| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 09/01/2023 | Permit Issued | DYNAMIC DEVELOPMENT AND C | Air Conditioning Systems, Associated Ducts and Piping, Heating and Air Conditioning Systems | Cooling Mitsubishi Electric PUHY-P144TKMU-A 144,000 BTU · Vrf Outdoor ×2 PUHY-P72TKMU-A 72,000 BTU · Vrf Outdoor ×2 Heat / Cool Mitsubishi Electric PEFY-P72NMHSU-E 72,000 BTU · Vrf Indoor ×2 Ducts & Piping Indeeco INDEECO 247,000 BTU · Ductwork ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/28/2025 | — | — | 2 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/28/2025 | Permit Issued | J.HAUSMAN PLUMBING INC | Gas, Plumbing-Sprinkler, Water/Sanitary |
| 09/14/2023 | Signed-off | ALTAIR PLUMBING AND HEATI | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/17/2026 | Complete | R & T ELECTRICAL CORP | — |
| 08/29/2024 | Permit Issued | AURORA ELECL CONTG INC | — |
| 04/22/2024 | Complete | PRINCIPAL ELECTRIC CORP | General Wiring |
| 12/11/2023 | Complete | KRAFT ELECTRIC CORP | General Wiring |
| 09/07/2023 | Permit Issued | ACCURATE ELEC'L CORP. | 165 meters, 1 new_meters |
| 08/10/2022 | Permit Issued | STAR ELEC'L CONTRACTORS C | — |
| 02/22/2022 | Permit Issued | ACCURATE ELEC'L CORP. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/22/2023 | Permit Issued | DYNAMIC DEVELOPMENT AND C | Steel |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/27/2024 | Permit Issued | PRAT ENTERPRISES CORP | Sidewalk Shed |
| Owner | Filings | Most Recent |
|---|---|---|
| DOUGLAS ELLIMAN PROPERTY MANAGEMENT | 22 | 07/08/2026 |
| PRAT ENTERPRISES | 5 | 07/08/2026 |
| CHARLES H GREENTHAL | 4 | 07/08/2026 |
| NATE | 12 | 07/08/2026 |
| PRATT CONSTRUCTION&REST | 1 | 03/22/2026 |
| INSIGNIA MANAGEMENT | 1 | 03/22/2026 |
| TO THE OWNER OF APT 4E & | 1 | 03/22/2026 |
| GOODSTEIN MNGMT CO. | 2 | 03/22/2026 |
| GOODSTEIN MANAGEMENT C | 1 | 03/22/2026 |
| OWNER OF 1156 3 AVE | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| JMV CONSULTING ENGINEERING | 4 | 04/28/2025 |
| RIGID STRUCTURAL DESIGN, LLC | 2 | 08/27/2024 |
| AMR ENGINEERING CONSULTANT, P.C. | 1 | 08/09/2024 |
| ROBERT GERMAIN JR. PE | 5 | 10/20/2023 |
| JRS CONSULTING | 5 | 09/14/2023 |
| AMERILAND BROOK LLC | 3 | 08/22/2023 |
| SI DESIGN | 1 | 08/03/2023 |
| BGM ENGINEERING | 3 | 09/12/2022 |
| ASHRAF CORP | 1 | 02/06/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| PRAT ENTERPRISES | 10 | 03/21/2026 |
| EAST COAST ENGINEERING P C | 2 | 03/21/2026 |
| LLOYD NOEL BUILDING CONSULTANT | 1 | 03/21/2026 |
| A2ZCM | 6 | 03/21/2026 |
| ADAM BERGMAN CONSTRUCTION AND DEVEL | 10 | 03/21/2026 |
| Rigid Structural Design, LLC | 3 | 03/21/2026 |
| HH BUILDING CONSULTING & ARCHITECTU | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PRAT ENTERPRISES CORP | General Contractor | 12 | 07/08/2026 |
| DYNAMIC DEVELOPMENT AND C | General Contractor | 10 | 07/08/2026 |
| CAPE PLUMBING INC | Plumbing | 4 | 07/08/2026 |
| INTERSYSTEMS INSTAL S&S | General Contractor | 3 | 03/21/2026 |
| LUIS JIMENEZ | Electrical | 1 | 03/21/2026 |
| MARIO CASTRO | Electrical | 1 | 03/21/2026 |
| PRINCIPAL ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| CRYSTAL COMFORT INC | General Contractor | 1 | 07/08/2026 |
| INTERSYSTEM INSTALLATION | General Contractor | 1 | 07/08/2026 |
| NGC GROUP LLC | General Contractor | 1 | 07/08/2026 |
| PROFESSIONAL DOOR CORP | General Contractor | 1 | 07/08/2026 |
| ALTAIR PLUMBING AND HEAT | Plumbing | 1 | 07/08/2026 |
| AURORA ELECL CONTG INC | Electrical | 1 | 03/22/2026 |
| CC CONTROLLED PLBG CO.,IN | Plumbing | 1 | 07/08/2026 |
| CARLO JR, THOMAS | Electrical | 1 | 03/21/2026 |
| JIMENEZ LUIS | Electrical | 1 | 03/21/2026 |
| KRAFT ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| KZ ENGINEERING, P.C. | 4665 | 5 | 06/25/2025 |
| JMV CONSULTING ENGINEERIN | 804 | 1 | 12/17/2024 |
| ROBERT F. GERMAIN JR. PE | 5100 | 5 | 10/20/2023 |
| HRF SERVICES CORP | 5616 | 4 | 09/01/2023 |
| SI DESIGN | 6486 | 1 | 08/03/2023 |
| BGM ENGINEERING, LLC | 1514 | 3 | 09/12/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | PRAT ENTERPRISES CORP | 09/18/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | PRAT ENTERPRISES CORP | 08/26/2025 |
| DOB NOW | Supported Scaffold | Signed-off | PRAT ENTERPRISES CORP | 08/05/2025 |
| DOB NOW | Supported Scaffold | Signed-off | PRAT ENTERPRISES CORP | 05/30/2025 |
| DOB NOW | Mechanical Systems | Signed-off | PROFESSIONAL DOOR CORP | 05/13/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | PRAT ENTERPRISES CORP | 05/09/2025 |
| DOB NOW | Plumbing | Permit Issued | CAPE PLUMBING INC | 04/16/2025 |
| DOB NOW | Plumbing | Permit Issued | CAPE PLUMBING INC | 03/05/2025 |
| DOB NOW | General Construction | Permit Issued | PRAT ENTERPRISES CORP | 09/19/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | PRATT CONSTRUCTION & RES | 09/18/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | PRAT ENTERPRISES CORP | 08/27/2024 |
| DOB NOW | Supported Scaffold | Signed-off | INTERSYSTEMS INSTAL S&S | 08/05/2024 |
| DOB NOW | General Construction | Permit Issued | DYNAMIC DEVELOPMENT AND C | 02/20/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | DYNAMIC DEVELOPMENT AND C | 08/29/2023 |
| DOB NOW | Structural | Permit Issued | DYNAMIC DEVELOPMENT AND C | 08/16/2023 |
| DOB NOW | General Construction | Signed-off | NGC GROUP LLC | 08/10/2023 |
| DOB NOW | Construction Fence | Permit Issued | DYNAMIC DEVELOPMENT AND C | 07/10/2023 |
| DOB NOW | Mechanical Systems | Signed-off | CRYSTAL COMFORT | 03/23/2023 |
| DOB NOW | Plumbing | Signed-off | CC CONTROLLED PLBG CO.,IN | 03/23/2023 |
| DOB NOW | General Construction | Permit Issued | DYNAMIC DEVELOPMENT AND C | 12/28/2022 |
| DOB NOW | Construction Fence | Permit Issued | DYNAMIC DEVELOPMENT AND C | 07/13/2022 |
| DOB NOW | Plumbing | Signed-off | ALTAIR PLUMBING AND HEAT | 02/14/2022 |
| DOB NOW | General Construction | Permit Issued | DYNAMIC DEVELOPMENT AND C | 01/06/2022 |
| DOB NOW | Supported Scaffold | Permit Issued | INTERSYSTEM INSTALLATION | 02/07/2020 |
| BIS | PL | ISSUED | ORBIT PLBG & HTG INC | 01/17/2024 |
| BIS | PL | ISSUED | CC CONTROLLED PLBG CO.,IN | 11/23/2022 |
| BIS | OT | ISSUED | DYNAMIC DEVELOPMENT AND C | 02/23/2021 |
| BIS | OT | ISSUED | UNIK XVIII LLC | 03/29/2017 |
| BIS | OT | ISSUED | SPEECHLESS ENTERPRISES IN | 07/20/2016 |
| BIS | PL | ISSUED | FIVE STAR P&H CO,INC | 07/12/2016 |
| BIS | OT | ISSUED | SJB INTERIORS INC | 07/11/2016 |
| BIS | EQ | ISSUED | INTERSYSTEM S&S CORP | 06/23/2016 |
| BIS | OT | ISSUED | PRATT CONSTRUCTION & REST | 05/24/2016 |
| BIS | OT | ISSUED | PRATT CONSTRUCTION & REST | 01/07/2016 |
| BIS | EQ | ISSUED | INTERSYSTEM S&S CORP | 11/10/2015 |
| BIS | EQ | ISSUED | INTERSYSTEM S&S CORP | 09/23/2015 |
| BIS | PL | ISSUED | A & E MECHANICAL CORP | 07/21/2015 |
| BIS | OT | ISSUED | TROY CONSTRUCTION OF NY INC. | 06/17/2015 |
| BIS | EQ | ISSUED | INTERSYSTEM S&S CORP | 09/23/2014 |
| BIS | PL | ISSUED | ADVANCED PLUMBING MECH | 09/23/2014 |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/30/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/12/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 08/12/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 06/11/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/25/2025 | Pass-Final House Connection | Pass | View ↗ |
| 03/31/2025 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 06/14/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/03/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 02/09/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/29/2023 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 09/20/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/20/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 09/06/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/19/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/19/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/27/2025 | Alternative Materials - OTCR Buildings Bulletin Number | Karol Zdancewicz | special |
| 06/27/2025 | Post-installed Anchors | Karol Zdancewicz | special |
| 06/25/2025 | Post-installed Anchors | Karol Zdancewicz | special |
| 06/25/2025 | Alternative Materials - OTCR Buildings Bulletin Number | Karol Zdancewicz | special |
| 05/12/2025 | Tenant Protection Plan Compliance | — | special |
| 05/09/2025 | Alternative Materials - OTCR Buildings Bulletin Number | Karol Zdancewicz | special |
| 05/09/2025 | Post-installed Anchors | Karol Zdancewicz | special |
| 04/23/2025 | Tenant Protection Plan Compliance | — | special |
| 01/02/2025 | Alternative Materials - OTCR Buildings Bulletin Number | Karol Zdancewicz | special |
| 01/02/2025 | Post-installed Anchors | Karol Zdancewicz | special |
| 12/20/2024 | Post-installed Anchors | Karol Zdancewicz | special |
| 12/20/2024 | Alternative Materials - OTCR Buildings Bulletin Number | Karol Zdancewicz | special |
| 12/17/2024 | Tenant Protection Plan Compliance | — | special |
| 11/27/2024 | Mechanical Systems | Joseph Vuto | special |
| 11/27/2024 | Final | Joseph Vuto | progress |
| 11/27/2024 | Sprinkler Systems | — | special |
| 10/23/2023 | Tenant Protection Plan Compliance | Robert Germain Jr. | special |
| 10/23/2023 | Fire-Resistant Penetrations and Joints | Robert Germain Jr. | special |
| 10/18/2023 | Tenant Protection Plan Compliance | — | special |
| 10/18/2023 | Fire-Resistant Penetrations and Joints | Robert Germain Jr. | special |
| 09/07/2023 | Mechanical Systems | Robert Germain Jr. | special |
| 09/07/2023 | Final | Robert Germain Jr. | progress |
| 09/07/2023 | Tenant Protection Plan Compliance | — | special |
| 09/04/2023 | Mechanical Systems | FAHAD FATEH | special |
| 09/04/2023 | Final | FAHAD FATEH | progress |