| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 03/04/2021 | $1.3M | — | — → — | $467/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| BORO ARCHITECTS LLC | 6 | 10/24/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| PERMITWISE | 12 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| GO GREENER PLUMBING LLC | Plumbing | 5 | 07/08/2026 |
| MAC GLOBAL DESIGN & RENOV | General Contractor | 3 | 03/21/2026 |
| DARRIN KRUMPUS | Electrical | 1 | 03/21/2026 |
| LENS ELECTRIC, INC | Electrical | 1 | 03/22/2026 |
| CRESCENT STREET CONSTRUCTION | General Contractor | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ASE ENGINEERING PLLC | 5785 | 6 | 10/24/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | GO GREENER PLUMBING LLC | 09/09/2021 |
| DOB NOW | Structural | Permit Issued | MAC GLOBAL DESIGN & RENOV | 08/18/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/24/2024 | Signed-off | GO GREENER PLUMBING LLC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/16/2021 | Complete | LENS ELECTRIC, INC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/29/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/25/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/14/2022 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/01/2021 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/24/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/12/2021 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 11/04/2021 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/17/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/04/2024 | HVAC-R and service water heating equipment | alon egozi | energy_progress |
| 11/04/2024 | Fenestration air leakage | alon egozi | energy_progress |
| 11/04/2024 | HVAC-R and service water heating system controls | alon egozi | energy_progress |
| 11/04/2024 | Maintenance information | alon egozi | energy_progress |
| 11/04/2024 | Fenestration and door U-factor and product ratings | alon egozi | energy_progress |
| 11/04/2024 | Lighting in dwelling units | alon egozi | energy_progress |
| 11/04/2024 | HVAC-R and service water piping design and insulation | alon egozi | energy_progress |
| 11/04/2024 | Energy Code Compliance Inspections | alon egozi | progress |
| 11/04/2024 | Final | alon egozi | progress |
| 11/04/2024 | Post-installed Anchors | alon egozi | special |
| 11/04/2024 | Structural Stability – Alterations of existing buildings | alon egozi | special |
| 11/04/2024 | Structural Steel - High Strength Bolting | alon egozi | special |
| 11/04/2024 | Fire-Resistant Penetrations and Joints | alon egozi | special |
| 11/04/2024 | Structural Steel - Welding | alon egozi | special |
| 11/04/2024 | Structural Steel - Details | alon egozi | special |
| 11/04/2024 | Mechanical Systems | alon egozi | special |
| 10/24/2024 | HVAC-R and service water piping design and insulation | alon egozi | energy_progress |
| 10/24/2024 | Post-installed Anchors | alon egozi | special |
| 10/24/2024 | Fire-Resistant Penetrations and Joints | alon egozi | special |
| 10/24/2024 | Mechanical Systems | alon egozi | special |
| 10/24/2024 | Structural Stability – Alterations of existing buildings | alon egozi | special |
| 10/24/2024 | Structural Steel - Details | alon egozi | special |
| 10/24/2024 | Structural Steel - High Strength Bolting | alon egozi | special |
| 10/24/2024 | Structural Steel - Welding | alon egozi | special |
| 10/24/2024 | Energy Code Compliance Inspections | alon egozi | progress |