1178 STERLING PLACE
BROOKLYN · BIN 3032071
💬 Discuss this project
1907Year Built
2Stories
C0Building Class
R6Zoning
3,032 sfGross Floor Area
3Units
Rent Stabilized14 Open Violations ▸FDNY Report ↗
Three families · 2,491 sf lot · 1.22 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingGeneral
Roof6p · 1 filing · 20 docs
Floor 310p · 1 filing · 20 docs
Floor 23p · 1 filing · 20 docs
Floor 13p · 1 filing · 20 docs
Cellar7p · 1 filing · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
05/03/2022$2.2M—Private party → Private party$726/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CORDERO ARCHITECTURE PLLC701/30/2025
NY BUILDING ASSOCIATES INC106/06/2024
EP ENGINEERING LLC204/04/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
RAMPULLA ASSOCIATES ARCHITECTS1003/21/2026
BROOKLYN SOLARWORKS103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NY PRO ENTERPRISES INCGeneral Contractor507/08/2026
AMOR ELECTRIC CORPElectrical303/22/2026
BROOKLYN SOLARWORKS LLCGeneral Contractor107/08/2026
JUST PLBG & HTG INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ACE STRUCTURAL ENGINEERIN496401/30/2025
EP INSPECTIONS AND COMMIS7079501/30/2025
NKM ENGINEERING PLLC6244106/06/2024
Building Lifecycle
All (145)Filed (10)Permit Issued (6)Signed Off (5)Violation (46)Inspection (6)Objection (42)Special Inspection (30)
05/06/2026
Violation issued (HPD, open)
A
12/09/2025
Signed off — Alteration
Mechanical Modifications to include installation of electric heat, HVAC, and associated HVAC ductwork. No change of use, occupancy, or egress under this application.
B00902518-I1
12/05/2025
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
11/19/2025
Violation issued (HPD, open)
I
11/17/2025
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
09/25/2025
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
08/06/2025
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
06/11/2025
Violation issued (HPD, open)
A
05/27/2025
Permit issued — General Construction
B00902518-I1-GC
03/24/2025
Signed off — Alteration
Mechanical Modifications to include installation of electric heat, HVAC, and associated HVAC ductwork. No change of use, occupancy, or egress under this application.
B00902518-S2
03/24/2025
Signed off — Alteration
Mechanical Modifications to include installation of electric heat, HVAC, and associated HVAC ductwork. No change of use, occupancy, or egress under this application.
B00902518-S1
03/24/2025
Signed off — Alteration
Mechanical Modifications to include installation of electric heat, HVAC, and associated HVAC ductwork. No change of use, occupancy, or egress under this application.
B00902518-S3
03/14/2025
Permit issued — Mechanical Systems
B00902518-S1-MS
02/05/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
ANTHONY UGBEBOR
02/05/2025
Special inspection requirement — Final
ANTHONY UGBEBOR
02/05/2025
Special inspection requirement — Tenant Protection Plan Compliance
Christopher Burgess
02/05/2025
Special inspection requirement — Post-installed Anchors
ANTHONY UGBEBOR
02/05/2025
Special inspection requirement — Mechanical Systems
ANTHONY UGBEBOR
01/30/2025
Filed — Alteration
Mechanical Modifications to include installation of electric heat, HVAC, and associated HVAC ductwork. No change of use, occupancy, or egress under this application.
B00902518-P5
01/16/2025
Signed off — Alteration
INSTALLATION OF SOLAR PV SYSTEM. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
B01055593-I1
11/26/2024
Violation issued (HPD, open)
I
11/06/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
ANTHONY UGBEBOR
11/06/2024
Special inspection requirement — Post-installed Anchors
ANTHONY UGBEBOR
11/05/2024
Objection resolved — Addressed
10/31/2024
Objection raised — Other
10/30/2024
Special inspection requirement — Fire-Resistance Rated Construction
ANTHONY UGBEBOR
10/29/2024
Filed — Alteration
Mechanical Modifications to include installation of electric heat, HVAC, and associated HVAC ductwork. No change of use, occupancy, or egress under this application.
B00902518-P4
10/29/2024
Filed — Alteration
Mechanical Modifications to include installation of electric heat, HVAC, and associated HVAC ductwork. No change of use, occupancy, or egress under this application.
B00902518-P3
10/23/2024
Special inspection requirement — Fire-Resistance Rated Construction
Ian Watchorn
10/23/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Christopher Burgess
10/23/2024
Special inspection requirement — Post-installed Anchors
Christopher Burgess
08/30/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
06/13/2024
Permit issued — Solar
B01055593-I1-SL
06/06/2024
Filed — Alteration
INSTALLATION OF SOLAR PV SYSTEM. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
B01055593-I1
05/22/2024
Special inspection requirement — Air barrier - visual inspection
NARESH MAHANGU
05/22/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
NARESH MAHANGU
05/22/2024
Special inspection requirement — Final
NARESH MAHANGU
05/22/2024
Special inspection requirement — Energy Code Compliance Inspections
NARESH MAHANGU
05/22/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
NARESH MAHANGU
04/25/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
04/11/2024
Violation issued (HPD, open)
A
04/04/2024
Filed — Alteration
Mechanical Modifications to include installation of electric heat, HVAC, and associated HVAC ductwork. No change of use, occupancy, or egress under this application.
B00902518-P2
04/02/2024
Permit issued — Plumbing
B00902518-S2-PL
04/02/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Christopher Burgess
04/02/2024
Special inspection requirement — Mechanical Systems
Christopher Burgess
04/02/2024
Special inspection requirement — Post-installed Anchors
Christopher Burgess
04/02/2024
Special inspection requirement — Tenant Protection Plan Compliance
Christopher Burgess
04/02/2024
Special inspection requirement — Final
Christopher Burgess
02/29/2024
Permit issued — General Construction
B00902518-I1-GC
02/28/2024
Permit issued — Structural
B00902518-S3-ST
12/04/2023
Filed — Alteration
Mechanical Modifications to include installation of electric heat, HVAC, and associated HVAC ductwork. No change of use, occupancy, or egress under this application.
B00902518-P1
12/03/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Christopher Burgess
12/03/2023
Special inspection requirement — Mechanical Systems
Christopher Burgess
12/03/2023
Special inspection requirement — Post-installed Anchors
Christopher Burgess
12/03/2023
Special inspection requirement — Tenant Protection Plan Compliance
Christopher Burgess
12/03/2023
Special inspection requirement — Final
Christopher Burgess
11/20/2023
Violation issued (HPD, open)
I
10/25/2023
Objection resolved — Addressed
10/05/2023
Objection resolved — Addressed
09/29/2023
Objection resolved — Addressed
Latest 60 of 145 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offNY PRO ENTERPRISES INC05/27/2025
DOB NOWMechanical SystemsSigned-offNY PRO ENTERPRISES INC03/14/2025
DOB NOWSolarSigned-offBROOKLYN SOLARWORKS LLC06/13/2024
DOB NOWPlumbingSigned-offMOHAMED ABDELRAZEK04/02/2024
DOB NOWGeneral ConstructionSigned-offNY PRO ENTERPRISES INC02/29/2024
DOB NOWStructuralSigned-offNY PRO ENTERPRISES INC02/28/2024
4 projects · most recent 02/04/2025
General Wiring
FiledStatusContractorScope
02/04/2025CompleteAMOR ELECTRIC CORPGeneral Wiring
02/04/2025CompleteAMOR ELECTRIC CORP4 meters, 1 new_meters
11/13/2024CompleteBROOKYLN SOLARWORKS, LLC—
05/22/2019Permit IssuedTRIPLE T ELECTRIC INC3 meters, 3 new_meters
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
12/05/2025Pass-Final General Construction Non-Directive 14PassView ↗
11/17/2025Fail-Final General Construction Non-Directive 14FailView ↗
09/25/2025Fail-Final General Construction Non-Directive 14FailView ↗
08/06/2025Fail-Final General Construction Non-Directive 14FailView ↗
08/30/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
04/25/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 31
DateRequirementInspectorRole
02/05/2025Fire-Resistant Penetrations and JointsANTHONY UGBEBORspecial
02/05/2025FinalANTHONY UGBEBORprogress
02/05/2025Tenant Protection Plan ComplianceChristopher Burgessspecial
02/05/2025Post-installed AnchorsANTHONY UGBEBORspecial
02/05/2025Mechanical SystemsANTHONY UGBEBORspecial
11/06/2024Fire-Resistant Penetrations and JointsANTHONY UGBEBORspecial
11/06/2024Post-installed AnchorsANTHONY UGBEBORspecial
10/30/2024Fire-Resistance Rated ConstructionANTHONY UGBEBORprogress
10/23/2024Fire-Resistance Rated ConstructionIan Watchornprogress
10/23/2024Fire-Resistant Penetrations and JointsChristopher Burgessspecial
10/23/2024Post-installed AnchorsChristopher Burgessspecial
05/22/2024Air barrier - visual inspectionNARESH MAHANGUenergy_progress
05/22/2024Fire-Resistant Penetrations and JointsNARESH MAHANGUspecial
05/22/2024FinalNARESH MAHANGUprogress
05/22/2024Energy Code Compliance InspectionsNARESH MAHANGUprogress
05/22/2024Structural Stability – Alterations of existing buildingsNARESH MAHANGUspecial
04/02/2024Fire-Resistant Penetrations and JointsChristopher Burgessspecial
04/02/2024Mechanical SystemsChristopher Burgessspecial
04/02/2024Post-installed AnchorsChristopher Burgessspecial
04/02/2024Tenant Protection Plan ComplianceChristopher Burgessspecial
04/02/2024FinalChristopher Burgessprogress
12/03/2023Fire-Resistant Penetrations and JointsChristopher Burgessspecial
12/03/2023Mechanical SystemsChristopher Burgessspecial
12/03/2023Post-installed AnchorsChristopher Burgessspecial
12/03/2023Tenant Protection Plan ComplianceChristopher Burgessspecial
Latest 25 of 31.
▾Documents — 50 on file (BIS + DOB NOW)
▸Plans & Drawings10
▸DOB NOWPlans/Sketch10
08/27/2026B00902518-P5Request digital key ↗
08/27/2026B00902518-P4Request digital key ↗
08/27/2026B00902518-P3Request digital key ↗
Showing 3 of 10 on file for this type
▸Applications & Permits10
▸DOB NOWLPC Approval/Permit10
08/13/2026B00902518-S1Open ↗
08/13/2026B00902518-S3Open ↗
08/13/2026B01055593-I1Open ↗
Showing 3 of 10 on file for this type
▸Seals & Professional Certifications22
▸DOB NOWDPL-1: Design Professional Seal & Signature10
08/27/2026B00902518-P2Open ↗
08/27/2026B00902518-P5Open ↗
08/27/2026B00902518-P4Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWProgress Inspector Seal & Signature6
08/28/2026B01055593-I1Open ↗
08/28/2026B01055593-I1Open ↗
08/26/2026B00902518-S3Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
08/28/2026B01055593-I1Open ↗
08/26/2026B00902518-S3Open ↗
08/23/2026B00902518-P4Open ↗
Showing 3 of 6 on file for this type
▸Environmental & Asbestos5
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form4
08/27/2026B00902518-S3Open ↗
08/27/2026B00902518-S2Open ↗
08/27/2026B00902518-S1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/24/2026B01055593-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026B01055593-I1Open ↗
▸Other Documents2
▸DOB NOWProof of Historic Building2
08/13/2026B00902518-P3Open ↗
08/13/2026B00902518-I1Open ↗