| Owner | Filings | Most Recent |
|---|---|---|
| KAN-DO DEVELOPMENT | 6 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| PARKER AND WEST ENGINEERING, PLLC | 1 | 08/19/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| SUNRUN | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SUNRUN INSTALLATION SVC | General Contractor | 2 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PARKER AND WEST ENGINEERI | 5272 | 1 | 08/19/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | SUNRUN INSTALLATION SVC | 08/21/2024 |
| BIS | PL | ISSUED | ATTACK PLG INC | 10/04/2005 |
| BIS | — | ISSUED | JNB CONSTRUCTION LLC | 09/26/2005 |
| BIS | EQ | ISSUED | JNB CONSTRUCTION LLC | 09/26/2005 |
| BIS | — | ISSUED | JNB CONSTRUCTION LLC | 08/30/2005 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/19/2024 | Complete | SUNRUN SOLAR ELECTL CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/19/2024 | Signed-off | SUNRUN INSTALLATION SVC | 13 panels, 5.33 kw, 274.8 roof_area_sqft |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/15/2024 | Fire-Resistant Penetrations and Joints | Walid Abdulla | special |
| 08/15/2024 | Structural Stability – Alterations of existing buildings | Walid Abdulla | special |
| 08/15/2024 | Energy Code Compliance Inspections | Walid Abdulla | progress |
| 08/15/2024 | Final | Walid Abdulla | progress |
| 08/15/2024 | Air barrier - visual inspection | Walid Abdulla | energy_progress |