| Owner | Filings | Most Recent |
|---|---|---|
| PLATINUM SERVICES NY | 2 | 08/30/2026 |
| 1151 45 STREET | 19 | 08/29/2026 |
| OWNER OF 1151 45 ST | 1 | 03/22/2026 |
| CITYSCAPE BUILDERS | 1 | 03/22/2026 |
| GUARDIAN REALTY & MANAGEMENT | 4 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/23/2024 | $1.4M | — | Private party → 1151 45 STREET LLC | $645/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| CHARLES DAVIDSON | 1 | 08/26/2026 |
| EYAL LEVITT | 2 | 07/21/2026 |
| ARTEM KORSUN | 5 | 07/09/2026 |
| MEY ASSOCIATES | 3 | 06/02/2026 |
| MJE PROFESSIONAL SERVICES | 1 | 05/01/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| ERETZ BUILDERS ASSISTANCE. | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CITYSCAPE BUILDERS LLC | General Contractor | 5 | 07/08/2026 |
| YOEL TAUBER | Electrical | 2 | 03/21/2026 |
| LIGHTFORCE ELECL CONTNG I | Electrical | 1 | 03/22/2026 |
| CROWBAR INDUSTRIES | General Contractor | 1 | 06/28/2026 |
| PLATINUM SERVICES NY LLC | General Contractor | 1 | 08/30/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BIG APPLE GROUP NY A RMA | 9168 | 2 | 02/10/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Full Demolition | Signed-off | CROWBAR INDUSTRIES INC | 06/12/2026 |
| BIS | — | ISSUED | FONTANA CONSTRUCTION CORP. | 04/06/1993 |
| BIS | — | ISSUED | FONTANA CONSTRUCTION CORP. | 04/03/1992 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/01/2025 | Permit Issued | CITYSCAPE BUILDERS LLC | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/29/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 07/29/2026 | Sprinkler Systems | — | special |
| 07/24/2026 | Excavations - Sheeting, Shoring, and Bracing | Murad Saleh | special |
| 07/24/2026 | Subgrade Inspections | Murad Saleh | special |
| 06/02/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 06/02/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | — | special |
| 06/02/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 06/02/2026 | Maintenance information | — | energy_progress |
| 06/02/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 06/02/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 05/15/2026 | Construction Operations Influencing Adjacent Structures | Murad Saleh | special |
| 05/15/2026 | Concrete - Cast-In-Place | Murad Saleh | special |
| 05/15/2026 | Excavations - Sheeting, Shoring, and Bracing | Murad Saleh | special |
| 05/15/2026 | Subgrade Inspections | Murad Saleh | special |
| 05/15/2026 | Underpinning and alternate methods of support of buildings and adjacent property | Murad Saleh | special |
| 05/14/2026 | Subgrade Inspections | Murad Saleh | special |
| 05/11/2026 | Final | Murad Saleh | progress |
| 05/11/2026 | Footing and Foundation | Murad Saleh | progress |
| 04/02/2026 | Interior lighting power | SOORJBALLY HARILALL | energy_progress |
| 04/02/2026 | Fire-Resistance Rated Construction | SOORJBALLY HARILALL | progress |
| 04/02/2026 | Energy Code Compliance Inspections | SOORJBALLY HARILALL | progress |
| 04/02/2026 | Fenestration air leakage | SOORJBALLY HARILALL | energy_progress |
| 04/02/2026 | Air barrier - visual inspection | SOORJBALLY HARILALL | energy_progress |
| 04/02/2026 | Metering | SOORJBALLY HARILALL | energy_progress |
| 04/02/2026 | Exterior lighting power | SOORJBALLY HARILALL | energy_progress |