Fire Department
116-02 NEWPORT AVENUE
QUEENS · BIN 4304087
💬 Discuss this project
2007Year Built
1Stories
Y1Building Class
R5BZoning
3,700 sfGross Floor Area
1Units
0 Active Violations 2 old, status unconfirmed ▸FDNY Report ↗
Fire Department · Owner of record: NYC Fire Department · 18,985 sf lot · 0.19 FAR built · Flood zone AE
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofPlumbing and sprinkler workUnder Construction113p · 5 filings · 18 docs
BulkheadNew Fire Station constructionUnder Construction2p · 2 filings · 18 docs
Floor 3Plumbing and sprinkler workUnder Construction110p · 4 filings · 18 docs
Floor 2Plumbing and sprinkler workUnder Construction111p · 4 filings · 18 docs
Floor 1The Fire Department of the City of New York (FDNY)Under Construction110p · 7 filings · 18 docs
MezzaninePlumbing and sprinkler workUnder Construction110p · 4 filings · 18 docs
Site & exteriorFDNY Engine Co. 268Under Construction55p · 4 filings · 18 docs
Filed — no permit issuedNew fire station diesel fuel system5p · 1 filing · 3 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Fire Department of the City of New York3310/13/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Dseny Engineering Services403/21/2026
J Callahan Consulting2403/21/2026
Anthony Potestio103/21/2026
Russo Development Enterprises203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Ashnu InternationalGeneral Contractor606/27/2026
Ashnu InternationalScaffold210/04/2026
ACS System AssociatesGeneral Contractor107/08/2026
Russo Development EnterprisesGeneral Contractor104/09/2026
Russo Development EnterprisesScaffold104/09/2026
Civetta MechanicalPlumbing107/23/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Distinct Engineering Solu26411010/12/2026
Age Engineering6695109/09/2025
Building Lifecycle
All (88)Filed (20)Permit Issued (11)Signed Off (1)Violation (8)Inspection (2)Objection (16)Special Inspection (30)
10/12/2026
Filed — Alteration
Mechanical work in conjunction with NB
Q00672444-P2
10/06/2026
Filed — New Building
New FDNY fire station
Q00635508-P1
09/30/2026
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
09/30/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
09/04/2026
Permit issued — Construction Fence
Q01270447-I1-FN
07/22/2026
Permit issued — Plumbing
Q00672339-I1-PL
05/29/2026
Permit issued — Support of Excavation
Q01254426-I1-SE
05/05/2026
Filed — Alteration
Q01254426-I1
04/23/2026
Permit issued — Mechanical Systems
Q00672444-I1-MS
03/20/2026
Permit issued — Foundation
Q00672500-I1-GC-CX
03/13/2026
Permit issued — General Construction
Q00635508-I1-GC
01/06/2026
Permit issued — General Construction
Q00635508-I1-GC
12/19/2025
Signed off — Full Demolition
Q01251586-I1
12/09/2025
Permit issued — Full Demolition
Q01251586-I1-FD
12/04/2025
Special inspection requirement — Subgrade Inspections
YAZAN YANES
12/04/2025
Special inspection requirement — Footing and Foundation
YAZAN YANES
12/04/2025
Special inspection requirement — Final
YAZAN YANES
12/04/2025
Special inspection requirement — Post-installed Anchors
YAZAN YANES
12/04/2025
Special inspection requirement — Structural Steel - Welding
YAZAN YANES
12/04/2025
Special inspection requirement — Concrete - Cast-In-Place
YAZAN YANES
12/04/2025
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
YAZAN YANES
12/04/2025
Special inspection requirement — Structural Steel - Details
YAZAN YANES
12/04/2025
Special inspection requirement — Structural Steel - High Strength Bolting
YAZAN YANES
12/04/2025
Special inspection requirement — Masonry
YAZAN YANES
11/13/2025
Permit issued — General Construction
Q00635508-I1-GC
11/06/2025
Filed — Alteration
Structural and Foundation work in conjunction with NB
Q00672500-P1
11/05/2025
Filed — Alteration
Q01270447-P1
11/05/2025
Special inspection requirement — Masonry
YAZAN YANES
10/30/2025
Special inspection requirement — Footing and Foundation
Ramnarayan Tirumala
10/30/2025
Special inspection requirement — Concrete - Cast-In-Place
YAZAN YANES
10/30/2025
Special inspection requirement — Structural Steel - Details
Ramnarayan Tirumala
10/30/2025
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
YAZAN YANES
10/30/2025
Special inspection requirement — Final
Ramnarayan Tirumala
10/30/2025
Special inspection requirement — Structural Steel - High Strength Bolting
YAZAN YANES
10/30/2025
Special inspection requirement — Structural Steel - Welding
YAZAN YANES
10/30/2025
Special inspection requirement — Subgrade Inspections
YAZAN YANES
10/30/2025
Special inspection requirement — Post-installed Anchors
YAZAN YANES
10/20/2025
Filed — Full Demolition
Q01251586-S1
10/20/2025
Permit issued — Protection and Mechanical Methods
Q01251586-S1-PMM
09/09/2025
Filed — Full Demolition
Q01251586-I1
09/05/2025
Permit issued — Construction Fence
Q01270447-I1-FN
08/15/2025
Filed — Alteration
Q01270447-I1
07/11/2025
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
YAZAN YANES
07/07/2025
Special inspection requirement — Demolition
ROBESPIERRE ARISTILDE
07/07/2025
Special inspection requirement — Structural Stability – Alterations of existing Buildings
ROBESPIERRE ARISTILDE
02/29/2024
Filed — Alteration
Plumbing and sprinkler work in conjunction with NB
Q00672339-P1
10/10/2023
Violation issued (FDNY_NOV, closed)
09/08/2023
Special inspection requirement — HVAC-R and service water heating system controls
Ramnarayan Tirumala
09/08/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
Ramnarayan Tirumala
09/08/2023
Special inspection requirement — Maintenance information
Ramnarayan Tirumala
09/08/2023
Special inspection requirement — Shutoff dampers
Ramnarayan Tirumala
09/08/2023
Special inspection requirement — Ventilation and air distribution system
Ramnarayan Tirumala
09/08/2023
Special inspection requirement — Duct leakage testing, insulation and design
Ramnarayan Tirumala
09/08/2023
Special inspection requirement — Final
Ramnarayan Tirumala
08/30/2023
Objection resolved — Addressed
08/15/2023
Objection raised — Scope
08/04/2023
Objection resolved — Addressed
08/03/2023
Objection resolved — Addressed
03/29/2023
Filed — Alteration
Q00680958-P2
01/05/2023
Objection resolved — Addressed
Latest 60 of 88 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWConstruction FencePermit IssuedAshnu International09/04/2026
DOB NOWPlumbingPermit IssuedCivetta Mechanical07/22/2026
DOB NOWSupport of ExcavationPermit IssuedAshnu International05/29/2026
DOB NOWMechanical SystemsPermit IssuedACS System Associates04/23/2026
DOB NOWFoundationPermit IssuedErnest Kuriqi03/20/2026
DOB NOWGeneral ConstructionPermit IssuedErnest Kuriqi03/13/2026
DOB NOWGeneral ConstructionPermit IssuedErnest Kuriqi01/06/2026
DOB NOWFull DemolitionSigned-offRusso Development Enterprises12/09/2025
DOB NOWGeneral ConstructionPermit IssuedErnest Kuriqi11/13/2025
DOB NOWProtection and Mechanical MethodsSigned-offRusso Development Enterprises10/20/2025
DOB NOWConstruction FencePermit IssuedErnest Kuriqi09/05/2025
1 project · most recent 10/12/2026
Air Conditioning Systems Heating Systems Refrigeration Systems
FiledStatusContractorScopeMake / Model / Capacity
10/12/2026Permit IssuedACS System AssociatesAir Conditioning Systems, Heating Systems, Refrigeration Systems
Cooling
Mitsubishi Electric TURYE1443BN40AN 483,000 BTU · Fan Coil Indoor ×6
Trane OAKE300A3 271,000 BTU ×2
Heating
Sussman EW108 369,000 BTU · Boiler ×4
Refrigeration
Mitsubishi Electric TURYE1443BN40AN 483,000 BTU · Condensing Unit ×6
1 project · most recent 02/29/2024
FiledStatusContractorScope
02/29/2024——402 heads
1 project · most recent 02/29/2024
Gas Storm Water/Sanitary
FiledStatusContractorScope
02/29/2024Permit IssuedCivetta MechanicalGas, Storm, Water/Sanitary
3 projects · most recent 08/11/2025
General Wiring Lighting
FiledStatusContractorScope
08/11/2025Permit IssuedArcadia Elect'l Co1 meters, 1 new_meters
08/11/2025Permit IssuedArcadia Elect'l CoGeneral Wiring, Lighting
06/27/2019CompletePeter J. CatanzaroGeneral Wiring
1 project · most recent 11/06/2025
Steel Concrete
FiledStatusContractorScope
11/06/2025Permit IssuedAshnu InternationalSteel, Concrete
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
09/30/2026Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
09/30/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 41
DateRequirementInspectorRole
12/04/2025Subgrade InspectionsYAZAN YANESspecial
12/04/2025Footing and FoundationYAZAN YANESprogress
12/04/2025FinalYAZAN YANESprogress
12/04/2025Post-installed AnchorsYAZAN YANESspecial
12/04/2025Structural Steel - WeldingYAZAN YANESspecial
12/04/2025Concrete - Cast-In-PlaceYAZAN YANESspecial
12/04/2025Excavations - Sheeting, Shoring, and BracingYAZAN YANESspecial
12/04/2025Structural Steel - DetailsYAZAN YANESspecial
12/04/2025Structural Steel - High Strength BoltingYAZAN YANESspecial
12/04/2025MasonryYAZAN YANESspecial
11/05/2025MasonryYAZAN YANESspecial
10/30/2025Footing and FoundationRamnarayan Tirumalaprogress
10/30/2025Concrete - Cast-In-PlaceYAZAN YANESspecial
10/30/2025Structural Steel - DetailsRamnarayan Tirumalaspecial
10/30/2025Excavations - Sheeting, Shoring, and BracingYAZAN YANESspecial
10/30/2025FinalRamnarayan Tirumalaprogress
10/30/2025Structural Steel - High Strength BoltingYAZAN YANESspecial
10/30/2025Structural Steel - WeldingYAZAN YANESspecial
10/30/2025Subgrade InspectionsYAZAN YANESspecial
10/30/2025Post-installed AnchorsYAZAN YANESspecial
07/11/2025Excavations - Sheeting, Shoring, and BracingYAZAN YANESspecial
07/07/2025DemolitionROBESPIERRE ARISTILDEspecial
07/07/2025Structural Stability – Alterations of existing BuildingsROBESPIERRE ARISTILDEspecial
09/08/2023HVAC-R and service water heating system controlsRamnarayan Tirumalaenergy_progress
09/08/2023HVAC-R and service water piping design and insulationRamnarayan Tirumalaenergy_progress
Latest 25 of 41.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
FDNY Engine Co. 268Government / Civic—
Project Q01270447 Alteration · Permit Entire · 08/15/2025
The Fire Department of the City of New York (FDNY)Government / CivicFloor 1
Project Q00679925 Alteration · Approved · 04/25/2022
Project Q00679997 Alteration · Approved · 04/25/2022
Project Q00680027 Alteration · Approved · 04/25/2022
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 121 on file (BIS + DOB NOW)
▸Plans & Drawings19
▸DOB NOWPlans/Sketch19
08/26/2026Q00680958-P2Request digital key ↗
08/26/2026Q00680958-I1Request digital key ↗
08/26/2026Q00674677-I1Request digital key ↗
Showing 3 of 19 on file for this type
▸Applications & Permits1
▸BISPLAN / WORK APPROVAL APPLICATION1
03/05/2022440705603Open ↗
▸Zoning, Tax Lot & Property Records3
▸DOB NOWZD1: DOB Zoning Diagram2
08/26/2026Q00635508-P1Open ↗
08/13/2026Q00635508-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/26/2026Q00635508-I1Open ↗
▸Seals & Professional Certifications32
▸DOB NOWDPL-1: Design Professional Seal & Signature19
08/26/2026Q00680027-I1Open ↗
08/26/2026Q00635508-I1Open ↗
08/26/2026Q00635508-P1Open ↗
Showing 3 of 19 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature7
09/01/2026Q00672500-P1Open ↗
08/29/2026Q01251586-I1Open ↗
08/29/2026Q01251586-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
09/01/2026Q00672500-P1Open ↗
08/27/2026Q00672500-I1Open ↗
08/27/2026Q00672444-I1Open ↗
Showing 3 of 4 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
03/05/2022440705603Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
03/05/2022440705603Open ↗
▸Trade Schedules & Equipment5
▸DOB NOWElectric Cut-Off1
08/13/2026Q01251586-I1Open ↗
▸DOB NOWWater Cut-Off1
08/13/2026Q01251586-I1Open ↗
▸DOB NOWGas Cut-Off1
08/13/2026Q01251586-I1Open ↗
▸DOB NOWSewer Cut-Off1
08/13/2026Q01251586-I1Open ↗
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)1
08/13/2026Q00635508-I1Open ↗
▸Safety & Tenant Protection5
▸BISSTREET TREE CHECKLIST2
06/13/2022440705603Open ↗
03/05/2022440705603Open ↗
▸DOB NOWStreet Tree Checklist2
08/26/2026Q00635508-I1Open ↗
08/26/2026Q00635508-P1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026Q00635508-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/18/2026Q01251586-I1Open ↗
▸DOB NOWRodent Control1
08/13/2026Q01251586-I1Open ↗
▸Approvals, Objections & Sign-offs38
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter19
08/26/2026Q00680027-I1Open ↗
08/26/2026Q00635508-I1Open ↗
08/26/2026Q00635508-P1Open ↗
Showing 3 of 19 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)16
08/26/2026Q00635508-P1Open ↗
08/26/2026Q00672444-I1Open ↗
08/13/2026Q00680027-I1Open ↗
Showing 3 of 16 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION1
03/05/2022440705603Open ↗
▸BISNEW CC APPROVAL BY DOB1
06/13/2022440705603Open ↗
▸BISDESIGN COMM. APPROVAL: CITY-OWNED PROPERTY (EXTERIOR WORK)1
03/05/2022440705603Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
03/05/2022440705603Open ↗
▸Other Documents15
▸DOB NOWFlood Plan Emergency Temporary Flood Shields6
08/26/2026Q00635508-I1Open ↗
08/26/2026Q00635508-P1Open ↗
08/26/2026Q00672339-P1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/26/2026Q00635508-P1Open ↗
08/13/2026Q00635508-I1Open ↗
▸BISSupporting Document: Fee Exempt1
03/05/2022440705603Open ↗
▸BISRECORDS MGMT FEE PAYMENT RECEIPT1
03/05/2022440705603Open ↗
▸DOB NOWFull Demo: 10-Day Notice1
08/13/2026Q01251586-I1Open ↗
▸DOB NOWStructure Photographs1
08/13/2026Q01251586-I1Open ↗
▸DOB NOWProject Specific General Liability (PGL1)1
08/13/2026Q00635508-I1Open ↗
▸DOB NOWCommunity Board Notification1
08/13/2026Q01251586-I1Open ↗
▸DOB NOWProperty Ownership Certification1
08/18/2026Q01251586-I1Open ↗