CONSTRUCTION CO | 04/15/2019 |
| BIS | — | ISSUED | THE VOREA CONSTRUCTION CO | 04/15/2019 |
| BIS | PL | ISSUED | COPPER SERVICES, LLC | 01/04/2019 |
| BIS | — | ISSUED | THE VOREA CONSTRUCTION CO | 10/19/2018 |
| BIS | EQ | ISSUED | DYNAMIC INSTALLATION CORP. | 09/11/2018 |
| BIS | SP | ISSUED | COPPER SERVICES LLC | 08/13/2018 |
| BIS | — | ISSUED | THE VOREA CONSTRUCTION CO | 07/10/2018 |
| BIS | EQ | ISSUED | THE VOREA CONSTRUCTION CO | 07/05/2018 |
| BIS | — | ISSUED | THE VOREA CONSTRUCTION CO | 07/02/2018 |
| BIS | — | ISSUED | THE VOREA CONSTRUCTION CO | 07/02/2018 |
| BIS | — | ISSUED | PMG CONSTRUCTION GROUP LL | 03/29/2018 |
| BIS | PL | ISSUED | COPPER SERVICES, LLC | 01/24/2018 |
| BIS | EQ | ISSUED | PMG CONSTRUCTION GROUP LL | 10/24/2017 |
| BIS | EQ | ISSUED | DYNAMIC INSTALLATION CORP. | 09/07/2017 |
| BIS | SP | ISSUED | COPPER SERVICES LLC | 09/06/2017 |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/28/2022 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |