| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/17/2025 | — | — | Air Conditioning Systems, Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Daikin CAH006GDGC 2,000 CFM ×2 DAHA11A 2,000 CFM ×2 CAH021GDAM 10,000 CFM · Ahu ×1 CAH032GDCM 12,000 CFM ×1 CAH050GDCC 19,000 CFM ×1 DAHA09A 1,500 CFM · Erv ×1 DAHA19A 3,000 CFM ×1 FCVS104 266 CFM · Fan Coil Indoor ×35 Jetson ACCM030FDD21 1,786,100 BTU · Chiller ×3 Airedale UVV050BBMECBNN266 750 CFM · Fan Coil Indoor ×97 UVV060BBMECBNN266 1,000 CFM · Fan Coil Indoor ×60 UVV030BBMECBNN266 500 CFM · Fan Coil Indoor ×15 UVV040BBMECBNN266 600 CFM · Fan Coil Indoor ×4 Ventilation Greenheck GB-098 350 CFM · Exhaust Fan ×5 GB-097 100 CFM · Exhaust Fan ×4 GB-220 4,000 CFM · Kitchen Exhaust ×3 GB-160 1,370 CFM · Exhaust Fan ×2 CUBE-200 3,600 CFM · Kitchen Exhaust ×1 GB-100 620 CFM · Exhaust Fan ×1 SQ-70-VG 50 CFM · Exhaust Fan ×1 USF-12-F3 1,900 CFM · Exhaust Fan ×1 USF-30-A1 9,000 CFM · Exhaust Fan ×1 USF-30-B4 11,000 CFM · Exhaust Fan ×1 USF-36-B4 13,800 CFM · Exhaust Fan ×1 Cooling Daikin FTKF09AXVJU 11,200 BTU · Fan Coil Indoor ×3 FTXV36AVJU9 34,400 BTU · Fan Coil Indoor ×3 RKF09AXVJU 11,200 BTU · Condensing Unit ×3 RXV36AVJU9 34,400 BTU · Condensing Unit ×3 FTKF24AXVJU 26,400 BTU · Fan Coil Indoor ×2 RKF24AXVJU 2 tons · Condensing Unit ×2 FTXV18AVJU9 22 BTU · Fan Coil Indoor ×1 RXT18AVJU9 21,600 BTU · Vrf Outdoor ×1 |
| 03/01/2024 | Permit Issued | GRIDSPAN CORPORATION | Air Conditioning Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/17/2025 | — | — | Gas, Storm, Water/Sanitary |
| 03/01/2024 | Permit Issued | DH EAGLE PLBG & HTG INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/30/2025 | Permit Issued | A.T.J. ELECTRICAL CO.INC. | General Wiring |
| 08/19/2024 | Complete | CHARAN ELEC'L ENTERP'S IN | — |
| 08/16/2024 | Complete | METROPOLIS ELECTRIC CORP | General Wiring |
| 10/04/2023 | Complete | ACE ELEC'L CONSTRUCTION | General Wiring |
| 07/19/2023 | Permit Issued | C.FALCO ELETL CONT CORP | General Wiring |
| 03/01/2023 | Complete | GEMINI ELECTRIC CO., INC. | — |
| 03/31/2022 | Complete | CHARAN ELEC'L ENTERP'S IN | — |
| 09/24/2021 | Complete | CHARAN ELEC'L ENTERP'S IN | — |
| 06/08/2021 | Complete | INLIGHT ELECTRICAL CORP | General Wiring |
| 03/20/2020 | Complete | CHARAN ELEC'L ENTERP'S IN | — |
| 04/30/2019 | Complete | CHARAN ELEC'L ENTERP'S IN | General Wiring |
| 04/15/2019 | Complete | MK ELECTRIC CONTR'S, INC | General Wiring |
| 10/11/2018 | Permit Issued | ELECTRIC FIXX INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/17/2025 | — | — | Steel, Concrete |
| Owner | Filings | Most Recent |
|---|---|---|
| NYC SCHOOL CONSTRUCTION AUTHORITY | 22 | 07/08/2026 |
| NYC DEPARTMENT OF PARKS AND RECREATION | 1 | 03/22/2026 |
| DEPARTMENT OF EDUCATION | 5 | 03/22/2026 |
| DOE IS 296 040 | 3 | 03/22/2026 |
| DEPARTMENT OF EDUCATION 0 | 4 | 03/22/2026 |
| DOE I.S. 296 | 5 | 03/22/2026 |
| NYC DOE 0 | 1 | 03/22/2026 |
| D.O.E. I.S. 296 0 | 1 | 03/22/2026 |
| JHS 296 DOE | 1 | 03/22/2026 |
| DEPT OF EDUCATION IS 296 | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| GREENMAN-PEDERSEN, INC. | 7 | 10/17/2025 |
| SUSAN G. DOBAN | 1 | 09/08/2025 |
| EME CONSULTING ENGINEERING GROUP | 8 | 03/01/2024 |
| DSENY ENGINEERING SERVICES, PC | 1 | 02/04/2022 |
| ARUP | 2 | 06/14/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| DSENY ENGINEERING SERVICES | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| GRIDSPAN CORPORATION | General Contractor | 12 | 03/21/2026 |
| FRANCIS RICHARDS | Electrical | 6 | 03/21/2026 |
| J-TRACK, LLC | General Contractor | 6 | 03/21/2026 |
| SPIRO SINANIS | Electrical | 5 | 03/21/2026 |
| METROPOLIS ELECTRIC CORP 003482 | General Contractor | 4 | 03/22/2026 |
| WMP PLUMBING LLC | Plumbing | 2 | 07/08/2026 |
| JEFFREY SOCOL | Electrical | 2 | 03/21/2026 |
| CHARAN ELEC'L ENTERP'S IN | Electrical | 2 | 03/22/2026 |
| MAGRIPLES JAMES | Electrical | 1 | 03/21/2026 |
| REMIGIUSZ ZUBER | Electrical | 1 | 03/21/2026 |
| SCHWERDTFEGER, MARCUS | Electrical | 1 | 03/21/2026 |
| ACE ELECL CONSTRUCTION 003978 | General Contractor | 1 | 03/22/2026 |
| DH EAGLE PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| LUPINSKI, MAREK | Electrical | 1 | 03/21/2026 |
| ANDREW DRAZIC | Electrical | 1 | 03/21/2026 |
| CEDOMIR MARA | Electrical | 1 | 03/21/2026 |
| C.FALCO ELETL CONT CORP | Electrical | 1 | 03/22/2026 |
| CHAYUT, ALLEN | Electrical | 1 | 03/21/2026 |
| FLORENTINE ARTISTIC IRON | Electrical | 1 | 03/21/2026 |
| JAMES MAGRIPLES | Electrical | 1 | 03/21/2026 |
| ACE ELEC'L CONSTRUCTION | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| JPC LOGISTICS DBA JPCL EN | 351 | 8 | 03/01/2024 |
| UNIVERSAL TESTING AND INS | 400 | 2 | 06/14/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | GRIDSPAN CORPORATION | 01/10/2024 |
| DOB NOW | General Construction | Permit Issued | GRIDSPAN CORPORATION | 01/10/2024 |
| DOB NOW | Plumbing | Permit Issued | L.SPINA PLUMB & HTG INC | 08/30/2023 |
| DOB NOW | General Construction | Permit Issued | GRIDSPAN CORPORATION | 05/17/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | GRIDSPAN CORPORATION | 05/17/2023 |
| DOB NOW | Construction Fence | Signed-off | J-TRACK, LLC | 02/14/2022 |
| DOB NOW | Plumbing | Signed-off | WMP PLUMBING LLC | 12/30/2021 |
| DOB NOW | Plumbing | Signed-off | WMP PLUMBING LLC | 11/10/2021 |
| DOB NOW | General Construction | Signed-off | J-TRACK, LLC | 10/29/2021 |
| BIS | OT | ISSUED | LIU ELECTRIC LLC | 12/08/2017 |
| BIS | OT | ISSUED | LIU ELECTRIC LLC | 03/17/2017 |
| BIS | OT | ISSUED | KG CONSTRUCTION SERVICES | 05/10/2013 |
| BIS | OT | ISSUED | KG CONSTRUCTION SERVICES | 05/10/2013 |
| BIS | OT | ISSUED | R.A.M.S. MECHANICAL INC | 03/13/2013 |
| BIS | MH | ISSUED | R.A.M.S. MECHANICAL INC | 03/13/2013 |
| BIS | OT | ISSUED | R.A.M.S. MECHANICAL INC | 02/07/2013 |
| BIS | MH | ISSUED | R.A.M.S. MECHANICAL INC | 02/07/2013 |
| BIS | PL | ISSUED | MAR-SAL PLBG & HTG, INC | 09/04/2012 |
| BIS | OT | ISSUED | KG CONSTRUCTION SERVICES | 08/14/2012 |
| BIS | OT | ISSUED | KG CONSTRUCTION SERVICES | 08/14/2012 |
| BIS | OT | ISSUED | R.A.M.S. MECHANICAL INC | 03/20/2012 |
| BIS | MH | ISSUED | R.A.M.S. MECHANICAL INC | 03/20/2012 |
| BIS | OT | ISSUED | R.A.M.S. MECHANICAL INC | 03/05/2012 |
| BIS | MH | ISSUED | R.A.M.S. MECHANICAL INC | 03/05/2012 |
| BIS | OT | ISSUED | R.A.M.S. MECHANICAL INC | 09/22/2011 |
| BIS | MH | ISSUED | R.A.M.S. MECHANICAL INC | 09/22/2011 |
| BIS | PL | ISSUED | LAFATA CORALLO P & H INC | 09/22/2011 |
| BIS | OT | ISSUED | EDISON ELECTRICAL CORPORATION | 11/15/2007 |
| BIS | EQ | ISSUED | EDISON ELECTRICAL CONTRACTORS | 11/14/2007 |
| BIS | OT | ISSUED | VOLMAR SERVICES | 08/15/2006 |
| BIS | EQ | ISSUED | ROCKLEDGE SCAFFOLD CORP | 05/01/2001 |
| BIS | OT | ISSUED | DECENT ENTERPRISES | 08/02/2000 |
| BIS | EQ | ISSUED | SAFWAY STEEL PRODUCTS INC | 07/03/2000 |
| BIS | OT | ISSUED | DECENT ENTERPRISES | 06/23/2000 |
| BIS | EQ | ISSUED | SAFWAY STEEL PRODUCTS | 06/06/2000 |
| BIS | EQ | ISSUED | ROCKLEDGE SCAFFOLD CORP | 11/24/1998 |
| BIS | EQ | ISSUED | M&S MASONRY CONTRACTORS | 01/16/1998 |
| BIS | PL | ISSUED | FRANCO BELLI PLUMBING AND HEATIN | 08/20/1997 |
| BIS | EQ | ISSUED | SHERIDAN INTERNATIONAL ENTERPRIS | 04/05/1994 |
| BIS | OT | ISSUED | SHERIDAN INTERNATIONAL ENTERPRIS | 11/12/1993 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/26/2026 | Subsurface Conditions – Fill Placement & In-Place Density | — | special |
| 11/18/2025 | Fire-Resistance Rated Construction | — | progress |
| 10/15/2025 | Post-installed Anchors | — | special |
| 10/15/2025 | Fire-Resistant Penetrations and Joints | — | special |
| 09/05/2025 | Fire-Resistant Penetrations and Joints | — | special |
| 09/05/2025 | Structural Stability – Alterations of existing buildings | — | special |
| 09/05/2025 | Masonry | — | special |
| 09/05/2025 | Post-installed Anchors | — | special |
| 08/24/2025 | Post-installed Anchors | — | special |
| 08/24/2025 | Fire-Resistant Penetrations and Joints | — | special |
| 08/18/2025 | Structural Stability – Alterations of existing buildings | — | special |
| 08/18/2025 | Structural Steel - High Strength Bolting | — | special |
| 08/18/2025 | Final | — | progress |
| 08/18/2025 | Sprayed fire-resistant materials | — | special |
| 08/18/2025 | Final | — | progress |
| 08/18/2025 | Mechanical Systems | — | special |
| 08/18/2025 | Structural Steel - Welding | — | special |
| 08/18/2025 | Post-installed Anchors | — | special |
| 08/18/2025 | Structural Steel - Details | — | special |
| 04/18/2024 | Post-installed Anchors | Asma Hashmi | special |
| 04/18/2024 | Energy Code Compliance Inspections | Asma Hashmi | progress |
| 04/18/2024 | Final | Asma Hashmi | progress |
| 04/18/2024 | Fire-Resistance Rated Construction | Asma Hashmi | progress |
| 04/18/2024 | Post-installed Anchors | Asma Hashmi | special |
| 04/18/2024 | Mechanical Systems | Asma Hashmi | special |