1940Year Built
2Stories
B2Building Class
R4AZoning
1,939 sfGross Floor Area
2Units
Two family frame · 5,000 sf lot · 0.39 FAR built · Flood zone X
Locations of Work
Electrical
Roof3p · 1 filing · 13 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR210/24/2025
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281210/24/2025
Building Lifecycle
All (14)Filed (2)Permit Issued (1)Signed Off (1)Special Inspection (10)
11/06/2025
Signed off — Alteration
Installation of solar panels, rooftop, railed, grid-tied, 16 modules, 6.56 KW
Q01191895-I1
10/24/2025
Filed — Alteration
Installation of solar panels, rooftop, railed, grid-tied, 16 modules, 6.56 KW
Q01191895-P1
10/24/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
10/24/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
10/24/2025
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
10/24/2025
Special inspection requirement — Final
Mina Makar
10/24/2025
Special inspection requirement — Air barrier - visual inspection
Mina Makar
10/24/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
10/24/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
10/24/2025
Special inspection requirement — Final
Mina Makar
10/24/2025
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
10/24/2025
Special inspection requirement — Air barrier - visual inspection
Mina Makar
03/24/2025
Permit issued — Solar
Q01191895-I1-SL
03/11/2025
Filed — Alteration
Installation of solar panels, rooftop, railed, grid-tied, 16 modules, 6.56 KW
Q01191895-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offMOMENTUM SOLAR03/24/2025
2 projects · most recent 05/27/2025
General Wiring
FiledStatusContractorScope
05/27/2025CompleteDNR ELECTRIC INCORPORATEGeneral Wiring
03/07/2025CompleteISLAND ELECTRIC CORP—
▾Special Inspection Requirements (DOB NOW) — 10
DateRequirementInspectorRole
10/24/2025Fire-Resistant Penetrations and JointsMina Makarspecial
10/24/2025Structural Stability – Alterations of existing buildingsMina Makarspecial
10/24/2025Energy Code Compliance InspectionsMina Makarprogress
10/24/2025FinalMina Makarprogress
10/24/2025Air barrier - visual inspectionMina Makarenergy_progress
10/24/2025Structural Stability – Alterations of existing buildingsMina Makarspecial
10/24/2025Fire-Resistant Penetrations and JointsMina Makarspecial
10/24/2025FinalMina Makarprogress
10/24/2025Energy Code Compliance InspectionsMina Makarprogress
10/24/2025Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 13 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/20/2026Q01191895-P1Request digital key ↗
08/20/2026Q01191895-I1Request digital key ↗
▸Seals & Professional Certifications8
▸DOB NOWProgress Inspector Seal & Signature4
09/01/2026Q01191895-I1Open ↗
09/01/2026Q01191895-I1Open ↗
08/22/2026Q01191895-P1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/20/2026Q01191895-P1Open ↗
08/20/2026Q01191895-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/01/2026Q01191895-I1Open ↗
08/22/2026Q01191895-P1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/20/2026Q01191895-P1Open ↗
08/20/2026Q01191895-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01191895-I1Open ↗