| Owner | Filings | Most Recent |
|---|---|---|
| MNK ENTERPRISES | 7 | 07/08/2026 |
| HKS CONSTRUCTION | 6 | 07/08/2026 |
| HOME BUILDERS 1LP | 1 | 03/22/2026 |
| HOME BUILDERS 1 L P | 2 | 03/21/2026 |
| MLG 904 DEVELOPMENT | 11 | 03/21/2026 |
| CITY OF NY DEPT OF HPD | 2 | 03/21/2026 |
| MLG 904DEVELOPMENTLLC | 1 | 03/21/2026 |
| HPD | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| P. M. ARCHITECTURE, PC | 3 | 11/22/2022 |
| GREEN DESIGN | 2 | 11/12/2020 |
| HAIDER ENGINEERING, P.E. | 1 | 09/18/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| PM ARCHITECTURE PC | 6 | 03/21/2026 |
| HAIDER ENGINEERING, P.E. | 1 | 03/21/2026 |
| HAIDER ENGINEERING P E | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| M. EARLY PLBG & HTG CORP | Plumbing | 3 | 07/08/2026 |
| MNK ENTERPRISES LLC | General Contractor | 2 | 07/08/2026 |
| TRIBORO ELEC'L CONTR'G CO | Electrical | 1 | 03/22/2026 |
| HKS CONSTRUCTION CORP | General Contractor | 1 | 07/08/2026 |
| HOME BUILDERS 1 L.P | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SKYLINE ENGINEERING, PLLC | 267 | 1 | 08/23/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | HOME BUILDERS 1 L.P | 10/06/2022 |
| DOB NOW | Sprinklers | Signed-off | M. EARLY PLBG & HTG CORP | 09/07/2022 |
| DOB NOW | Sprinklers | Signed-off | M. EARLY PLBG & HTG CORP | 09/05/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | MNK ENTERPRISES LLC | 11/16/2020 |
| DOB NOW | Supported Scaffold | Signed-off | MNK ENTERPRISES LLC | 11/16/2020 |
| DOB NOW | Supported Scaffold | Signed-off | HKS CONSTRUCTION CORP | 09/19/2018 |
| BIS | — | ISSUED | OME BUILDERS 1 L.P. | 04/13/2021 |
| BIS | — | ISSUED | HOME BUILDERS 1 L.P | 07/02/2019 |
| BIS | SP | ISSUED | DDS MECHANICAL FPS CORP | 02/21/2019 |
| BIS | EQ | ISSUED | HOME BUILDERS 1 L.P | 10/12/2018 |
| BIS | — | ISSUED | HOME BUILDERS 1 L.P | 06/20/2018 |
| BIS | — | ISSUED | HOME BUILDERS 1 L.P | 06/13/2018 |
| BIS | — | ISSUED | HOME BUILDERS 1 L.P | 03/09/2018 |
| BIS | SP | ISSUED | DDS MECHANICAL FPS CORP | 03/01/2018 |
| BIS | PL | ISSUED | D.D.S. MECH PBG&HTG CORP | 11/30/2017 |
| BIS | — | ISSUED | HOME BUILDERS 1 L.P | 10/18/2017 |
| BIS | EQ | ISSUED | HOME BUILDERS 1 L.P | 10/16/2017 |
| BIS | EQ | ISSUED | HKS CONSTRUCTION CORP | 09/11/2017 |
| BIS | BL | ISSUED | BALTER-LEHIGH P&H CORP | 11/28/2006 |
| BIS | OT | ISSUED | BJ PIPING & HEATING LLC | 09/18/2006 |
| BIS | PL | ISSUED | MARATHON MECHANICAL LLC | 06/26/2006 |
| BIS | EQ | ISSUED | TRIPLE R INC | 03/14/2000 |
| BIS | EQ | ISSUED | TRIPLE R INC | 11/18/1999 |
| BIS | OT | ISSUED | SKYLARK GENERAL CONTR | 08/20/1999 |
| BIS | OT | ISSUED | ALISONS CONSTRUCTION | 08/09/1999 |
| BIS | EQ | ISSUED | ALISONS CONSTRUCTION | 08/09/1999 |
| BIS | BL | ISSUED | JOHN RAGOUSSIS & SON | 08/09/1996 |
| BIS | OT | ISSUED | SIDHU CONSTR. CO. | 04/10/1996 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/12/2020 | Complete | RICHARD NEU | — |
| 08/22/2019 | Complete | TRIBORO ELEC'L CONTR'G CO | General Wiring |
| 07/22/2019 | Complete | TRIBORO ELEC'L CONTR'G CO | General Wiring |
| 04/27/2018 | Complete | TRIBORO ELEC'L CONTR'G CO | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/22/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/20/2022 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/06/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/03/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/28/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/28/2022 | Certified Sprinkler - SP - Roughing | Certified | View ↗ |
| 09/26/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/01/2022 | Energy Code Compliance Inspections | Matthew Wavro | progress |
| 12/01/2022 | Lighting controls | Matthew Wavro | energy_progress |
| 12/01/2022 | Interior lighting power | Matthew Wavro | energy_progress |
| 11/21/2022 | Energy Code Compliance Inspections | Matthew Wavro | progress |
| 11/21/2022 | Lighting controls | Matthew Wavro | energy_progress |
| 11/21/2022 | Interior lighting power | Matthew Wavro | energy_progress |
| 08/17/2022 | Sprinkler Systems | Matthew Wavro | special |
| 11/12/2020 | Final | BRIAN T. O'CONNOR | progress |
| 09/13/2018 | Final | JAFAR HAIDER | progress |