| Owner | Filings | Most Recent |
|---|---|---|
| ISRA HOLDINGS | 23 | 07/08/2026 |
| OWNERS REP | 7 | 03/22/2026 |
| CORE SCAFFOLD SYSTEMS | 1 | 03/22/2026 |
| 115 WEST 190 ST LLC | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| AUTOMATED DESIGN ENGINEERING, PLLC | 3 | 06/21/2023 |
| PAUL PERDEK, PROF. ENG. PLLC | 4 | 03/14/2023 |
| ELEVATED ENGINEERING NYC | 2 | 06/13/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| BMG GROUP USA | 4 | 03/21/2026 |
| AE DESIGN SOLUTION | 8 | 03/21/2026 |
| NYC DESIGN FILE | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PRECISION BUILDERS USA | General Contractor | 19 | 07/08/2026 |
| MW CONSTRUCTION INC | General Contractor | 6 | 03/21/2026 |
| PRECISION BUILD USA INC | General Contractor | 6 | 07/08/2026 |
| CORE SCAFFOLD SYSTEMS INC. | General Contractor | 6 | 03/21/2026 |
| INFINITI ESC PLUMBING COR | Plumbing | 1 | 07/08/2026 |
| TFK ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| VILLAGE P & H NY INC | Fire Protection | 1 | 07/08/2026 |
| SOLAS ELECTRICAL CORP | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AUTOMATED DESIGN CONSULTA | 895 | 1 | 06/21/2023 |
| SHAHRISH SHUVO ENGINEERIN | 8524 | 2 | 09/29/2022 |
| ENGINEERING CONSULTING SE | 2050 | 2 | 06/13/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | PRECISION BUILD USA INC | 07/07/2023 |
| DOB NOW | Support of Excavation | Signed-off | PRECISION BUILDERS USA | 05/26/2023 |
| DOB NOW | General Construction | Permit Issued | PRECISION BUILD USA INC | 05/12/2023 |
| DOB NOW | Construction Fence | Signed-off | PRECISION BUILD USA INC | 05/12/2023 |
| DOB NOW | Sprinklers | Signed-off | VILLAGE P & H NY INC | 05/03/2023 |
| DOB NOW | Curb Cut | Signed-off | PRECISION BUILD USA INC | 04/20/2023 |
| DOB NOW | General Construction | Permit Issued | MW CONSTRUCTION INC | 03/24/2023 |
| DOB NOW | Construction Fence | Signed-off | MW CONSTRUCTION INC | 03/23/2023 |
| DOB NOW | Structural | Signed-off | PRECISION BUILDERS USA | 01/24/2023 |
| DOB NOW | General Construction | Permit Issued | PRECISION BUILDERS USA | 01/23/2023 |
| DOB NOW | General Construction | Permit Issued | PRECISION BUILDERS USA | 11/22/2022 |
| DOB NOW | Supported Scaffold | Signed-off | CORE SCAFFOLD SYSTEMS INC | 11/20/2022 |
| DOB NOW | Structural | Signed-off | PRECISION BUILDERS USA | 10/25/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | CORE SCAFFOLD SYSTEMS INC | 10/21/2022 |
| DOB NOW | Plumbing | Signed-off | INFINITI ESC PLUMBING COR | 10/05/2022 |
| DOB NOW | Foundation | Signed-off | PRECISION BUILDERS USA | 08/09/2022 |
| DOB NOW | Foundation | Signed-off | PRECISION BUILDERS USA | 07/14/2022 |
| DOB NOW | Foundation | Signed-off | PRECISION BUILDERS USA | 06/03/2022 |
| DOB NOW | Construction Fence | Signed-off | PRECISION BUILDERS USA | 03/25/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/09/2024 | Complete | TFK ELECTRIC CORP | General Wiring |
| 10/02/2024 | Permit Issued | TFK ELECTRIC CORP | 40 meters, 40 new_meters |
| 11/15/2022 | Complete | SOLAS ELECTRICAL CORP | — |
| 11/03/2022 | Complete | TFK ELECTRIC CORP | — |
| 10/28/2022 | Complete | SOLAS ELECTRICAL CORP | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/18/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/29/2023 | Certified Sprinkler-Dry Pipe Valve (SP)-Dry Pipe Valve Test | Certified | View ↗ |
| 12/06/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/28/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/15/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 11/13/2023 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 10/24/2023 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 03/31/2023 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 03/31/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/07/2022 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 10/12/2022 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 10/12/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/21/2023 | Sprinkler Systems | Gregory Mortman | special |
| 06/21/2023 | Energy Code Compliance Inspections | Gregory Mortman | progress |
| 06/21/2023 | HVAC-R and service water piping design and insulation | Gregory Mortman | energy_progress |
| 06/21/2023 | Maintenance information | Gregory Mortman | energy_progress |
| 06/21/2023 | HVAC-R and service water heating system controls | Gregory Mortman | energy_progress |
| 06/21/2023 | HVAC-R and service water heating equipment | Gregory Mortman | energy_progress |
| 09/29/2022 | HVAC-R and service water piping design and insulation | Shahrish Shuvo | energy_progress |
| 09/29/2022 | Mechanical Systems | Shahrish Shuvo | special |
| 09/29/2022 | Final | Shahrish Shuvo | progress |
| 09/29/2022 | Energy Code Compliance Inspections | Shahrish Shuvo | progress |
| 09/29/2022 | Maintenance information | Shahrish Shuvo | energy_progress |
| 09/29/2022 | HVAC-R and service water heating equipment | Shahrish Shuvo | energy_progress |
| 09/29/2022 | Shutoff dampers | Shahrish Shuvo | energy_progress |
| 09/29/2022 | Ventilation and air distribution system | Shahrish Shuvo | energy_progress |
| 09/29/2022 | HVAC-R and service water heating system controls | Shahrish Shuvo | energy_progress |
| 06/14/2022 | Final | JAMES SCHAEFER | progress |
| 06/14/2022 | Subsurface Investigations (Borings/Test Pits) | Rui Guo | special |
| 06/14/2022 | Subgrade Inspections | PAUL MARINO | special |
| 06/14/2022 | Concrete - Cast-In-Place | PAUL MARINO | special |
| 06/14/2022 | Footing and Foundation | PAUL MARINO | progress |
| 06/10/2022 | Final | JAMES SCHAEFER | progress |
| 06/10/2022 | Concrete - Cast-In-Place | PAUL MARINO | special |
| 06/10/2022 | Subgrade Inspections | PAUL MARINO | special |
| 06/10/2022 | Subsurface Investigations (Borings/Test Pits) | Rui Guo | special |
| 06/10/2022 | Footing and Foundation | PAUL MARINO | progress |